Progress Energy delays nuclear plant


NFPA 70b Training - Electrical Maintenance

Our customized live online or in‑person group training can be delivered to your staff at your location.

  • Live Online
  • 12 hours Instructor-led
  • Group Training Available
Regular Price:
$699
Coupon Price:
$599
Reserve Your Seat Today
Progress Energy Florida said it will delay initial operations for a proposed $17 billion nuclear power plant in Levy County and seek approval to lower the monthly cost to customers to build the plant.

The plant was originally planned to become operational sometime between 2016 to 2018. The delay of at least 20 months comes because the Nuclear Regulatory Commission recently told Progress Energy it will allow site preparation only after it issues a license to build and operate the plant, a ruling made public for the first time.

As a result, Progress Energy said in a news release, it will seek approval to spread certain costs, mainly for the new plant, over five years, which would provide some short-term customer relief, the company said in a news release.

If approved, the cost deferral would result in a nuclear charge of $6.69 per month per 1,000 kilowatt-hours for residential customers in 2010 instead of $12.63 per 1,000 kWh, as allowed by the current law, the release stated.

These costs are for the planned Levy County nuclear plant with two reactors plus improvements to increase the output at the existing Crystal River nuclear plant from 900 megawatts to 1,080 megawatts, Progress Energy said. The Crystal River plant rate accounts for 30 cents of the requested amount.

The Florida Public Service Commission will conduct hearings on the company's nuclear cost recovery in September and is expected to make a decision in mid-October.

In a separate issue, the PSC in October is expected to make decisions on the company's 2010 base rates, which make up about one-third of a typical residential monthly bill.

It is too early for Progress Energy to determine customers' costs for electricity per kilowatt-hour in 2010 or the average customers' January bill as both include factors that are not determined yet, company officials said.

That bill would include the base rate, fuel, energy conservation programs, government-mandated environmental projects, gross receipts taxes and local government fees and taxes, in addition to the nuclear project costs.

"I expect significant impact from (Obama Administration) energy initiatives, but I do not anticipate those would have an impact on the need for the new nuclear plant," said Jeff Lyash, president and CEO of Progress Energy Florida said in a prepared release.

"The Levy County nuclear project remains one of our company's top priorities, and we are committed to pursuing state-of-the-art new nuclear facilities in Florida, especially given the strong public policy support for nuclear energy at the state level," Jeff Lyash, president and CEO of Progress Energy Florida said in a prepared release.

"Shifting this portion of the work until we have the combined operating license in hand enables us to spread some of the costs over a longer period," he said.

"We believe this is in the best interest of our customers particularly during this continuing economic slowdown."

Progress Energy originally intended to do some site preparation, including pumping water from the site, and sought "limited work authorization" from the NRC.

The company did not specify when the NRC determined it must wait until it issues a license, beyond saying it received notification in April.

The shift in schedule provides time for the economy to recover, which should allow for financing in a more stable market, said Bill Johnson, president, chairman and CEO of Progress Energy in Raleigh, N.C.

It also provides more time for national leaders to develop potentially "transformational" energy policies currently under debate in Washington, Johnson said in a prepared statement.

Related News

Hydro-Quebec shocks cottage owner with $5,300 in retroactive charges

Hydro-Quebec back-billing arises from analogue meter errors and estimated consumption, leading to arrears for electricity…
View more

Canadian Gov't and PEI invest in new transmission line to support wind energy production

Skinners Pond Transmission Line expands PEI's renewable energy grid, enabling wind power integration, grid reliability,…
View more

New Texas will bill electric vehicle drivers an extra $200 a year

Texas EV Registration Fee adds a $200 annual charge under Senate Bill 505, offsetting lost…
View more

China aims to reduce coal power production

China Coal-Fired Power Consolidation targets capacity cuts through mergers, SASAC-led restructuring, debt reduction, asset optimization,…
View more

UAE’s nuclear power plant connects to the national grid in a major regional milestone

UAE Barakah Nuclear Plant connects Unit 1 to the grid, supplying clean electricity, nuclear baseload…
View more

TC Energy confirms Ontario pumped storage project is advancing

Ontario Pumped Storage advances as Ontario's largest energy storage project, delivering clean electricity, long-duration capacity,…
View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Live Online & In-person Group Training

Advantages To Instructor-Led Training – Instructor-Led Course, Customized Training, Multiple Locations, Economical, CEU Credits, Course Discounts.

Request For Quotation

Whether you would prefer Live Online or In-Person instruction, our electrical training courses can be tailored to meet your company's specific requirements and delivered to your employees in one location or at various locations.