Doubts about Brazilian grid linger

By Globe and Mail


NFPA 70e Training

Our customized live online or in‑person group training can be delivered to your staff at your location.

  • Live Online
  • 6 hours Instructor-led
  • Group Training Available
Regular Price:
$199
Coupon Price:
$149
Reserve Your Seat Today
BrazilÂ’s president fended off criticism of his nationÂ’s shaky power grid as officials investigated a blackout that plunged as many as 60 million people into darkness, prompting concerns about the countryÂ’s preparedness to host the 2016 Olympic Games.

Power went out for more than two hours in Rio de Janeiro, Sao Paulo and several other major cities after transmission problems knocked one of the worldÂ’s biggest hydroelectric dams offline. Airport operations were hindered and subways ground to a halt.

A group of muggers took advantage of the darkness to rob people en masse near RioÂ’s Maracana stadium, which will host the OlympicsÂ’ opening and closing ceremonies. But overall, police said, crime did not rise in Rio and fell in Sao Paulo during the outage.

All of neighbouring Paraguay also went dark, but for less than a half hour. A spokesman at Brazil’s Energy Ministry said up to 60 million people — nearly a third of the nation’s population — were affected by the blackout. He spoke on condition of anonymity, as he was not authorized to discuss the matter.

The failure affected more people than the worst U.S. blackout on record: an August 14, 2003 outage caused by power line problems in the Midwest that cut electricity to 50 million people in eight states and Canada.

The Energy Ministry called an emergency meeting, but Justice Minister Tarso Genro minimized the impact, saying Brazil has vastly improved its electrical grid since a series of outages in the 1990s.

“This is a micro-accident among the extraordinary conquests for energy production for Brazil over the last seven years,” Mr. Genro said.

Energy analysts say Brazil has failed to invest enough in transmission lines as demand for power skyrockets amid an extended boom for Latin AmericaÂ’s largest economy.

But President Luiz Inacio Lula da Silva defended his government from criticism that it has not done enough to improve the power grid since he took office in 2003, two years after Brazil suffered shortages and rationing under his predecessor.

“In seven years, we created 30 per cent of all the transmission lines built in the last 130 years,” Mr. Silva said.

Brazilian authorities blamed storms that took down power lines and towers, causing a domino effect that rippled across the region.

Lights twinkled back on along RioÂ’s Copacabana beach, in South AmericaÂ’s largest city of Sao Paulo and in ParaguayÂ’s sleepy capital of Asuncion. But some traffic lights were still out in both Rio and Sao Paulo and traffic officials were expecting drivers to face difficulties the rest of the day, according to local media.

In Rio, Governor Sergio Cabral sent an elite police unit into the streets to help maintain calm in a city known for its crime. The mayor dispatched 300 extra unarmed civil guards to help control traffic.

The city saw a series of robberies around the Maracana football stadium — where the opening and closing ceremonies of the 2016 Olympics will be held, along with the 2014 World Cup final. A police spokesman said a band of roughly a dozen criminals worked the area together, robbing people en masse — a crime phenomenon so routine it is known as a “big sweep.”

A Rio police statement said there was no increase in crime, though it did not give figures. In Sao Paulo, military police said they handled fewer incidents than usual.

Questions remained about what happened and what the fallout would be in Brazil, a nation seen as an ascending economic and political power.

“The image of Brazil, of Rio, is bad enough with all the violence,” said 35-year-old graphic designer Paulo Viera, as he sat in a restaurant a block from the sandy arc of Copacabana.

Standing in an open-air restaurant where patrons were drinking quickly warming beer, Mr. Viera said he worried about how the outage might look for a city that last month was picked to host the Olympics and will be the showcase city for soccer’s World Cup in 2014. “We don’t need this to happen. I don’t know how it could get worse.”

The blackout comes on the heels of a wave of gang fighting in RioÂ’s slums that led to violence fears ahead of the games.

“It’s sad to see such a beautiful city with such a precarious infrastructure,” 22-year-old law student Igor Fernandes said. “This shouldn’t happen in a city that is going to host the Olympic Games.”

The outage occurred when the huge Itaipu dam straddling the Brazilian-Paraguay border stopped producing 17,000 megawatts of power, Brazilian Mines and Energy Minister Edison Lobao said. His ministry said in a statement that outages hit 18 of the 27 states in this country of more than 190 million people. No power outages happened in Brasilia, the national capital.

Jorge Miguel Samek, the head of Itaipu Binacional, the agency in charge of the dam, said there was a “99 per cent chance the blackout happened because of a storm.”

“There was no problem with generating electricity, but a problem with ‘lightning or a storm that took down some towers’,” he said.

The agency said that despite the fact it never stopped functioning, “there was no possibility of transmitting energy because the transmission lines that connect Itaipu to the Brazilian system were disconnected.”

Mr. Lobao also said the hydro plant at the dam itself was working, but there were problems with the power lines that carry electricity across Brazil. Brazil uses almost all the energy produced by the dam, and Paraguay consumes the rest. About 80 per cent of BrazilÂ’s energy comes from hydroelectric power.

In Paraguay, the national energy agency blamed the blackout on a short-circuit at an electrical station near Sao Paulo, saying that failure shut down the entire power grid supplied by Itaipu. All of Paraguay went dark for about 20 minutes, ABC Color newspaper reported.

It is at least the fourth time since 1985 that Brazil has suffered a massive power outage involving transmission lines from Itaipu.

The worst of those, in 1999, occurred after lightning struck a power substation in Sao Paulo state, plunging 97 million Brazilians into darkness for up to five hours.

The blackouts came two days after CBSÂ’s 60 Minutes news program reported that several past Brazilian power outages were caused by computer hackers. Brazilian officials had played down the report before the latest outages, and Mr. Lobao did not mention it.

The Itaipu dam is the worldÂ’s second biggest hydroelectric producer, supplying 20 per cent of BrazilÂ’s electricity. ChinaÂ’s Three Gorges dam is the largest.

Related News

Britain's energy security bill set to become law

UK Energy Security Bill drives private investment, diversifies from fossil fuels with hydrogen and offshore wind, strengthens an independent system operator, and extends the retail price cap to shield consumers from volatile gas markets.

 

Key Points

A UK plan to reform energy, cut fossil fuel reliance, boost hydrogen and wind, and extend the retail price cap.

✅ Targets £100bn private investment and 480,000 jobs by 2030.

✅ Creates an independent system operator for grid planning.

✅ Extends retail energy price cap; mitigates volatile gas costs.

 

The British government said that plans to bolster the country's energy security, diversify away from fossil fuels amid the Europe energy crisis and protect consumers from spiralling prices are set to become law.

Britain's energy security bill will be introduced to Parliament on Wednesday and includes 26 measures to reform the energy system, including ending the gas-electricity price link, and reduce its dependency on fossil fuels and exposure to volatile gas prices.

Global energy prices have skyrocketed this year, and UK natural gas and electricity have risen sharply, particularly after Russia's invasion of Ukraine which has led to many European countries trying to reduce reliance on Russian pipeline gas and seek cheaper alternatives.

The bill will help drive 100 billion pounds ($119 billion) of private sector investment by 2030 into industries to diversify Britain's energy supply, including hydrogen and offshore wind, which could help lower costs as a 16% decrease in bills in April is anticipated, and create around 480,000 jobs by the end of the decade, the government said.

"We’re going to slash red tape, get investment into the UK, and grab as much global market share as possible in new technologies to make this plan a reality," Business and Energy Secretary Kwasi Kwarteng, amid high winter energy costs, said in a statement.

The bill will establish a new independent system operator to coordinate and plan Britain's energy system, while MPs move to restrict prices for gas and electricity through oversight.

It will also enable the extension of a cap on retail energy prices beyond 2023, with the price cap cost under scrutiny, which limits the amount suppliers can charge for each unit of gas and electricity.

The bill will also enable the secretary of state to prevent potential disruptions to the downstream oil sector due to industrial action or malicious protests, the government added.

 

Related News

View more

Texas Weighs Electricity Market Reforms To Avoid Blackouts

Texas PUC Electricity Market Reforms aim to boost grid reliability, support ERCOT resilience, pay standby generators, require capacity procurement, and mitigate blackout risk, though analysts warn higher consumer bills and winter reserve margin deficits.

 

Key Points

PUC proposals to bolster ERCOT reliability via standby capacity, capacity procurement, and measures to reduce blackout risk.

✅ Pays generators for standby capacity during grid stress

✅ Requires capacity procurement to meet forecast demand

✅ Could raise consumer bills despite reliability gains

 

The Public Utility Commission of Texas is discussing major reforms to the state’s electricity market with the purpose to avoid a repeat of the power failures and blackouts during the February 2021 winter storm, which led to the death of more than 100 people and left over 11 million residents without electricity for days.

The regulator is discussing at a meeting on Thursday around a dozen proposals to make the grid more stable and reliable in case of emergencies. Proposals include paying power generators that are on standby when the grid needs backup, and requiring companies to pre-emptively buy capacity to meet future demand.

It is not clear yet how many and which of the proposals for electricity market reforms PUC will endorse today, while Texans vote on funding to modernize electricity generation later this year.

Analysts and consumer protection bodies warn that the measures will raise the energy bills for consumers, as some electricity market bailout ideas shift costs to ratepayers as well.

“Customers will be paying for more, but will they be getting more reliability?” Michael Jewell, an attorney with Jewell & Associates PLLC who represents clients at PUC proceedings, told Bloomberg.

“This is going to take us further down a path that’s going to increase cost to consumers, we better be darn sure these are the right choices,” Tim Morstad, Associate State Director, AARP Texas, told FOX 4 NEWS.

Last month, a report by the North American Electric Reliability Corp warned that the Texas power grid remained vulnerable to blackouts in case of a repeat of this year’s February Freeze.

Beyond Texas, electricity blackout risks have been identified across the U.S., underscoring the stakes for grid planning.

According to the 2021-2022 Winter Reliability Assessment report, Texas risks a 37-percent reserve margin deficit in case of a harsh winter, with ERCOT moving to procure capacity to address winter concerns, NERC said.

A reserve margin is the reserve of power generation capacity comparative to demand. The expected reserve margin for Texas for this winter, according to NERC, is 41.9 percent. Yet if another cold spell hits the state, it would affect this spare capacity, pushing the margin deeply into negative territory.

 

Related News

View more

Group to create Canadian cyber standards for electricity sector IoT devices

Canadian Industrial IoT Cybersecurity Standards aim to unify device security for utilities, smart grids, SCADA, and OT systems, aligning with NERC CIP, enabling certification, trust marks, compliance testing, and safer energy sector deployments.

 

Key Points

National standards to secure industrial IoT for utilities and grids, enabling certification and NERC CIP alignment.

✅ Aligns with NERC CIP and NIST frameworks for energy sector security

✅ Defines certification, testing tools, and a trusted device repository

✅ Enhances OT, SCADA, and smart grid resilience against cyber threats

 

The Canadian energy sector has been buying Internet-connected sensors for monitoring a range of activities in generating plants, distribution networks facing harsh weather risks and home smart meters for several years. However, so far industrial IoT device makers have been creating their own security standards for devices, leaving energy producers and utilities at their mercy.

The industry hopes to change that by creating national cybersecurity standards for industrial IoT devices, with the goal of improving its ability to predict, prevent, respond to and recover from cyber threats, such as emerging ransomware attacks across the grid.

To help, the federal government today announced an $818,000 grant support a CIO Strategy Council project oversee the setting of standards.

In an interview council executive director Keith Jansa said the money will help a three-year effort that will include holding a set of cross-country meetings with industry, government, academics and interest groups to create the standards, tools to be able to test devices against the standards and the development of product repository of IoT safe devices companies can consult before making purchases.

“The challenge is there are a number of these devices that will be coming online over the next few years,” Jansa said. “IoT devices are designed for convenience and not for security, so how do you ensure that a technology an electricity utility secures is in fact safeguarded against cyber threats? Currently, there is no associated trust mark or certification that gives confidence associated with these devices.”

He also said the council will work with the North American Electric Reliability Corporation (NERC), which sets North American-wide utility safety procedural standards and informs efforts on protecting the power grid across jurisdictions. The industrial IoT standards will be product standards.

According to Robert Wong, vice-president and CIO of Toronto Hydro, all the big provincial utilities are subject to adhering to NERC CIP standards which have requirements for both cyber and physical security. Ontario is different from most provinces in that it has local distribution companies — like Toronto Hydro — which buy electricity in bulk and resell it to customers.  These LDCs don’t own or operate critical infrastructure and therefore don’t have to follow the NERC CIP standards.

Regional reforms, such as regulatory changes in Atlantic Canada, aim to bring greener power options to the grid.

Electricity is considered around the world as one of a country’s critical national infrastructure. Threats to the grid can be used for ransom or by a country for political pressure. Ukraine had its power network knocked offline in 2015 and 2016 by what were believed to be Russian-linked attackers operating against utilities.

All the big provincial utilities operate “critical infrastructure” and are subject to adhering to NERC CIP (critical infrastructure protection) standards, which have requirements for both cyber and physical security, as similar compromises at U.S. electric utilities have highlighted recently.  There are audited on a regular basis for compliance and can face hefty fines if they fail to meet the requirements.  The LDCs in Ontario don’t own or operate “critical infrastructure” and therefore are not required to adopt NERC CIP standards (at least for now).

The CIO Strategy Council is a forum for chief information officers that is helping set standards in a number of areas. In January it announced a partnership with the Internet Society’s Canada Chapter to create standards of practice for IoT security for consumer devices. As part of the federal government’s updated national cybersecurity strategy it is also developing a national cybersecurity standard for small and medium-sized businesses. That strategy would allow SMBs to advertise to customers that they meet minimum security requirements.

“The security of Canadians and our critical infrastructure is paramount,” federal minister of natural resources Seamus O’Regan said in a statement with today’s announcement. “Cyber attacks are becoming more common and dangerous. That’s why we are supporting this innovative project to protect the Canadian electricity sector.”

The announcement was welcomed by Robert Wong, Toronto Hydro’s vice-president and CIO. “Any additional investment towards strengthening the safeguards against cyberattacks to Canada’s critical infrastructure is definitely good news.  From the perspective of the electricity sector, the convergence of IT and OT (operational technology) has been happening for some time now as the traditional electricity grid has been transforming into a Smart Grid with the introduction of smart meters, SCADA systems, electronic sensors and monitors, smart relays, intelligent automated switching capabilities, distributed energy resources, and storage technologies (batteries, flywheels, compressed air, etc.).

“In my experience, many OT device and system manufacturers and vendors are still lagging the traditional IT vendors in incorporating Security by Design philosophies and effective security features into their products.  This, in turn, creates greater risks and challenges for utilities to protecting their critical infrastructures and ensuring a reliable supply of electricity to its customers.”

The Ontario Energy Board, which regulates the industry in the province, has led an initiative for all utilities to adopt the National Institute of Standards and Technology (NIST) Cybersecurity Framework, along with the ES-C2M2 maturity and Privacy By Design models, he noted.  Toronto Hydro has been managing its cybersecurity practice in adherence to these standards, as the city addresses growing electricity needs as well, he said.

“Other jurisdictions, such as Israel, have invested heavily on a national level in developing its cybersecurity capabilities and are seen as global leaders.  I am confident that given the availability of talent, capabilities and resources in Canada (especially around the GTA) if we get strong support and leadership at a federal level we can also emerge as a leader in this area as well.”

 

Related News

View more

Investigation underway to determine cause of Atlanta Airport blackout

Atlanta Airport Power Outage disrupts Hartsfield-Jackson as an underground fire cripples switchgear redundancy, canceling flights during holiday travel; Georgia Power restores electricity overnight while utility crews probe causes and monitor system resilience.

 

Key Points

A major Hartsfield-Jackson blackout from an underground fire; power restored as switchgear redundancy is investigated.

✅ Underground fire near Plane Train tunnel damaged switchgear systems

✅ Over 1,100 flights canceled; holiday travel severely disrupted

✅ Georgia Power restored service; redundancy and root cause under review

 

Power has been restored at the world’s busiest airport after a massive outage Sunday afternoon left planes and passengers stranded for hours, forced airlines to cancel more than 1,100 flights and created a logistical nightmare during the already-busy holiday travel season.

An underground fire caused a complete power outage Sunday afternoon at Hartsfield-Jackson Atlanta International Airport, resulting in thousands of canceled flights at the world's busiest terminal and affecting travelers worldwide.

The massive outage didn’t just leave passengers stranded overnight Sunday, it also affected travelers with flights Monday morning schedules.

According to Paul Bowers, the president and CEO of Georgia Power,  “From our standpoint, we apologize for the inconvenience,” he said. The utility restored power to the airport shortly before midnight.

Utility Crews are monitoring the fixes that restored power and investigating what caused the fire and why it was able to damage redundant systems. Bowers said the fire occurred in a tunnel that runs along the path of the underground Plane Train tunnel near Concourse E.

Sixteen highly trained utility personnel worked in the passageway to reconnect the network.“Our investigation is going through the process of what do we do to ensure we have the redundancy going back at the airport, because right now we are a single source feed,” Bowers said.

“We will have that complete by the end of the week, and then we will turn to what caused the failure of the switchgear.”

Though the cause isn’t yet known, he said foul play is not suspected.“There are two things that could happen,” he said.

“There are inner workings of the switchgear that could create the heat that caused the fire, or the splicing going into that switchgear -- that the cable had a failure on that going into the switch gear.”

When asked if age of the system could have been a failure, Bowers said his company conducts regular inspections.“We constantly inspect,” he said. “We inspect on an annual basis to ensure the reliability of the network, and that redundancy is protection for the airport.”Bowers said he is not familiar with any similar fire or outage at the airport.

“The issue for us is to ensure the reliability is here and that it doesn’t happen again and to ensure that our network is resilient enough to withstand any kind of fire,” he said. He added that Georgia Power will seek to determine what can be done in the future to avoid a similar event, such as those experienced during regional outages in other communities.

 

Related News

View more

First Nuclear Reactors Built in 30 Years Take Shape at Georgia Power Plant

Vogtle Units 3 and 4 are Westinghouse AP1000 nuclear reactors under construction in Waynesboro, Georgia, led by Southern Nuclear, Georgia Power, and Bechtel, adding 2,234 MWe of carbon-free baseload power with DOE loan guarantees.

 

Key Points

Vogtle Units 3 and 4 are AP1000 reactors in Georgia delivering 2,234 MWe of low-carbon baseload electricity.

✅ Each unit: Westinghouse AP1000, 1,117 MWe capacity.

✅ Managed by Southern Nuclear, built by Bechtel.

✅ DOE loan guarantees support financing and risk.

 

Construction is ongoing for two new nuclear reactors, Units 3 and 4, at Georgia Power's Alvin W. Vogtle Electric Generating Plant in Waynesboro, Ga. the first new nuclear reactors to be constructed in the United Stated in 30 years, mirroring a new U.S. reactor startup that will provide electricity to more than 500,000 homes and businesses once operational.

Construction on Unit 3 started in March 2013 with an expected completion date of November 2021. For Unit 4, work began in November 2013 with a targeted delivery date of November 2022. Each unit houses a Westinghouse AP1000 (Advanced Passive) nuclear reactor that can generate about 1,117 megawatts (MWe). The reactor pressure vessels and steam generators are from Doosan, a South Korean firm.

The pouring of concrete was delayed to 2013 due to the United States Nuclear Regulatory Commission issuing a license amendment which permitted the use of higher-strength concrete for the foundations of the reactors, eliminating the need to make additional modifications to reinforcing steel bar.

The work is occurring in the middle of an operational nuclear facility, and the construction area contains many cranes and storage areas for the prefabricated parts being installed. Space also is needed for various trucks making deliveries, especially concrete.

The reactor buildings, circular in shape, are several hundred feet apart from one another and each one has an annex building and a turbine island structure. The estimated total price for the project is expected in the $18.7 billion range. Bechtel Corporation, which built Units 1 and 2, was brought in January 2017 to take over the construction that is being overseen by Southern Nuclear Operating Company (SNOC), which operates the plant.

The project will require the equivalent of 3,375 miles of sidewalk; the towers for Units 3 and 4 are 60 stories high and have two million pound CA modules; the office space for both units is 300,000 sq. ft.; and there are more than 8,000 construction workers over 30 percent being military veterans. The new reactors will create 800 permanent jobs.

Southern Nuclear and Georgia Power took over management of the construction project in 2017 after Westinghouse's Chapter 11 bankruptcy. The plant, built in the late 1980s with Unit 1 becoming operational in 1987 and Unit 2 in 1989, is jointly owned by Georgia Power (45.7 percent), Oglethorpe Power Corporation (30 percent), Municipal Electric Authority of Georgia (22.7 percent) and Dalton Utilities (1.6 percent).

"Significant progress has been made on the construction of Vogtle 3 and 4 since the transition to Southern Nuclear following the Westinghouse bankruptcy," said Paul Bowers, Chairman, President and CEO of Georgia Power. "While there will always be challenges in building the first new nuclear units in this country in more than 30 years, we remain focused on reducing project risk and maintaining the current project momentum in order to provide our customers with a new carbon-free energy source that will put downward pressure on rates for 60 to 80 years."

The Vogtle and Hatch nuclear plants currently provide more than 20 percent of Georgia's annual electricity needs. Vogtle will be the only four-unit nuclear facility in the country. The energy is needed to meet the rising demand for electricity as the state expects to have more than four million new residents by 2030.

The plant's expansion is the largest ongoing construction project in Georgia and one of the largest in the state's history, while comparable refurbishments such as the Bruce reactor overhaul progress in Canada. Last March an agreement was signed to secure approximately $1.67 billion in additional Department of Energy loan guarantees. Georgia Power previously secured loan guarantees of $3.46 billion.

The signing highlighted the placement of the top of the containment vessel for Unit 3, echoing the Hinkley Point C roof lift seen in the U.K., which signified that all modules and large components had been placed inside it. The containment vessel is a high-integrity steel structure that houses critical plant components. The top head is 130 ft. in diameter, 37 ft. tall, and weighs nearly 1.5 million lbs. It is comprised of 58 large plates, welded together with each more than 1.5 in. thick.

"From the very beginning, public and private partners have stood with us," said Southern Company Chairman, President and CEO Tom Fanning. "Everyone involved in the project remains focused on sustaining our momentum."

Bechtel has completed more than 80 percent of the project, and the major milestones for 2019 have been met, aligning with global nuclear milestones reported across the industry, including setting the Unit 4 pressurizer inside the containment vessel last February, which will provide pressure control inside the reactor coolant system. More specialized construction workers, including craft labor, have been hired via the addition of approximately 300 pipefitters and 350 electricians since November 2018. Another 500 to 1,000 craft workers have been more recently brought in.

A key accomplishment occurred last December when 1,300 cu. yds. of concrete were poured inside the Unit 4 containment vessel during a 21-hour operation that involved more than 100 workers and more than 120 truckloads of concrete. In 2018 alone, more than 23,000 cu. yds. of concrete were poured part of the nearly 600,000 cu. yds. placed since construction started, and the installation of more than 16,200 yds. of piping.

Progress also has been solid for Unit 3. Last January the integrated head package (IHP) was set inside the containment vessel. The IHP, weighing 475,000 lbs. and standing 48 ft. tall, combines several separate components in one assembly and allows the rapid removal of the reactor vessel head during a refueling outage. One month earlier, the placement of the third and final ring for containment vessel, and the placement of the fourth and final reactor coolant pump (RCP, 375,000 lbs.), were executed.

"Weighing just under 2 million pounds, approximately 38 feet high and with a diameter of 130 feet, the ring is the fourth of five sections that make up the containment vessel," stated a Georgia Power press release. "The RCPs are mounted to the steam generator and serve a critical part of the reactor coolant system, circulating water from the steam generator to the reactor vessel, allowing sufficient heat transfer for safe plant operation. In the same month, the Unit 3 shield building with additional double-decker panels, was placed.

According to a construction update from Georgia Power, a total of eight six-panel sections have been placed, with each one measuring 20 ft. tall and 114 ft. wide, weighing up to 300,000 lbs. To date, more than half of the shield building panels have been placed for Unit 3. The shield building panels, fabricated in Newport News, Va., provide structural support to the containment cooling water supply and protect the containment vessel, which houses the reactor vessel.

Building the reactors is challenging due to the design, reflecting lessons from advanced reactors now being deployed. Unit 3 will have 157 fuel assemblies, with each being a little over 14 ft. long. They are crucial to fuelling the reactor, and once the initial fueling is completed, nearly one-third of the fuel assemblies will be replaced for each re-fuelling operation. In addition to the Unit 3 containment top, placement crews installed three low-pressure turbine rotors and the generator rotor inside the unit's turbine building.

Last November, major systems testing got underway at Unit 3 as the site continues to transition from construction toward system operations. The Open Vessel Testing will demonstrate how water flows from the key safety systems into the reactor vessel ensuring the paths are not blocked or constricted.

"This is a significant step on our path towards operations," said Glen Chick, Vogtle 3 & 4 construction executive vice president. "[This] will prepare the unit for cold hydro testing and hot functional testing next year both critical tests required ahead of initial fuel load."

It also confirms that the pumps, motors, valves, pipes and other components function as designed, a reminder of how issues like the South Carolina plant leak can disrupt operations when systems falter.

"It follows the Integrated Flush process, which began in August, to push water through system piping and mechanical components that feed into the Unit 3 reactor vessel and reactor coolant loops for the first time," stated a press release. "Significant progress continues ... including the placement of the final reinforced concrete portion of the Unit 4 shield building. The 148-cubic yard placement took eight hours to complete and, once cured, allows for the placement of the first course of double-decker panels. Also, the upper inner casing for the Unit 3 high-pressure turbine has been placed, signifying the completion of the centerline alignment, which will mean minimal vibration and less stress on the rotors during operations, resulting in more efficient power generation."

The turbine rotors, each weighing approximately 200 tons and rotating at 1,800 revolutions per-minute, pass steam through the turbine blades to power the generator.

The placement of the middle containment vessel ring for Unit 4 was completed in early July. This required several cranes to work in tandem as the 51-ft. tall ring weighed 2.4 million lbs. and had dozens of individual steel plates that were fabricated on site.

A key part of the construction progress was made in late July with the order of the first nuclear fuel load for Unit 3, which consists of 157 fuel assemblies with each measuring 14 ft. tall.

On May 7, Unit 3 was energized (permanently powered), which was essential to perform the testing for the unit. Prior to this, the plant equipment had been running on temporary construction power.

"[This] is a major first step in transitioning the project from construction toward system operations," Chick said.

Construction of the north side of the Unit 3 Auxiliary Building (AB) has progressed with both the floor and roof modules being set. Substantial work also occurred on the steel and concrete that forms the remaining walls and the north AB roof at elevation.

 

Related News

View more

BC announces grid development, job creation

BC Hydro Power Pathway accelerates electrification with clean energy investments, new transmission lines, upgraded substations, and renewable projects like wind and solar, strengthening the grid, supporting decarbonization, and creating jobs across British Columbia's growing economy.

 

Key Points

A $36B, 10-year BC Hydro plan to expand clean power infrastructure, accelerate electrification, and support jobs.

✅ $36B for new lines, substations, dam upgrades, and distribution

✅ Supports 10,500-12,500 jobs per year across B.C.

✅ Adds wind and solar, leveraging hydro to balance renewables

 

BC Hydro is gearing up for a decade of extensive construction to enhance British Columbia's electrical system, supporting a burgeoning clean economy and community growth while generating new employment opportunities.

Premier David Eby emphasized the necessity of expanding the electrical system for industrial growth, residential needs, and future advancements. He highlighted the role of clean, affordable energy in reducing pollution, securing well-paying jobs, and fostering economic growth.

At the B.C. Natural Resources Forum in Prince George, Premier Eby unveiled a $36-billion investment plan for infrastructure projects in communities and regions and green energy solutions to provide clean, affordable electricity for future generations.

The Power Pathway: Building BC’s Energy Future, BC Hydro’s revised 10-year capital plan, involves nearly $36 billion in investments across the province from 2024-25 to 2033-34. This marks a 50% increase from the previous plan of $24 billion and includes a substantial rise in electrification and emissions-reduction projects (nearly $10 billion, up from $1 billion).

These upcoming construction projects are expected to support approximately 10,500 to 12,500 jobs annually. The plan is set to bolster and sustain BC Hydro’s capital investments as significant projects like Site C are near completion.

The plan addresses the increasing demand for electricity due to population and housing growth, industrial development, such as a major hydrogen project, and the transition from fossil fuels to clean electricity. Key projects include constructing new high-voltage transmission lines from Prince George to Terrace, building or expanding substations in high-growth areas, and upgrading dams and generating facilities for enhanced safety and efficiency.

Minister of Energy, Mines, and Low Carbon Innovation Josie Osborne stated that this plan aims to build a clean energy future and support EV charging expansion while creating construction jobs. With BC Hydro’s capital plan allocating almost $4 billion annually for the next decade, it will drive economic growth and ensure access to clean, affordable electricity.

BC Hydro aims to add new clean, renewable energy sources like wind and solar, while acknowledging power supply challenges that must be managed as capacity grows. B.C.’s hydroelectric dams, functioning as batteries, enable the integration of intermittent renewables into the grid, providing reliable backup.

Chris O’Riley, president and CEO of BC Hydro, said the grid is one of the world’s cleanest. The new $36 billion capital plan encompasses investments in generation assets, large transmission infrastructure, and local distribution networks.

In partnership with BC Hydro, Premier Eby also announced a new streamlined approval process to expedite electrification for high-demand industries and support job creation, complementing measures like the BC Hydro rebate and B.C. Affordability Credit that help households.

Minister of Environment and Climate Change Strategy George Heyman highlighted the importance of rapid electrification in collaboration with the private sector to achieve CleanBC climate goals by 2030, including corridor charging via the BC's Electric Highway, and maintain the competitiveness of B.C. industries. The new process will streamline approvals for industrial electrification projects, enhancing efficiency and funding certainty.

 

Related News

View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Live Online & In-person Group Training

Advantages To Instructor-Led Training – Instructor-Led Course, Customized Training, Multiple Locations, Economical, CEU Credits, Course Discounts.

Request For Quotation

Whether you would prefer Live Online or In-Person instruction, our electrical training courses can be tailored to meet your company's specific requirements and delivered to your employees in one location or at various locations.