BC Hydro still in dark about cause of blackout

By National Post


CSA Z463 Electrical Maintenance

Our customized live online or in‑person group training can be delivered to your staff at your location.

  • Live Online
  • 6 hours Instructor-led
  • Group Training Available
Regular Price:
$249
Coupon Price:
$199
Reserve Your Seat Today
BC Hydro crews spent Thanksgiving Monday pouring over computer data to try and locate the cause of a massive power outage that darkened homes from Ladysmith to Victoria on Vancouver Island the previous day — but so far they've found no answers.

All they've been able to determine is that it's not an obvious problem, said BC Hydro spokesman Ted Olynyk.

"It's not like a tree fell on the line, or it was wind or snow or ice or there was physical damage to the property," explained Olynyk.

"What we are doing now is BC Transmission Corp. technical folks are reviewing computer information, data, to see if they can pinpoint where and when the fault happened."

The outage began with disruption of at least one south Island power line around 5:45 p.m. local time October 12. A cascade effect amplified the damage by subsequently tripping all the power lines south of Ladysmith, including the Gulf Islands, and leaving more than 200,000 customers in the dark during Thanksgiving dinner.

That's not supposed to happen, said Olynyk. The Island's power system, which includes 31 substations, was built to protect against cascade outages when a few lines go down, he said.

"It's designed so that doesn't happen," said Olynyk. Nonetheless, it has happened in the past, most often when lightening strikes, he said.

What caused the cascade is now a primary focus of the investigation, said Olynyk.

"It's very important to find the reasons for this, so we can take preventive measures and ensure this doesn't happen again, not only at the location it will have happened but throughout the power system."

When the power failed, BC Hydro crews were quick to try and visually inspect as many of the transmission lines as they could, said Olynyk.

Finding no obvious problems — cut cables, fallen trees or blown transformers, for example — they began activating lines one by one to see if they would hold power, said Olynyk. They did, and all were re-activated by 8 p.m.

It's similar, he said, to tripping a circuit breaker in a house. Sometimes the combination of appliances that trigger the outage is not clear, but power can be restored by resetting the breaker at the source.

"Sometimes we've gone out there and there's an outage and there's no indication of what caused the outage," he said. "We reset the system and it's back up, and sometimes we just don't know."

Related News

Site C mega dam billions over budget but will go ahead: B.C. premier

Site C Dam Update outlines hydroelectric budget overruns, geotechnical risks, COVID-19 construction delays, BC Hydro timelines, cancellation costs, and First Nations treaty rights concerns affecting renewable energy, ratepayers, and Peace Valley impacts.

 

Key Points

Overview of Site C costs, delays, geotechnical risks, and concerns shaping BC Hydro hydroelectric plans.

✅ Cost to cancel estimated at least $10B

✅ Final budget now about $16B; completion pushed to 2025

✅ COVID-19 and geotechnical risks drove delays and redesigns

 

The cost to cancel a massive B.C. energy development project would be at least $10 billion, provincial officials revealed in an update on the future of Site C.

Thus the project will go ahead, Premier John Horgan and Energy Minister Bruce Ralston announced Friday, but with an increased budget and timeline.

Horgan and Ralston spoke at a news conference in Victoria about the findings of a status report into the hydroelectric dam project in northeastern B.C.

Peter Milburn, former deputy finance minister, finished the report earlier this year, but the findings were not initially made public.

$10B more than initial estimate
On Friday, it was announced that the project's final price tag has once again ballooned by billions of dollars.

Site C was initially estimated to cost $6 billion, and the first approved budget, back in 2014, was $8.775 billion. The budget increased to $10.8 billion in 2018.

But the latest update suggests it will cost about $16 billion in total.

And, in addition to a higher budget, the date of completion has been pushed back to 2025 – a year later than the initial target.

Among the reasons for the revisions, according to the province, is the impact of COVID-19. While officials did not get into details, there have been multiple cases of the disease publicly reported at Site C work camps.

Additionally, fewer workers were permitted on site to allow for physical distancing, and construction was scaled back.

Also cited as a cause for the increased cost were "unforeseeable" geotechnical issues at the site, which required installation of an enhanced drainage system.

Speaking to reporters Friday, the premier deflected blame.

“Managing the contract the BC Liberals signed has been difficult because it transfers the vast majority of the geotechnical risk back to BC Hydro,” said Horgan.

Former Premier Christy Clark vowed to get the project to a point of no return, and in 2017 the NDP decided to continue with the project because of the cost of cancelling it.

The Liberals now say the clean energy project should continue, but deny they shoulder any of the blame.

“Someone has to take ownership – and it's got to be government in power,” said MLA Tom Shypitka, BC Liberal critic for energy. 

There are also several reviews underway, including how to change contractor schedules to reflect delays and potential cost impacts from COVID-19, and how to keep the work environment safe during the pandemic.

A total of 17 recommendations were made in Milburn's report, all of which have been accepted by BC Hydro and the province.

Among these recommendations is a restructured project assurance board with a focus on skill-specific membership and autonomy from BC Hydro.

Cost of cancelling the project
The report looked into whether it would be better to scrap the project altogether, but the cost of cancelling it at this point would be at least $10 billion, Horgan and Ralston said.

That cost does not include replacing lost energy and capacity that Site C's electricity would have provided, according to the province.

A study conducted in 2019 suggested B.C. will need to double its electricity production by 2055, especially as drought conditions are forcing BC Hydro to adapt power generation. 

The NDP government says the cost to ratepayers of cancelling the project would be $216 a year for 10 years. Going forward will still have a cost, but instead, that payment will be split over more than 70 years, the estimated lifetime of Site C, meaning BC Hydro customers will pay about $36 more a year once the site goes live, the NDP says, even as cryptocurrency mining raises questions about electricity use.

“We will not put jobs at risk; we will not shock people's hydro bills,” said Horgan.

"Our government has taken this situation very seriously, and with the advice of independent experts guiding us, I am confident in the path forward for Site C," Ralston said.

"B.C. needs more renewable energy to bridge the electricity gap with Alberta and electrify our economy, transition away from fossil fuels and meet our climate targets."

The minister said the site is currently employing about 4,500 people.

Arguments against Site C
While there are benefits to the project, there has also been vocal opposition.

In a statement released following the announcement that the project would go ahead, the Union of B.C. Indian Chiefs suggested the decision violated the premier's commitment to a UN declaration.

"The Site C dam has never had the free, prior and informed consent of all impacted First Nations, and proceeding with the project is a clear infringement of the treaty rights of the West Moberly First Nation," the UBCIC's secretary treasurer said.

Kukpi7 Judy Wilson said the UN's Committee on the Elimination of Racial Discrimination has called for a suspension of the project until it has the consent of Indigenous peoples.

"B.C. did not even attempt to engage First Nations about the safety risks associated with the stability of the dam in the recent reviews," she said.

"It is unfathomable that such clear human rights violations are somehow OK by this government."

Chief Roland Wilson of the West Moberly First Nation said he was disappointed the province didn’t consult his and other communities prior to making this announcement. In an interview with CTV News, he said he was offered an opportunity to join a call this morning.

“We signed a treaty in 1814,” he said. “Our treaty rights are being trampled on.”

Wilson said his nation has ongoing concerns about safety issues and the plans to flood the Peace Valley. West Moberly is in a bitter court battle with the province.

At the BC Legislature, Green Party Leader Sonia Furstenau slammed the government’s decision.

“It is an astonishingly terrible business case in any circumstances, but considering that we lose the agricultural land, the biodiversity, the traditional treaty lands of Treaty 8, this is particularly catastrophic,” she told reporters.

She went on to accuse the NDP government of keeping bad news from the public. She alleged the NDP knew of serious problems before last fall’s unscheduled election, but chose not to release information.

Prior to the decision former BC Hydro president and a former federal fisheries minister are among those who added their voices to calls to halt work on the dam.

They were among 18 Canadians who wrote an open letter to the province calling for an independent team of experts to explore geotechnical problems at the site.

In the letter, signed in September, the group that also included Grand Chief Stewart Phillip of the UBCIC wrote that going ahead would be a "costly and potentially catastrophic mistake." 

According to Friday's update, independent experts have confirmed the site is safe, though improvements have been recommended to enhance oversight and risk management.

Earlier in the project, a B.C. First Nation claimed it was a $1-billion treaty violation, though an agreement was reached in 2020 after the province promised to improve land management and restore traditional place names in areas of cultural significance.

The Prophet River First Nation will also receive payments while the site is operating, and some Crown land will be transferred to the nation as part of the agreement. 

Additionally, residents of a tiny community not far from the site is suing the province over two slow-moving landslides they claim caused property values to plummet.

Nearly three dozen residents of Old Fort are behind the allegations of negligence and breach of their charter right to security of person. The claim is tied to two landslides, in 2018 and 2020, that the group alleges were caused by ground destabilization from construction related to Site C.

One of the landslides damaged the only road into the community, leaving residents under evacuation for a month.

 

Related News

View more

In Europe, A Push For Electricity To Solve The Climate Dilemma

EU Electrification Strategy 2050 outlines shifting transport, buildings, and industry to clean power, accelerating EV adoption, heat pumps, and direct electrification to meet targets, reduce emissions, and replace fossil fuels with renewables and low-carbon grids.

 

Key Points

EU plan to cut emissions 95% by 2050 by electrifying transport, buildings and industry with clean power.

✅ 60% of final energy from electricity by 2050

✅ EVs dominate transport; up to 63% electric share

✅ Heat pumps electrify buildings; industry to 50% direct

 

The European Union has one of the most ambitious carbon emission reduction goals under the global Paris Agreement on climate change – a 95% reduction by 2050.

It seems that everyone has an idea for how to get there. Some are pushing nuclear energy. Others are pushing for a complete phase-out of fossil fuels and a switch to renewables.

Today the European electricity industry came out with their own plan, amid expectations of greater electricity price volatility in Europe in the coming years. A study published today by Eurelectric, the trade body of the European power sector, concludes that the 2050 goal will not be possible without a major shift to electricity in transport, buildings and industry.

The study finds that for the EU to reach its 95% emissions reduction target, electricity needs to cover at least 60 percent of final energy consumption by 2050. This would require a 1.5 percent year-on-year growth of EU electricity use, with evidence that EVs could raise electricity demand significantly in other markets, while at the same time reducing the EU’s overall energy consumption by 1.3 percent per year.

#google#

Transport is one of the areas where electrification can deliver the most benefit, because an electric car causes far less carbon emissions than a conventional vehicle, with e-mobility emerging as a key driver of electricity demand even if that electricity is generated in a fossil fuel power plant.

In the most ambitious scenario presented by the study, up to 63 percent of total final energy consumption in transport will be electric by 2050, and some analyses suggest that mass adoption of electric cars could occur much sooner, further accelerating progress.

Building have big potential as well, according to the study, with 45 to 63 percent of buildings energy consumption could be electric in 2050 by converting to electric heat pumps. Industrial processes could technically be electrified with up to 50 percent direct electrification in 2050, according to the study. The relative competitiveness of electricity against other carbon-neutral fuels will be the critical driver for this shift, but grid carbon intensity differs across markets, such as where fossil fuels still supply a notable share of generation.

 

Related News

View more

Bangladesh develops nuclear power with IAEA Assistance

Bangladesh Rooppur Nuclear Power Plant advances nuclear energy with IAEA support and ROSATOM construction, boosting energy security, baseload capacity, and grid reliability; 2400 MW units aid development, regulatory compliance, and newcomer infrastructure milestones.

 

Key Points

A 2400 MW nuclear project in Rooppur, built with IAEA guidance and ROSATOM, to boost Bangladesh's reliable power.

✅ Two units totaling 2400 MW for stable baseload supply

✅ IAEA Milestones and INIR reviews guide safe deployment

✅ ROSATOM builds; national regulator strengthens oversight

 

The beginning of construction at Bangladesh’s first nuclear power reactor on 30 November 2017 marked a significant milestone in the decade-long process to bring the benefits of nuclear energy to the world’s eighth most populous country. The IAEA has been supporting Bangladesh on its way to becoming the third ‘newcomer’ country to nuclear power in 30 years, following the United Arab Emirates in 2012 and Belarus in 2013.

Bangladesh is in the process of implementing an ambitious, multifaceted development programme to become a middle-income country by 2021 and a developed country by 2041. Vastly increased electricity production, with the goal of connecting 2.7 million more homes to the grid by 2021, is a cornerstone of this push for development, and nuclear energy will play a key role in this area, said Mohammad Shawkat Akbar, Managing Director of Nuclear Power Plant Company Bangladesh Limited. Bangladesh is also working to diversify its energy supply to enhance energy security, reduce its dependence on imports and on its limited domestic resources, he added.

#google# In the region, India's nuclear program is taking steps to get back on track, underscoring broader momentum.

“Bangladesh is introducing nuclear energy as a safe, environmentally friendly and economically viable source of electricity generation,” said Akbar.  The plant in Rooppur, 160 kilometres north-west of Dhaka, will consist of two units, with a combined power capacity of 2400 MW(e). It is being built by a subsidiary of Russia’s State Atomic Energy Corporation ROSATOM. The first unit is scheduled to come online in 2023 and the second in 2024, reflecting progress similar to the UK's latest nuclear power station developments.  “This project will enhance the development of the social, economic, scientific and technological potential of the country,” Akbar said.

The country’s goal of increased electricity production via nuclear energy will soon be a reality, Akbar said. “For 60 years, Bangladesh has had a dream of building its own nuclear power plant. The Rooppur Nuclear Power Plant will provide not only a stable baseload of electricity, but it will enhance our knowledge and allow us to increase our economic efficiency.

 

Milestones for nuclear

Bangladesh is among around 30 countries that are considering, planning or starting the introduction of nuclear power, with milestones at nuclear projects worldwide offering context for this progress. The IAEA assists them in developing their programmes through the Milestones Approach — a methodology that provides guidance on working towards the establishment of nuclear power in a newcomer country, including the associated infrastructure. It focuses on pointing out gaps, if any, in countries’ progress towards the introduction of nuclear power.

The IAEA has been supporting Bangladesh in developing its nuclear power infrastructure, including in establishing a regulatory framework and developing a radioactive waste-management system. This support has been delivered under the IAEA technical cooperation programme and is partially funded through the Peaceful Uses Initiative.

Nuclear infrastructure is multifaceted, containing governmental, legal, regulatory and managerial components, in addition to the physical infrastructure. The Milestones Approach consists of three phases, with a milestone to be reached at the end of each.

The first phase involves considerations before a decision is taken to start a nuclear power programme and concludes with the official commitment to the programme. The second phase entails preparatory work for the contracting and construction of a nuclear power plant, as seen in Bulgaria's nuclear project planning, ending with the commencement of bids or contract negotiations for the construction. The final phase includes activities to implement the nuclear power plant, such as the final investment decision, contracting and construction. The duration of these phases varies by country, but they typically take between 10 and 15 years.

“The IAEA Milestones Approach is a guiding document and the Integrated Work Plan (IWP) is the important means of bringing all of the stakeholders in Bangladesh together to ensure the fulfilment of all safety, security, and safeguards requirements of the Rooppur NPP project,” said Akbar. “This IWP enabled Bangladesh to develop a holistic approach to implementing IAEA guidance as well as cooperating with national stakeholders and other bilateral partners towards the development of a national nuclear power programme.”

When completed, the two units of the Rooppur Nuclear Power Plant will have a combined power capacity of 2400 MW(e). (Photo: Arkady Sukhonin/Rosatom)

 

INIR Mission

The Integrated Nuclear Infrastructure Review (INIR) is a holistic peer review to assist Member States in assessing the status of their national infrastructure for introducing nuclear power. The IAEA completed its first INIR mission to Bangladesh in November 2011, making recommendations on how to develop a plan to establish the nuclear infrastructure. Nearly five years later, in May 2016, a follow-up mission was conducted, which noted the progress made — Bangladesh had established a nuclear regulatory body, had chosen a site for the power plant and had completed site characterization and environmental impact assessment.

“The IAEA and other bodies, including those from experienced countries, can and do provide support, but the responsibility for safety and security will lie with the Government,” said Dohee Hahn, Director of the IAEA’s Division of Nuclear Power, at the ceremony for the pouring of the first nuclear safety-related concrete at Rooppur on 30 November 2017. “The IAEA stands ready to continue supporting Bangladesh in developing a safe, secure, peaceful and sustainable nuclear power programme.”

Supporting Infrastructure for Introducing a Nuclear Power Plant in Bangladesh: the IAEA Assists with the Review of Regulatory Guidance on Site Evaluation

How the IAEA Assists Newcomer Countries in Building Their Way to Sustainable Energy

"Exciting times for nuclear power," IAEA Director General Says

 

Related News

View more

Honda Accelerates Electric Vehicle Push with Massive Investment in Ontario

Honda Ontario EV Investment accelerates electric vehicle manufacturing in Canada, adding a battery plant, EV assembly capacity, clean energy supply chains, government subsidies, and thousands of jobs to expand North American production and innovation.

 

Key Points

The Honda Ontario EV Investment is a $18.4B plan for EV assembly and battery production, jobs, and clean growth.

✅ $18.4B for EV assembly and large-scale battery production

✅ Thousands of Ontario manufacturing jobs and supply chain growth

✅ Backed by Canadian subsidies to accelerate clean transportation

 

The automotive industry in Ontario is on the verge of a significant transformation amid an EV jobs boom across the province, as Honda announces plans to build a new electric vehicle (EV) assembly plant and a large-scale battery production facility in the province. According to several sources, Honda is prepared to invest an estimated $18.4 billion in this initiative, signalling a major commitment to accelerating the automaker's shift towards electrification.


Expanding Ontario's EV Ecosystem

This exciting new investment from Honda builds upon the growing momentum of electric vehicle development in Ontario. The province is already home to a burgeoning EV manufacturing ecosystem, with automakers like Stellantis and General Motors investing heavily in retooling existing plants for EV production, including GM's $1B Ontario EV plant in the province. Honda's new facilities will significantly expand Ontario's role in the North American electric vehicle market.


Canadian Government Supports Clean Vehicles

The Canadian government has been actively encouraging the transition to cleaner transportation by offering generous subsidies to bolster EV manufacturing and adoption, exemplified by the Ford Oakville upgrade that received $500M in support. These incentives have been instrumental in attracting major investments from automotive giants like Honda and solidifying Canada's position as a global leader in EV technology.


Thousands of New Jobs

Honda's investment is not only excellent news for the Canadian economy but also promises to create thousands of new jobs in Ontario, boosting the province's manufacturing sector. The presence of a significant EV and battery production hub will attract a skilled workforce, as seen with a Niagara Region battery plant that is bolstering the region's EV future, and likely lead to the creation of related businesses and industries that support the EV supply chain.


Details of the Plan

While the specific location of the proposed Honda plants has not yet been confirmed, sources indicate that the facilities will likely be built in Southwestern Ontario, near Ford's Oakville EV program and other established sites. Honda's existing assembly plant in Alliston will be converted to produce hybrid models as part of the company's broader plan to electrify its lineup.


Honda's Global EV Ambitions

This substantial investment in Canada aligns with Honda's global commitment to electrifying its vehicle offerings. The company has set ambitious goals to phase out traditional gasoline-powered cars and achieve net-zero carbon emissions by 2040.  Honda aims to expand EV production in North America to meet growing consumer demand and deepen Canada-U.S. collaboration in the EV industry.


The Future of Transportation

Honda's announcement signifies a turning point for the automotive landscape in Canada. This major investment reinforces the shift toward electric vehicles as an inevitable future, with EV assembly deals putting Canada in the race as well.  The move highlights Canada's dedication to fostering a sustainable, clean-energy economy while establishing a robust automotive manufacturing industry for the 21st century.

 

Related News

View more

TransAlta Scraps Wind Farm as Alberta's Energy Future Blusters

Alberta Wind Energy Policy Changes highlight TransAlta's Riplinger cancellation amid UCP buffer zones for pristine viewscapes, regulatory uncertainty, and market redesign debates, reshaping Alberta's renewables investment climate and clean energy diversification plans.

 

Key Points

UCP rules and market shifts reshaping wind siting, permits, and finance, increasing uncertainty and delays for new projects.

✅ 35-km buffer near pristine viewscapes limits wind siting

✅ TransAlta cancels 300 MW Riplinger project

✅ Market redesign uncertainty chills renewables investment

 

The winds of change are blowing through Alberta's energy landscape today, and they're not necessarily carrying good news for renewable energy development. TransAlta, a major Canadian energy company, recently announced the cancellation of a significant wind farm project, citing a confluence of factors that create uncertainty for the future of wind power in the province. This decision throws a spotlight on the ongoing debate between responsible development and fostering a clean energy future in Alberta.

The scrapped project, the Riplinger wind farm near Cardston, Alberta, was envisioned as a 300-megawatt facility capable of providing clean electricity to the province. However, TransAlta pointed to recent regulatory changes implemented by the United Conservative Party (UCP) government, following the end of the renewable energy moratorium in Alberta, as a key reason for the project's demise. These changes include the establishment of a 35-kilometer buffer zone around designated "pristine viewscapes," which significantly restricts potential wind farm locations.

John Kousinioris, CEO of TransAlta, expressed frustration with the lack of clarity surrounding the future of renewable energy policy in Alberta. He highlighted this, along with the aforementioned rule changes, as major factors in the project's cancellation. TransAlta has also placed three other power projects on hold, indicating a broader concern about the current investment climate for renewable energy in the province.

The news has been met with mixed reactions. While some residents living near the proposed wind farm site celebrate the decision due to concerns about potential impacts on tourism and the environment, others worry about the implications for Alberta's clean energy ambitions, including renewable energy job growth in the province. The province, a major energy producer in Canada, has traditionally relied heavily on fossil fuels, and this decision might be seen as a setback for its goals of diversifying its energy mix.

The Alberta government defends its changes to renewable energy policy, arguing that they are necessary to ensure responsible development and protect sensitive ecological areas. However, the TransAlta decision raises questions about the potential unintended consequences of these changes. Critics argue that the restrictions might discourage investment in renewable energy and the province's ability to sell clean power to wider markets altogether, hindering Alberta's progress towards a more sustainable future.

Adding to the uncertainty is the ongoing process of redesigning Alberta's energy market. The aim is to incorporate more renewable energy sources, including solar energy expansion across the grid, but the details of this redesign remain unclear. This lack of transparency makes it difficult for companies like TransAlta to make sound investment decisions, further dampening enthusiasm for renewable energy projects.

The future of wind energy development in Alberta remains to be seen. TransAlta's decision to scrap the Riplinger project is a significant development, and it will be interesting to observe how other companies respond to the changing regulatory landscape, as a Warren Buffett-linked developer pursues a $200 million wind project in Alberta. Striking a balance between responsible development, protecting the environment, and fostering a clean energy future will be a crucial challenge for Alberta moving forward.

This situation highlights the complex considerations involved in transitioning to a renewable energy future, where court rulings on wind projects can influence policy and investment decisions. While environmental concerns are paramount, ensuring a stable and predictable investment climate is equally important. Open communication and collaboration between industry, government, and stakeholders will be key to navigating these challenges and ensuring Alberta can harness the power of wind energy for a sustainable future.

 

Related News

View more

UK electricity and gas networks making ‘unjustified’ profits

UK Energy Network Profits are under scrutiny as Ofgem price controls, Citizens Advice claims, and National Grid margins spark debate over monopolies, allowed returns, consumer bills, rebates, and future investment under tougher regulation.

 

Key Points

UK Energy Network Profits are returns set by Ofgem for regulated grid operators, shaping consumer bills and investment

✅ Ofgem sets allowed returns for monopoly networks via price controls

✅ Dispute over interest rates, bond yields, and risk premiums

✅ Reforms proposed: shorter controls, tougher investor incentives

 

Companies that run Britain’s electricity and gas networks, including National Grid, are making “eye-watering” profits at the expense of households, according to a well-known consumer group.

Citizens Advice believes £7.5bn in “unjustified” profits should be returned to consumers who pay for network costs via their electricity and gas bills, with parallels seen in a deferred BC Hydro costs report abroad, although its figures have been contested by the energy industry and regulator.

Ownership of electricity and gas networks came under the spotlight in the run-up to June’s general election, after the Labour party said in its manifesto it would bring both national and regional grid infrastructure to back into public ownership, amid wider debates about grid privatization concerns elsewhere, over time.

Electricity sector privatisation began in 1990 and the gas industry was privatised in 1986. Energy network companies — which own and operate the cables and wires that help deliver electricity and gas to homes and businesses — are in effect monopolies that are regulated by Ofgem. Ofgem evaluates what their costs, including the cost of capital to finance investments, might be over an eight-year “price control” period, similar to determinations like the OEB decision on Hydro One rates in Ontario, Canada. Citizens Advice claims many of the regulator’s calculations for the most recent price control went “considerably in networks’ financial favour”.

It believes assumptions Ofgem made about factors such as the future path of interest rates and returns on government bonds were too generous, with international contrasts like power theft challenges in India illustrating different risk contexts, as was the regulator’s assessment of the risk associated with operating a network company. 

These “generous” assumptions will lead to network companies making average profit margins of 19 per cent and an average return of 10 per cent for their investors at the expense of consumers, Citizens Advice claims in a report published on Wednesday, which recommends a shorter price control period to allow for more accurate forecasting.

“Decisions made by Ofgem have allowed gas and electricity network companies to make sky-high profits that we’ve found are not justified by their performance,” said Gillian Guy, chief executive of Citizens Advice. Ofgem defended its regulatory regime, saying it helped to cut costs, improve reliability and customer satisfaction. 

“Ofgem has already cut costs to consumers by 6 per cent in the current price control and secured a rebate of over £4.5bn from network companies and is engaging with the industry to deliver further savings, with some regions seeing Ontario electricity rate reductions for businesses as well,” said Dermot Nolan, chief executive of the energy regulator.

Mr Nolan insisted the next price controls would be “tougher for investors”. The current price controls for the gas and electricity transmission networks, plus gas distribution, run until 2021 and until 2023 for local electricity distribution networks.

“While we don’t agree with its modelling and the figures it has produced, the Citizens Advice report raises some important issues about network regulation which will be addressed in the next control,” Mr Nolan said.

The Energy Networks Association, a trade body, refuted the claims of Citizens Advice, insisting that costs had fallen by 17 per cent in real terms since privatisation. The current regulatory framework was established after a public consultation, it said, adding that today’s report repeated several old claims that had previously been rejected by the Competition and Markets Authority.

“Our energy networks are among the most reliable and lowest cost in the world and their performance has never been better. In the next six years energy network companies are forecasted to deliver £45bn of investment in the UK economy,” a spokesman for the networks association added. National Grid said that since 2013 it had generated savings of £460m for bill payers.

 

Related News

View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Download the 2025 Electrical Training Catalog

Explore 50+ live, expert-led electrical training courses –

  • Interactive
  • Flexible
  • CEU-cerified