OEB proposes Distribution System Code amendments
The amendments would exempt the following generation projects from the queuing process, while ensuring any reliability and customer impact issues can be addressed:
• generation facilities greater than 10 kilowatts (kW) and up to 250 kW that connect to a line of less than 15 kilovolts (kV); and
• generation facilities greater than 10 kW and up to 500 kW that connect to a line that is 15 kV or higher.
The amendments would support government policy by facilitating the connection of generation facilities that qualify under initiatives such as the renewable energy standard offer program and the Ontario Ministry of Agriculture, Food and Rural Affairs program for small farm-based biomass.
The Board invites interested parties to comment on the revised proposed amendments in writing by January 9, 2009.
Related News

PG&E says power lines may have started 2 California fires
SANTA ROSA, Calif - Pacific Gas & Electric Co. power lines may have started two wildfires over the weekend in the San Francisco Bay Area, the utility said Monday, even though widespread blackouts were in place to prevent downed lines from starting fires during dangerously windy weather.
The fires described in PG&E reports to state regulators match blazes that destroyed a tennis club and forced evacuations in Lafayette, about 20 miles (32 kilometres) east of San Francisco.
The fires began in a section of town where PG&E had opted to keep the lights on. The sites were not designated as a high…