$2 billion PATH project in peril
CHARLESTON, WEST VIRGINIA - An application to build a $2 billion power line from West Virginia to Maryland should be dismissed because less expensive alternatives should be considered first, say staff reviewing the project for the West Virginia Public Service Commission.
Developers of the Potomac-Appalachian Transmission Highline, or PATH, say the 765-kilovolt line is needed to meet projected power demand along the East Coast by 2015.
But PSC staff said it was “ludicrous” to continue with the project while changes to the region’s existing power grid are being contemplated. Staff specifically mentioned Virginia-based Dominion’s recent notice to rebuild its 500-kilovolt line from Mt. Storm in West Virginia to the Doubs substation in Maryland. That upgrade and other improvements are estimated to cost $500 million to $600 million.
Another planned project is the Mid-Atlantic Power Pathway in Maryland. The line is to provide power to the Delmarva Peninsula.
Dominion says the Mt. Storm-Doubs line, which was built in 1966, must be rebuilt to maintain service. Developers gave the lineÂ’s current condition as a justification for the PATH project and the separate Trans-Allegheny Interstate Line.
“The rebuild will be a more stable line with 65 percent increased capacity,” PSC staff said it its December 10 filing. The additional capacity “will push the need for the PATH line further out on the horizon,” perhaps to 2020, staff wrote.
PATH is a joint venture of Allegheny Energy Co. and American Electric Power Co. The proposed 275-mile line would run from AEPÂ’s John Amos plant in West Virginia, across three counties in Northern Virginia, to a substation near Kemptown in Frederick County.
At least 250 groups, representing landowners, The Sierra Club, local county commissions and boards of education are opposed to PATHÂ’s construction. Many of them have submitted letters supporting the latest staff filing.
The filing marks the second time PSC staff has recommended the application be dismissed. In October 2009, staff sought to dismiss the application because MarylandÂ’s utility commission had dismissed an application in that state, saying it had been improperly filed.
Instead, the utilities agreed to extend the deadline for when the PSC must make a decision from May 16 to July 28, 2011.
PATH spokeswoman Jeri Matheny said the Dominion line “ties in very well” with the PATH project. Also, once PATH is built the Dominion line can be taken out of service for a rebuild, he said.
Matheny did not have an immediate comment on the staffÂ’s recommendation to dismiss the application, saying a formal response would be filed with the PSC.
Earlier this month PJM Interconnection approved the Mt. Storm-Doubs line, but also reaffirmed its support of the PATH project. PJM manages the electrical grid in a 13-state region.
If the three-member PSC doesnÂ’t dismiss the PATH application, staff is asking that it require developers to submit new testimony regarding the economic and environmental aspects of the project. Staff is also asking that AEP and Allegheny Energy again agree to extend the decision deadline.
Related News
San Diego Gas & Electric Orders Mitsubishi Power Emerald Storage Solution
SAN DIEGO - San Diego Gas & Electric Company (SDG&E), a regulated public utility that provides energy service to 3.7 million people, has awarded Mitsubishi Power an order for a 10 megawatt (MW) / 60 megawatt-hour (MWh) energy storage solution for its Pala-Gomez Creek Energy Storage Project in Pala, California. The battery energy storage system (BESS) will add capacity to help meet high energy demand, support grid reliability and operational flexibility, maximize use of renewable energy, and help prevent outages during peak demand.
The BESS project is Mitsubishi Power’s eighth in California, bringing total capacity to 280 MW / 1,140 MWh…