Largest Power Co-Generation Plant in Canada Starts Operation

Calgary/Edmonton, AB - - Electricity from CanadaÂ’s largest-ever co-generation plant at Joffre, Alberta flowed into the provincial power grid as the Joffre Cogeneration facility moves closer to completion. The co-generation power plant is currently undergoing start-up testing and has been synchronized with the provincial power grid. The Cogeneration facility is a significant part of the Joffre 2000 petrochemical expansion currently underway at the NOVA Chemicals Corporation (NOVA Chemicals) Joffre site.

When fully operational, the $380 million plant, operated by ATCO Power, will increase the amount of electricity generated in Alberta by more than four per cent. Major partners with a 40 per cent share in the 416-megawatt plant are ATCO Power and EPCOR, with NOVA Chemicals owning the final 20 per cent.

"As we fully power up, more electricity will be available to meet the growing needs of Albertans and NOVA Chemicals demands at Joffre," said ATCO Power President Gary Bauer. "This facility is one of the most cost-efficient, technologically-advanced and environmentally progressive in the world."

On average NOVA Chemicals is expected to use 128 megawatts of electricity with the remaining 288 megawatts available for sale by ATCO Power and EPCOR to meet growing provincial needs. The plant will supply the electrical and steam/heat needs for the entire Joffre petrochemical site, where NOVA Chemicals owns and operates two ethylene plants and a polyethylene plant.

"One of the environmental benefits of co-generation is its ability to maximize the use of energy generated on-site," said Don Lowry, President and CEO of EPCOR. "Nothing goes to waste as the heat and steam byproducts of generation will be used on-site and the additional power can be used to meet power needs in the province.

The innovative co-generation plant consists of two Siemens-Westinghouse 501F combustion turbine generators, each with a heat recovery boiler supplying steam to a single steam turbine generator. It uses natural gas to simultaneously produce steam through the recovery of exhaust heat and electrical energy. A major milestone occurred February 27 with the firing of the first combustion turbine. Both turbines went on line together and synchronized to the provincial grid on March 14, 2000. The turbines are being operated on an intermittent basis during the testing and tuning stages with the steam turbine expected to be fully operational within one month.

Dan Boivin, NOVA ChemicalsÂ’ President of Olefins/Polyolefins said: "The efficient generation of low-cost energy will contribute to our goal of being a very low cost producer of both ethylene and polyethylene."

The ATCO Group of Companies is engaged in electric power generation, transmission and distribution; natural gas gathering, processing, transmission, storage and distribution; workforce housing; industrial noise abatement and technical services and facilities management. More information about ATCO can be found on our website, http://www.ATCO.com

EPCOR is an Alberta-based company that supplies essential elements for living -- water, power, natural gas and technology services - to customers in Alberta, Ontario and British Columbia. More information about EPCOR can be found on our website, htpp://www.epcor-group.com

NOVA Chemicals is a focused commodity chemicals company producing ethylene/polyethylene and styrenics at 18 locations in Canada, the United States, France, the Netherlands and the United Kingdom. Visit NOVA Chemicals on the Internet at http://www.novachem.com

For more information contact: Grant Lake ATCO Power Vice President, Commercial Tel: (403) 209-6905

Related News

chicago wind electricity

Proposed underground power line could bring Iowa wind turbine electricity to Chicago

CHICAGO - The company behind a proposed underground transmission line that would carry electricity generated mostly by wind turbines in Iowa to the Chicago area said Monday that the $2.5 billion project could be operational in 2024 if regulators approve it.

Direct Connect Development Co. said it has lined up three major investors to back the project. It plans to bury the transmission line in land that runs along existing Canadian Pacific railroad tracks, hopefully reducing the disruption to landowners. It's not unusual for pipelines or fiber optic lines to be buried along railroad tracks in the land the railroad…

READ MORE
new mexico wind farm

New Mexico Governor to Sign 100% Clean Electricity Bill ‘As Quickly As Possible’

READ MORE

Substation Maintenance Training

Substation Maintenance Training

READ MORE

UK electricity and gas networks making ‘unjustified’ profits

READ MORE

ev building charging

How vehicle-to-building charging can save costs, reduce GHGs and help balance the grid: study

READ MORE