Pennsylvania power company never inspected plant equipment that failed, data show
PENNSYLVANIA - PPL Corp. officials never inspected the part of a power plant's discharge area that failed in August, causing a major environmental problem on the Delaware River across from Warren County, according to Pennsylvania records.
The Pennsylvania plant's 1,500-foot-long basin was to let the fly ash - a byproduct of burning coal - settle to the bottom while clear water from the top flowed out a discharge pipe. But a leaking barrier allowed the ash to mix with the discharge water, officials said. About 100 million gallons of coal ash slurry spilled into the river.
The discharge structure had concrete walls on three sides and wooden stop logs on the fourth. The stop logs, which look like railroad ties, were the part that failed.
Related News

Construction of expanded Hoa Binh Hydropower Plant to start October 2020
VIETNAM - The extended Hoa Binh Hydropower Plant, which is expected to break ground in October 2020, is considered the largest power project to be constructed this year.
Covering an area of 99.2 hectares, the project is invested by Electricity of Vietnam (EVN). Besides, Vietnam Electricity Power Projects Management Board No.1 (EVNPMB1) is the representative of the investor and Power Engineering Consulting JSC 1 (EVNPECC1) is in charge of building the feasibility report for the project. The expanded Hoa Binh Hydro Power Plant has a total investment of VND9.22 trillion ($400.87 million), 30 per cent of which is EVN’s equity and…