Point Lepreau delay will cost PEI customers
POINT LEPREAU, NEW BRUNSWICK - Bad news from New Brunswick's Point Lepreau power plant will mean higher electricity rates for Prince Edward Islanders.
The Point Lepreau nuclear power plant went off-line in March 2008. Because PEI buys most of its power from New Brunswick, Maritime Electric, the Island's electrical utility, was then forced to find a temporary and more expensive source of power.
That replacement energy is costing Maritime Electric $2 million more each month. It's a cost the utility will now have to bear for longer than it had hoped.
"We had heard of the delays prior to this so we had estimated it would be coming back online next summer," said utility president Fred O'Brien.
"It was definitely disappointing news to hearÂ… that it is going to be extended. Their current forecast is to February 2011."
O'Brien said those added costs will be passed on to customers, but the company is working out how to best do that.
"There will be additional costs in energy supply that will have to be recovered," he said.
"What we're trying to do is figure out the most appropriate way to recover those costs over an extended period of time."
Maritime Electric will be putting together a proposal for rate increases for the Island Regulatory and Appeals Commission, which sets electricity prices, in January.
O'Brien said it's too early to say how much more Islanders might have to pay.
Related News

Indian government takes steps to get nuclear back on track
DELHI - A lack of available domestically produced nuclear fuel and delays in constructing and commissioning nuclear power plants, including first-of-a-kind plants and the Prototype Fast Breeder Reactor (PFBR), meant that India failed to meet its nuclear generation targets under the governmental plans over the decade to 2017.
India's nuclear generation target under its 11th five-year plan, covering the period 2007-2012, was 163,395 million units (MUs) and the 12th five-year Plan (2012-17) was 241,748 MUs, Minister of state for the Department of Atomic Energy and the Prime Minister's Office Jitendra Singh told parliament on 6 February. Actual nuclear generation in those…