Partners in the canceled Sutherland Unit 4 power plant are talking about replacing the coal-fired plant with a natural gas-fired unit.

The $1.3 billion power plant was slated to go online in 2013 in Marshalltown to meet the growing power appetites of customers of Alliant Energy, Central Iowa Power Cooperative and Corn Belt Power Cooperative. A group of Iowa municipal utilities was also planning to take a stake in the plant.

The recession has curbed electric demand, reducing the urgency of a new plant in Iowa. Even so, leaving the plantÂ’s 649 megawatts of power-generating capacity out of the future mix leaves a hole in projected demand that must be filled.

“Regulators and politicians have sent a pretty strong message about coal-burning power plants,” Alliant spokesman Ryan Stensland said. “But we’re still going to need more base-load generation.”

Opponents said Sutherland Unit 4 would be overly expensive and would contribute to global climate change. A hybrid plant design that allowed it to get 10 percent of its fuel from renewable biomass did not assuage critics.

One strong option appears to be a combined cycle natural gas baseload power plant, not too different from the $400 million, 550-megawatt Emery Generating Station Alliant built near Mason City in 2004. Combined cycle plants burn natural gas to power a turbine that generates electricity. The plants then recapture the waste heat from that turbine to generate additional electricity from a steam turbine.

Emery is an “intermittent load” plant. It can be activated quickly when power needs dictate, but doesn’t run all of the time like a baseload plant.

The credit rating agency Fitch said that Central Iowa Power Cooperative is working on plans to “either build or buy into a proposed combined cycle gas-fired generation project” to meet the growing energy needs of its members. CIPCO, based in rural Cedar Rapids, generates and transmits power to 12 rural electric cooperatives and 15 municipal systems.

CIPCO spokeswoman Kathe Breheny said CIPCO confirmed the utility is studying such a project, but is also weighing other options.

Alliant is also studying a combined cycle natural gas plant as one option. It would cost much less to build than Sutherland Unit 4, Stensland said, but Alliant is concerned about wild swings in natural gas prices and how they could affect electric customers.

The combined cycle gas plant could also be developed more quickly than a coal-burning plant.

“We haven’t talked specifics about any sites,” Stensland said.

He said the current site of the Sixth Street Generating Station, which was destroyed by the June 2008 flood in Cedar Rapids, hasnÂ’t been ruled out as a possibility.

Related News

San Diego Gas & Electric Orders Mitsubishi Power Emerald Storage Solution

SDG&E Mitsubishi Power Energy Storage adds a 10 MW/60 MWh BESS in Pala, boosting grid…
View more

Ontario energy minister asks for early report exploring a halt to natural gas power generation

Ontario Natural Gas Moratorium gains momentum as IESO weighs energy storage, renewables, and demand management…
View more

Vietnam Redefines Offshore Wind Power Regulations

Vietnam Offshore Wind Regulations expand coastal zones to six nautical miles, remove water depth limits,…
View more

Zero-emission electricity in Canada by 2035 is practical and profitable

Canada 100% Renewable Power by 2035 envisions a decentralized grid built on wind, solar, energy…
View more

Sens. Wyden, Merkley Introduce Bill to Ensure More Wildfire Resilient Power Grid

Wildfire Resilient Power Grid Act proposes DOE grants for utility companies to fund wildfire mitigation,…
View more

Energy Department Announces 20 New Competitors for the American-Made Solar Prize

American-Made Solar Prize Round 3 accelerates DOE-backed solar innovation, empowering entrepreneurs and domestic manufacturing with…
View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Live Online & In-person Group Training

Advantages To Instructor-Led Training – Instructor-Led Course, Customized Training, Multiple Locations, Economical, CEU Credits, Course Discounts.

Request For Quotation

Whether you would prefer Live Online or In-Person instruction, our electrical training courses can be tailored to meet your company's specific requirements and delivered to your employees in one location or at various locations.