ERCOT eyes 3 billion in transmission line projects

TEXAS - The Electric Reliability Council of Texas said that utilities and other transmission providers in the region plan to add 2,538 miles of new transmission lines over the next five years at a cost of about $3 billion.

The annual transmission planning report, which covers the 2008-2012 period, is similar in many ways to the report ERCOT issued in January 2007. Then, ERCOT projected that $3.1 billion would be spent on new transmission lines and related projects in the 2007-11 period.

The report includes several 345-kV transmission-line projects that have been under develop Clear Spring to Salado that will be energized in 2010-11, and an 198-mile project from Red Creek to Killeen that will come online in 2012.

Planned improvements identified for the first time in 2008's five-year plan, ERCOT said, include a 22-mile, 345-kV line from Nacogdoches to Lufkin in eastern Texas; a 345-kV switching station in northwest Houston to increase the ability of the grid to transport power between northern Texas and the Houston area; and additional autotransformer and 138-kV line upgrades in the Dallas/Fort Worth metropolitan area.

The reliability council said two new 345-kV lines and a new 345-kV switching station were included in the West region plan "due to the approximately 6,500 MW of wind generation that is installed or has completed an interconnection agreement in the West congestion management zone."

ERCOT added, however, that these West zone upgrades "may be superseded by the transmission lines that are ordered as a result of the Competitive Renewable Energy Zone process underway at the Public Utility Commission of Texas." The PUC is expected to designate the final CREZ transmission projects in mid-2008.

Related News

bitcoin screen

Bitcoin mining uses so much electricity that 1 city could curtail facility's power during heat waves

MEDICINE HAT - On the day of the grand opening of the largest bitcoin mining project in the country, the weather was partly cloudy and 15 C. On a Friday afternoon like this one, the new facility uses as much electricity as all of Medicine Hat, Alta., a city of more than 60,000 people and home to several large industrial plants.

The vast amount of electricity needed for bitcoin mining is why the city of Medicine Hat has championed the economic benefits of the project, while environmentalists say they are wary of the significant energy use.

Toronto-based Hut 8 has spent more…

READ MORE

Scotland’s Wind Farms Generate Enough Electricity to Power Nearly 4.5 Million Homes

READ MORE

iran electricity

Iran eyes transmitting electricity to Europe as region’s power hub

READ MORE

BC Hydro completes major milestone on Site C transmission line work

READ MORE

stellaten-and-innergex-sign-wind-deal-with-bc-hydro

Stellat'en and Innergex Sign Wind Deal with BC Hydro

READ MORE