Maintenance on Ex turbine begins
The turbine's rotor and generator will be removed, serviced and re-installed with the aid of two large construction cranes. This scheduled maintenance will focus on replacing the main bearing of the turbine and updating the controls.
"The bearing change-out is intended to extend the Ex Place turbine's lifespan," explains Dianne Saxe, President of WindShare. "On behalf of our 400 community members, we're pleased that this technical maintenance will help continue the generation of clean renewable wind power in Toronto."
The maintenance is expected to be completed by April 30.
In 2002, Toronto Hydro Energy Services Inc., with WindShare, constructed Canada's first urban wind turbine. Situated on a busy commuter route and in a major cultural, business and tourist site in Toronto it has helped to raise awareness about the nature of wind power. In 2010, the wind turbine achieved:
• A 94 per cent operating availability rate
• A 1,000 megawatt-hours of electricity production, the equivalent of powering 200 homes with 100 "green" electricity
• A displacement of 380 tonnes of CO2, the equivalent of taking 1,300 cars off the road or planting 30,000 trees each year.
Related News

EPA, New Taipei spar over power plant
TAIPEI - The controversy over the Shenao Power Plant heated up yesterday as Environmental Protection Administration (EPA) and New Taipei City Government officials quibbled over the project’s potential impact on a fisheries conservation area and other issues.
State-run Taiwan Power Co (Taipower) wants to build a coal-fired plant on the site of the old Shenao plant, which was near Rueifang District’s (瑞芳) Shenao Harbor.
The company’s original plan to build a new plant on the site passed an environmental impact assessment (EIA) in 2006, and the EPA on March 14 approved the firm’s environmental impact difference analysis report covering proposed changes to…