Verbund planning 88 MW hydropower plant

By Industrial Info Resources


Protective Relay Training - Basic

Our customized live online or in‑person group training can be delivered to your staff at your location.

  • Live Online
  • 12 hours Instructor-led
  • Group Training Available
Regular Price:
$699
Coupon Price:
$599
Reserve Your Seat Today
A new hydropower plant is planned for the Upper Inn Valley in Austria. Austrian energy providers Verbund AG, TIWAG and Engadiner Kraftwerke AG will unite their strengths and invest about $500 million (350 million euros) in the construction of an 88-megawatt (MW) hydropower plant.

Construction is planned to begin June 2010, with completion set for January 2013. At the moment, the project is in the midst of environmental impact studies — the strictest permitting procedure in Europe. After receiving approvals, the project company Gemeinschaftskraftwerk Inn GmbH will open a tender to select the engineering firm, equipment supplier and subcontractors.

The powerhouse will be constructed between the Austrian villages Prutz and Ried, close to the Inn River. Two 44-MW Francis turbines and generators will be placed in a subterranean shaft. The turbines will be driven by the Inn River, which will be dammed more than 20 kilometers upstream. The pressure tunnel, which will conduct the water to the turbines, will have a diameter of 6.5 meters and will be 130 to 1,200 meters deep. After being used, the water will re-enter the Inn via a subterranean duct.

Gemeinschaftskraftwerk Inn GmbH is a joint venture of Verbund AG (50%), TIWAG (36%) and Engadiner Kraftwerke AG (14%). At the moment TIWAG is conducting the permitting process for the 180-MW Kuehtai II Pumped storage plant. The Verbund subsidiary Verbund-Austrian Hydro Power is also advancing with the company's Reisseck II (430 MW) and Limberg II (480 MW) projects.

Related News

Sudbury Hydro crews aim to reconnect service after storm

Sudbury Microburst Power Outage strains hydro crews after straight-line winds; New Sudbury faces downed power lines, tree damage, and hazardous access as restoration efforts, mutual aid, and safety protocols aim to reconnect customers by weekend.

 

Key Points

A microburst downed lines in New Sudbury, cutting power as crews tackle hazardous access and complex repairs.

✅ Straight-line winds downed poles, trees, and service lines

✅ Crews face backyard access hazards, complex reconnections

✅ Mutual aid linemen, arborists, and crane work speed restoration

 

About 300 Sudbury Hydro customers are still without power Thursday after Monday's powerful microburst storm, part of a series of damaging storms in Ontario seen across the province.

The utility's spokesperson, Wendy Watson, says the power in the affected New Sudbury neighbourhoods should be back on by the weekend, even as Toronto power outages persisted in a recent storm.

The storm, which Environment Canada said was classified as a microburst or straight line wind damage, similar to a severe windstorm in Quebec, downed a number of power lines in the city.

Now crews are struggling with access to the lines, a challenge that BC Hydro's atypical storm response also highlighted, as they work to reconnect service in the area.

"In some cases, you can't get to someone's back yard, or you have to go through the neighbour's yard," Watson said.

"We have one case where [we had] equipment working over a swimming pool. It's dicey, it's really dirty and it's dangerous."

Monday's storm caused massive property damage across the city, particularly in New Sudbury. (Benjamin Aubé/CBC)

Veteran arborist Jim Allsop told CBC News he hasn't seen damage like this in his 30-plus years in the business.

"I don't know how many we've done up to date, but I have another 35 trees on houses," Allsop said. "We'll be probably another week."

"We've rented a crane to help speed up the process, and increase safety, and we're getting five or six done in our 12-hour days."

Scott Aultman, a lineman with North Bay Hydro, said he has seen a few storms in his career, and isn't usually surprised by extensive damage a storm can cause.

"When you see a trailer on its side, you know, you don't see that every day," Aultman said.

But during the clean up, Aultman said the spirit of camaraderie runs high with crews from different areas, as seen when Canadian crews helped Florida during Hurricane Irma.

"We were pumped. It's part of the trade, everybody gets together," Aultman said. "We had a big storm in 2006 and the Sudbury guys were up helping us, so it's great, it's nice to be able to return the favour and help them out."

 

Related News

View more

In North Carolina, unpaid electric and water bills are driving families and cities to the financial brink

North Carolina Utility Arrears Crisis strains households and municipal budgets as COVID-19 cuts jobs; unpaid utility bills mount, shutoffs loom, and emergency aid, unemployment benefits, and CARES Act relief lag behind rising arrears across cities.

 

Key Points

A COVID-19 driven spike in unpaid utility bills, threatening households and municipal budgets as federal aid lapses.

✅ 1 million families behind on power, water, sewage bills

✅ $218M arrears accrued April to June, double last year

✅ Municipal utilities face shutoffs, budget shortfalls

 

As many as 1 million families in North Carolina have fallen behind on their electric, water and sewage bills, a sign of energy insecurity threatening residents and their cities with severe financial hardship unless federal lawmakers act to approve more emergency aid.

The trouble stems from the widespread economic havoc wrought by the coronavirus, which has left millions of workers out of a job and struggling to cover their monthly costs as some states moved to suspend utility shut-offs to provide relief. Together, they’ve been late or missed a total of $218 million in utility payments between April 1 and the end of June, according to data released recently by the state, nearly double the amount in arrears at this time last year.

In some cases, cities that own or operate their own utilities have been forced to absorb these losses, as some utilities reconnected customers to prevent harm, creating a dire situation in which the government’s attempt to save people from the financial brink instead has pushed municipal coffers to their own breaking point.

In Elizabeth City, N.C., for example, about 2,500 residents haven’t paid their electric bills on time, according to Richard Olson, the city manager. The late payments at one point proved so problematic that Olson said he calculated Elizabeth City wouldn’t have enough money to pay for its expenses in July. In response, city leaders requested and obtained a waiver from a statewide order, similar to New York’s disconnection moratorium, issued in March, that protects people from being penalized for their past-due utility bills.

The predicament has presented unique budget challenges throughout North Carolina, while illustrating the consequences of a cash crunch plaguing the entire country, where proposals such as a Texas electricity market bailout surfaced following severe grid stress. State and federal leaders have extended a range of coronavirus relief programs since March to try to help people through the pandemic. But the money is limited and restricted — and it’s not clear whether more help from Congress is on the way — creating a crisis in which the nation’s economic woes are outpacing some of the aid programs adopted to combat them.

“We are entering a phase where the utilities [may] be able to shut off power, but what was propping up people’s economic lives, the unemployment benefits and Cares Act support, won’t be there,” said Paul Meyer, the executive director of the North Carolina League of Municipalities.

White House, GOP in disarray over coronavirus spending plan as deadline nears on expiring emergency aid

The future of that safety-net support — and other federal aid — hangs in the balance as lawmakers returned to work this week in their final sprint ahead of the August recess. The White House and congressional leaders are split over the contours of the next coronavirus relief package, including the need to extend more aid to cities and states as some utilities have waived fees to help customers, and reauthorize an extra $600 in weekly unemployment payments that were approved as part of the Cares Act in March.

Outside Washington, workers, businesses and government officials nationwide have pleaded with federal lawmakers to renew or expand those programs. Last week, Roy Cooper, the Democratic governor of North Carolina, urged Congress to act swiftly and adopt a wide array of new federal spending, including proposals for DOE nuclear cleanup funding, stressing in a letter that the “actions you take in the next few weeks are vital to our ability to emerge from this crisis. ”

 

Related News

View more

Clocks are running slow across Europe because of an argument over who pays the electricity bill

European Grid Frequency Clock Slowdown has made appliance clocks run minutes behind as AC frequency drifts on the 50 Hz electricity grid, driven by a Kosovo-Serbia billing dispute and ENTSO-E monitored supply-demand imbalance.

 

Key Points

An EU-wide timing error where 50 Hz AC deviations slow appliance clocks due to Kosovo-Serbia grid imbalances.

✅ Clocks drifted up to six minutes across interconnected Europe

✅ Cause: unpaid power in N. Kosovo, contested by Serbia

✅ ENTSO-E reported 50 Hz deviations from supply-demand mismatch

 

Over the past couple of months, Europeans have noticed time slipping away from them. It’s not just their imaginations: all across the continent, clocks built into home appliances like ovens, microwaves, and coffee makers have been running up to six minutes slow. The unlikely cause? A dispute between Kosovo and Serbia over who pays the electricity bill.

To make sense of all this, you need to know that the clocks in many household devices use the frequency of electricity to keep time. Electric power is delivered to our homes in the form of an alternating current, where the direction of the flow of electricity switches back and forth many times a second. (How this system came to be established is complex, but the advantage is that it allows electricity to be transmitted efficiently.) In Europe, this frequency is 50 Hertz — meaning a current alternating of 50 times a second. In America, it’s 60 Hz, and during peak summer demand utilities often prepare for blackouts as heat drives loads higher.

Since the 1930s, manufacturers have taken advantage of this feature to keep time. Each clock needs a metronome — something with a consistent rhythm that helps space out each second — and an alternating current provides one, saving the cost of extra components. Customers simply set the time on their oven or microwave once, and the frequency keeps it precise.

At least, that’s the theory. But because this timekeeping method is reliant on electrical frequency, when the frequency changes, so do the clocks. That is what has been happening in Europe.

The news was announced this week by ENTSO-E, the agency that oversees the single, huge electricity grid connecting 25 European countries and which recently synchronized with Ukraine to bolster regional resilience. It said that variations in the frequency of the AC caused by imbalances between supply and demand on the grid have been messing with the clocks. The imbalance is itself caused by a political argument between Serbia and Kosovo. “This is a very sensitive dispute that materializes in the energy issues,” Susanne Nies, a spokesperson for ENTSO-E, told The Verge.

Essentially, after Kosovo declared independence from Serbia in 2008, there were long negotiations over custody of utilities like telecoms and electricity infrastructure. As part of the ongoing agreements (Serbia still does not recognize Kosovo as a sovereign state), four Serb-majority districts in the north of Kosovo stopped paying for electricity. Kosovo initially covered this by charging the rest of the country more, but last December, it decided it had had enough and stopped paying. This led to an imbalance: the Kosovan districts were still using electricity, but no one was paying to put it on the grid.

This might sound weird, but it’s because electricity grids work on a system of supply and demand, where surging consumption has even triggered a Nordic grid blockade in response to constrained flows. As Stewart Larque of the UK’s National Grid explains, you want to keep the same amount of electricity going onto the grid from power stations as the amount being taken off by homes and businesses. “Think of it like driving a car up a hill at a constant speed,” Larque told The Verge. “You need to carefully balance acceleration with gravity.” (The UK itself has not been affected by these variations because it runs its own grid.)

 

“THEY ARE FREE-RIDING ON THE SYSTEM.”

This balancing act is hugely complex and requires constant monitoring of supply and demand and communication between electricity companies across Europe, and growing cyber risks have spurred a renewed focus on protecting the U.S. power grid among operators worldwide. The dispute between Kosovo and Serbia, though, has put this system out of whack, as the two governments have been refusing to acknowledge what the other is doing.

“The Serbians [in Kosovo] have, according to our sources, not been paying for their electricity. So they are free-riding on the system,” says Nies.

The dispute came to a temporary resolution on Tuesday, when the Kosovan government stepped up to the plate and agreed to pay a fee of €1 million for the electricity used by the Serb-majority municipalities. “It is a temporary decision but as such saves our network functionality,” said Kosovo’s prime minister Ramush Haradinaj. In the longer term, though, a new agreement will need to be reached.

There have been rumors that the increase in demand from northern Kosovo was caused by cryptocurrency miners moving into the area to take advantage of the free electricity. But according to ENTSO-E, this is not the case. “It is absolutely unrelated to cryptocurrency,” Nies told The Verge. “There’s a lot of speculation about this, and it’s absolutely unrelated.” Representatives of Serbia’s power operator, EMS, refused to answer questions on this.

For now, “Kosovo is in balance again,” says Nies. “They are producing enough [electricity] to supply the population. The next step is to take the system back to normal, which will take several weeks.” In other words, time will return to normal for Europeans — if they remember to change their clocks, even as the U.S. power grid sees more blackouts than other developed nations.

 

Related News

View more

Site C mega dam billions over budget but will go ahead: B.C. premier

Site C Dam Update outlines hydroelectric budget overruns, geotechnical risks, COVID-19 construction delays, BC Hydro timelines, cancellation costs, and First Nations treaty rights concerns affecting renewable energy, ratepayers, and Peace Valley impacts.

 

Key Points

Overview of Site C costs, delays, geotechnical risks, and concerns shaping BC Hydro hydroelectric plans.

✅ Cost to cancel estimated at least $10B

✅ Final budget now about $16B; completion pushed to 2025

✅ COVID-19 and geotechnical risks drove delays and redesigns

 

The cost to cancel a massive B.C. energy development project would be at least $10 billion, provincial officials revealed in an update on the future of Site C.

Thus the project will go ahead, Premier John Horgan and Energy Minister Bruce Ralston announced Friday, but with an increased budget and timeline.

Horgan and Ralston spoke at a news conference in Victoria about the findings of a status report into the hydroelectric dam project in northeastern B.C.

Peter Milburn, former deputy finance minister, finished the report earlier this year, but the findings were not initially made public.

$10B more than initial estimate
On Friday, it was announced that the project's final price tag has once again ballooned by billions of dollars.

Site C was initially estimated to cost $6 billion, and the first approved budget, back in 2014, was $8.775 billion. The budget increased to $10.8 billion in 2018.

But the latest update suggests it will cost about $16 billion in total.

And, in addition to a higher budget, the date of completion has been pushed back to 2025 – a year later than the initial target.

Among the reasons for the revisions, according to the province, is the impact of COVID-19. While officials did not get into details, there have been multiple cases of the disease publicly reported at Site C work camps.

Additionally, fewer workers were permitted on site to allow for physical distancing, and construction was scaled back.

Also cited as a cause for the increased cost were "unforeseeable" geotechnical issues at the site, which required installation of an enhanced drainage system.

Speaking to reporters Friday, the premier deflected blame.

“Managing the contract the BC Liberals signed has been difficult because it transfers the vast majority of the geotechnical risk back to BC Hydro,” said Horgan.

Former Premier Christy Clark vowed to get the project to a point of no return, and in 2017 the NDP decided to continue with the project because of the cost of cancelling it.

The Liberals now say the clean energy project should continue, but deny they shoulder any of the blame.

“Someone has to take ownership – and it's got to be government in power,” said MLA Tom Shypitka, BC Liberal critic for energy. 

There are also several reviews underway, including how to change contractor schedules to reflect delays and potential cost impacts from COVID-19, and how to keep the work environment safe during the pandemic.

A total of 17 recommendations were made in Milburn's report, all of which have been accepted by BC Hydro and the province.

Among these recommendations is a restructured project assurance board with a focus on skill-specific membership and autonomy from BC Hydro.

Cost of cancelling the project
The report looked into whether it would be better to scrap the project altogether, but the cost of cancelling it at this point would be at least $10 billion, Horgan and Ralston said.

That cost does not include replacing lost energy and capacity that Site C's electricity would have provided, according to the province.

A study conducted in 2019 suggested B.C. will need to double its electricity production by 2055, especially as drought conditions are forcing BC Hydro to adapt power generation. 

The NDP government says the cost to ratepayers of cancelling the project would be $216 a year for 10 years. Going forward will still have a cost, but instead, that payment will be split over more than 70 years, the estimated lifetime of Site C, meaning BC Hydro customers will pay about $36 more a year once the site goes live, the NDP says, even as cryptocurrency mining raises questions about electricity use.

“We will not put jobs at risk; we will not shock people's hydro bills,” said Horgan.

"Our government has taken this situation very seriously, and with the advice of independent experts guiding us, I am confident in the path forward for Site C," Ralston said.

"B.C. needs more renewable energy to bridge the electricity gap with Alberta and electrify our economy, transition away from fossil fuels and meet our climate targets."

The minister said the site is currently employing about 4,500 people.

Arguments against Site C
While there are benefits to the project, there has also been vocal opposition.

In a statement released following the announcement that the project would go ahead, the Union of B.C. Indian Chiefs suggested the decision violated the premier's commitment to a UN declaration.

"The Site C dam has never had the free, prior and informed consent of all impacted First Nations, and proceeding with the project is a clear infringement of the treaty rights of the West Moberly First Nation," the UBCIC's secretary treasurer said.

Kukpi7 Judy Wilson said the UN's Committee on the Elimination of Racial Discrimination has called for a suspension of the project until it has the consent of Indigenous peoples.

"B.C. did not even attempt to engage First Nations about the safety risks associated with the stability of the dam in the recent reviews," she said.

"It is unfathomable that such clear human rights violations are somehow OK by this government."

Chief Roland Wilson of the West Moberly First Nation said he was disappointed the province didn’t consult his and other communities prior to making this announcement. In an interview with CTV News, he said he was offered an opportunity to join a call this morning.

“We signed a treaty in 1814,” he said. “Our treaty rights are being trampled on.”

Wilson said his nation has ongoing concerns about safety issues and the plans to flood the Peace Valley. West Moberly is in a bitter court battle with the province.

At the BC Legislature, Green Party Leader Sonia Furstenau slammed the government’s decision.

“It is an astonishingly terrible business case in any circumstances, but considering that we lose the agricultural land, the biodiversity, the traditional treaty lands of Treaty 8, this is particularly catastrophic,” she told reporters.

She went on to accuse the NDP government of keeping bad news from the public. She alleged the NDP knew of serious problems before last fall’s unscheduled election, but chose not to release information.

Prior to the decision former BC Hydro president and a former federal fisheries minister are among those who added their voices to calls to halt work on the dam.

They were among 18 Canadians who wrote an open letter to the province calling for an independent team of experts to explore geotechnical problems at the site.

In the letter, signed in September, the group that also included Grand Chief Stewart Phillip of the UBCIC wrote that going ahead would be a "costly and potentially catastrophic mistake." 

According to Friday's update, independent experts have confirmed the site is safe, though improvements have been recommended to enhance oversight and risk management.

Earlier in the project, a B.C. First Nation claimed it was a $1-billion treaty violation, though an agreement was reached in 2020 after the province promised to improve land management and restore traditional place names in areas of cultural significance.

The Prophet River First Nation will also receive payments while the site is operating, and some Crown land will be transferred to the nation as part of the agreement. 

Additionally, residents of a tiny community not far from the site is suing the province over two slow-moving landslides they claim caused property values to plummet.

Nearly three dozen residents of Old Fort are behind the allegations of negligence and breach of their charter right to security of person. The claim is tied to two landslides, in 2018 and 2020, that the group alleges were caused by ground destabilization from construction related to Site C.

One of the landslides damaged the only road into the community, leaving residents under evacuation for a month.

 

Related News

View more

Australia to head huge electricity and internet project in PNG

Australia-PNG Infrastructure Rollout delivers electricity and broadband expansion across PNG, backed by New Zealand, the US, Japan, and South Korea, enhancing telecom capacity, digital connectivity, and regional development ahead of the APEC summit.

 

Key Points

A multi-billion-dollar plan to expand power and broadband in PNG, covering 70% of users with allied support.

✅ Delivers internet to 70% of PNG households and communities

✅ Expands electricity grid, boosting reliability and access

✅ Backed by NZ, US, Japan, and S. Korea; complements APEC investments

 

Australia will lead a new multi-billion-dollar electricity and internet rollout in Papua New Guinea, with the PM rules out taxpayer-funded power plants stance underscoring its approach to energy policy.

The Australian newspaper reported New Zealand, the US, Japan, whose utilities' offshore wind deal in the UK signaled expanding energy interests, and South Korea are supporting the project, which will be PNG's largest ever development investment.

The project will deliver internet to 70 percent of PNG and improve access to power, even as clean energy investment in developing nations has slipped sharply, according to a recent report.

Both China and the US are also expected to announce new investments in the region at the APEC summit this week, and recent China-Cambodia nuclear energy cooperation underscores those energy ties.

Beijing will announce new mining and energy investments in PNG, echoing projects such as the Chinese-built electricity poles plant in South Sudan, and two Confucius Insitutes to be housed at PNG universities.

 

Related News

View more

Poland’s largest power group opts to back wind over nuclear

Poland Offshore Wind Energy accelerates as PGE exits nuclear leadership, PKN Orlen steps in, and Baltic Sea projects expand to cut coal reliance, meet EU emissions goals, attract investors, and bridge the power capacity gap.

 

Key Points

A shift from coal and nuclear to Baltic offshore wind to add capacity, cut EU emissions, and attract investment.

✅ PGE drops lead in nuclear; pivots $10bn to offshore wind.

✅ PKN Orlen may assume nuclear role; projects await approval.

✅ 6 GW offshore could add 60b zlotys and 77k jobs by 2030.

 

PGE, Poland’s biggest power group has decided to abandon a role in building the country’s first nuclear power plant and will instead focus investment on offshore wind energy.

Reuters reports state-run refiner PKN Orlen (PKN.WA) could take on PGE’s role, while the latter announces a $10bn offshore wind power project.

Both moves into renewables and nuclear represent a major change in Polish energy policy, diversifying away from the country’s traditional coal-fired power base, as regional efforts like the North Sea wind farms initiative expand, in a bid to fill an electricity shortfall and meet EU emission standards.

An unnamed source told the news agency, PGE could not fund both projects and cheap technology had swung the decision in favour of wind, with offshore wind competing with gas in some markets. PGE could still play a smaller role in the nuclear project which has been delayed and still needs government approval.

#google#

A proposed law is currently before the Polish parliament aiming at facilitating easy construction of wind turbines, mindful of Germany’s grid expansion challenges that have hindered rollout.

If the law is passed, as expected, several other wind farm projects could also proceed.

Polenergia has said it would like to build a wind farm in the Baltic by 2022. PKN Orlen is also considering building one.

PGE said in March that it wants to build offshore windfarms with a capacity of 2.5 gigawatts (GW) by 2030.

Analysts and investors say that offshore wind farms are the easiest and fastest way for Poland to fill the expected capacity gap from coal, with examples like the largest UK offshore wind farm coming online underscoring momentum, and reduce CO2 emissions in line with EU’s 2030 targets as Poland seeks improved ties with Brussels.

The decision to open up the offshore power industry could also draw in investors, as shown by Japanese utilities’ UK offshore investment attracting cross-border capital. Statoil said in April it would join Polenergia’s offshore project which has drawn interest from other international wind companies. “

The Polish Wind Energy Association (PWEA) estimates that offshore windfarms with a total capacity of 6 GW would help create around 77,000 new jobs and add around 60 billion zlotys to economic growth.

 

Related News

View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Download the 2025 Electrical Training Catalog

Explore 50+ live, expert-led electrical training courses –

  • Interactive
  • Flexible
  • CEU-cerified