Duke Energy Edwardsport cost overrun drives Indiana regulatory scrutiny, with the IURC weighing rate increases for ratepayers as the IGCC coal gasification project faces calls for cost caps, safeguards, and accountability.

 

Key Information

Rising costs at Duke's Edwardsport IGCC plant spur IURC review and pushback against shifting overruns to ratepayers.

  • Total budget nears $2.88B, roughly double 2007 estimate
  • IURC hearing scheduled September 16 in Indianapolis
  • Consumer counselor seeks cost cap and end to tax deferral
  • Average 19% rate hike phased in by 2013 if approved
  • 630 MW IGCC coal gasification plant near Edwardsport

 

Indiana's advocate for utility ratepayers said he is "deeply concerned" about the mounting cost of a coal-gasification plant Duke Energy Corp. is building and urged state regulators to protect Duke's customers from the cost overruns.

 

Indiana Utility Consumer Counselor David Stippler's comments came four months after Duke Energy revealed the cost of its southwestern Indiana plant had grown to nearly $2.9 billion, as internal emails later showed, or about twice the project's original 2007 estimate.

In its April request to the Indiana Utility Regulatory Commission for permission to pass the higher costs onto its customers, Duke said those costs had risen $530 million, or 23 percent, since November largely due to design changes that required more materials.

Stippler said in a statement that his office, which represents ratepayers before the commission, scrutinized Duke's request and information the company provided about the project. He said he was not swayed by Duke's arguments.

Stippler said the review left him "deeply concerned about the dramatic rise in the project's costs in this short period of time" and also worried about Duke's "apparent inability" to control the 630-megawatt plant's costs.

"Utilities have a responsibility to demonstrate that rate-recovered costs, including increases to approved costs, are reasonable, necessary and prudent," he said. "Unfortunately, Duke Energy has not met this burden of proof", a conclusion echoed when the state said it overstated its case for new plants, in its request that the panel allow it to add more than a half-billion dollars to the amount ratepayers would end up footing.

Stippler urged the commission, which has the final say on utilities' rate increase requests, following Duke's decision to reopen the Edwardsport deal earlier, to provide safeguards to Duke's customers by capping the plant's overall costs at an amount significantly lower than the $2.88 billion Duke wants customers to foot.

He also recommended the commission end a financial incentive allowing Duke to increase earnings by deferring income taxes. Stippler said removing that incentive would quickly save Duke's Indiana ratepayers tens of millions of dollars.

The IURC is scheduled to hold a hearing September 16 in Indianapolis on Duke's request, amid Energy Summit concerns raised for then-Gov. Daniels.

If approved by regulators, Duke's Indiana customers would see on average an overall 19 percent rate increase phased in by 2013.

Duke spokeswoman Angeline Protogere said the Charlotte, N.C.-based company has done its best to hold down the cost of the plant, which Duke has said would be the first of its kind on such a scale, even as the state cut expansion plans at Cliffside in North Carolina.

Unlike traditional coal-fired power plants that burn coal to produce electricity, the new plant will convert coal into a synthetic gas processed to remove some pollutants such as mercury and sulfur, and to explore carbon storage options under study. The gas is then burned in a traditional turbine power plant to produce electricity.

The new plant, set to go online in 2012, will replace a 160-megawatt coal-fired plant.

Protogere said plant construction is about 45 percent complete at the site along the White River near Edwardsport, about 15 miles northeast of Vincennes.

Environmental and government watchdog groups have sued to try to derail the Edwardsport plant in court, calling it a huge waste of money that would be better spent on renewable energy such as wind farms and promoting energy efficiency.

Kerwin Olson, program director for the Citizens Action Coalition of Indiana, said construction of the plant should be immediately halted and Duke should be required to pay a big portion of the plant's costs.

"Duke should be required to eat all of the costs they incurred since May 2008, when they first realized that their initial estimates were way off base," he said. "We believe the ultimate protection for ratepayers is canceling the project today."

 

Related News

Related News

Bruce nuclear reactor taken offline as $2.1B project 'officially' begins

Bruce Power Unit 6 refurbishment replaces major reactor components, shifting supply to hydroelectric and natural…
View more

British Columbia Fuels Up for the Future with $900 Million Hydrogen Project

H2 Gateway Hydrogen Network accelerates clean energy in B.C., building electrolysis plants and hydrogen fueling…
View more

Duke Energy Florida's smart-thinking grid improves response, power restoration for customers during Hurricane Ian

Self-healing grid technology automatically reroutes power to reduce outages, speed restoration, and boost reliability during…
View more

PC Leader Doug Ford vows to fire Hydro One CEO, board if elected

Doug Ford's Hydro One firing vow targets CEO pay, the utility's board, and privatization, amid…
View more

Medicine Hat Grant Winners to Upgrade Grid and Use AI for Energy Savings

Medicine Hat Smart Grid AI modernizes electricity distribution with automation, sensors, and demand response, enhancing…
View more

Pandemic causes drop in electricity demand across the province: Manitoba Hydro

Manitoba Electricity Demand Drop reflects COVID-19 effects, lowering peak demand about 6% as businesses and…
View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Live Online & In-person Group Training

Advantages To Instructor-Led Training – Instructor-Led Course, Customized Training, Multiple Locations, Economical, CEU Credits, Course Discounts.

Request For Quotation

Whether you would prefer Live Online or In-Person instruction, our electrical training courses can be tailored to meet your company's specific requirements and delivered to your employees in one location or at various locations.