KCP&LÂ’s new coal plant behind schedule

WESTON, KANSAS - KCP&L said that its coal-fired power plant being built near Weston had fallen behind schedule and could be in service two months later than had been expected.

The 850-megawatt Iatan 2 power plant had been scheduled to start testing early this year and to be providing power to customers by late summer. But the plant has encountered construction delays, and the recent blizzard and frigid weather created more problems.

"The bitterly cold weather has made it impossible to make up that time," said Chuck Caisley, a spokesman for KCP&L.

Although some of the lost time could be recovered eventually, the utility said in a filing with the Securities and Exchange Commission that it now expected the power plant wouldn't be in service until fall.

KCP&L has a 73 percent stake in the power plant, including the portion acquired when Aquila was purchased by KCP&L's parent, Great Plains Energy. The other partners in the power plant are Empire District Electric, Kansas Electric Power Cooperative and the Missouri Joint Municipal Utility Commission.

The delay also could push back the effective dates a couple of months for a rate increase request already filed in Kansas and another that will be filed in Missouri. It was originally predicted that those rates could go into effect in October 2010 in Kansas and the first quarter of 2011 in Missouri.

The utility also said in the SEC filing that it had begun a review of the cost of Iatan 2 but didn't expect the cost for its share of the plant to rise above the $1.15 billion to $1.2 billion it previously announced.

Related News

scott fielding

Manitoba looking to raise electricity rates 2.5 per cent each year for 3 years

WINNIPEG - The Manitoba government is planning to raise electricity rates by 2.5 per cent a year over the next three years.

Finance Minister Scott Fielding says the increases, to be presented in a bill before the legislature, are the lowest in a decade and will help keep rates among the lowest in Canada.

Crown-owned Manitoba Hydro had asked for a 3.5 per cent increase this year to help pay off billions of dollars in debt.

“The way we figured this out, we looked at the rate increases that were approved by PUB (Public Utilities Board) over the last ten years, (and) we…

READ MORE
Newfoundland Consumer Advocate

NL Consumer Advocate says 18% electricity rate hike 'unacceptable'

READ MORE

dreamline

LOC Renewables Delivers First MWS Services To China's Offshore Wind Market

READ MORE

electricity pylon

Solar changing shape of electricity prices in Northern Europe

READ MORE

bc hydro president

Two new BC generating stations officially commissioned

READ MORE