Korean CANDU refurbishment achieves milestone

WOLSONG, SOUTH KOREA - Atomic Energy of Canada Limited AECL has reached an important milestone with the first successful completion in Wolsong, South Korea, of the removal and replacement of calandria tubes, pressure tubes and end fittings in a CANDU 6 nuclear reactor.

"This success marks the first time a CANDU 6 reactor has had all of the fuel channels removed and replaced," says Hugh MacDiarmid, AECL's President and CEO, "bringing us one step closer to completing the project and allowing the Wolsong reactor to continue building on its excellent operating performance record for another 30 years."

AECL developed hundreds of specialized tools and systems for this first-of-a-kind groundbreaking work. The tools' robotically driven movements are intricate and precise, and designed to be used in a radioactive environment.

AECL began work on the South Korean reactor in June 2009 to replace all 380 calandria tubes. Each calandria tube is approximately six metres long by 13 centimetres in diameter. Made of zirconium-alloy, the tubes house the reactor's 380 fuel channels. The fuel channels connect to end fittings on each fuel channel assembly to circulate heavy water coolant between the reactor and steam generators.

"We have 170 Canadian employees working in Korea on the Wolsong project, and they are focused on successfully completing their work in a safe, professional, quality manner," said Ramzi Fawaz, AECL Senior Vice-President of Operations. "Their experience gained at Wolsong will serve us well in delivering our current and future refurbishment projects."

The next stage of work at Wolsong is to remove the multi-tonne tooling systems and the work platforms supporting them before feeder installation begins. This will be managed jointly by AECL and the client, Korea Hydro & Nuclear Power Company Ltd. KHNP. The reactor is now on track to return to service for Korea's summer peak demand next year.

Related News

biomass generator

New energy projects seek to lower electricity costs in Southeast Alaska

ANCHORAGE - New projects are under development throughout the region to help reduce energy costs for Southeast Alaska residents. A panel presented some of those during last week’s Southeast Conference annual fall meeting in Ketchikan.

Jodi Mitchell is with Inside Passage Electric Cooperative, which is working on the Gunnuk Creek hydroelectric project for Kake. IPEC is a non-profit, she said, with the goal of reducing electric rates for its members.

The Gunnuk Creek project will be built at an existing dam.

“The benefits for the project will be, of course, renewable energy for Kake. And we estimate it will save about 6.2 million…

READ MORE
The Nalcor Energy Lower Churchill Project Soldiers Pond site

Financial update from N.L energy corp. reflects pandemic's impact

READ MORE

Federal government spends $11.8M for smart grid technology in Sault Ste. Marie

READ MORE

climate change

Charting a path to net zero electricity emissions by the middle of the century

READ MORE

Congressional Democrats

Congressional Democrats push FERC to act on aggregated DERs

READ MORE