South Carolina refuses to block nuclear plant


Substation Relay Protection Training

Our customized live online or in‑person group training can be delivered to your staff at your location.

  • Live Online
  • 12 hours Instructor-led
  • Group Training Available
Regular Price:
$699
Coupon Price:
$599
Reserve Your Seat Today
Utility regulators in South Carolina denied a request by two environmental groups to block Duke Energy Corp. from starting work at a proposed nuclear power plant.

In May, the S.C. Public Service Commission allowed Duke to spend up to $230 million through 2009 on preconstruction work at the site in Cherokee County.

In petitions filed last month, Friends of the Earth and NC Warn said that the federal Nuclear Regulatory Commission had not approved the reactor design that Duke plans, creating uncertainty about costs.

Commissioners said that the groups' petition was not filed quickly enough after the May decision and that it brought up no new issues that merited reconsideration.

"I'm not surprised they ruled against our motion," said Tom Clements, the Southeast nuclear-campaign coordinator for Friends of the Earth. "But this issue is going to come up again. The PSC is going to have to face up to the fact that that reactor design is not final."

Five companies, including Duke Energy and S.C. Electric and Gas, are proposing to use the same Westinghouse Electric Co. design for new reactors. SCE&G is planning two at its nuclear station in Fairfield County, with a request pending before the Public Service Commission to begin preconstruction work at the site.

The NRC and attorneys for Duke Energy said that Westinghouse's original design has been certified, but revisions are still being reviewed by the NRC.

Clements contends that means that "there is no final buildable design" and that costs could vary widely from current estimates.

Duke Energy has not released a cost estimate for its proposed reactors.

SCE&G, which is planning to build and operate its reactors in partnership with Santee Cooper, a state-owned utility, has estimated that its new reactors will cost about $10 billion.

Related News

Electricity bills on the rise in Calgary after

Calgary Electricity Price Increase signals higher ENMAX bills as grid demand surges; wholesale market volatility,…
View more

Europe's stunted hydro & nuclear output may hobble recovery drive

Europe 2023 Energy Shortfall underscores how weak hydro and nuclear offset record solar and wind,…
View more

Electricity and water do mix: How electric ships are clearing the air on the B.C. coast

Hybrid Electric Ships leverage marine batteries, LNG engines, and clean propulsion to cut emissions in…
View more

Alberta is a powerhouse for both green energy and fossil fuels

Alberta Renewable Energy Market is accelerating as wind and solar prices fall, corporate PPAs expand,…
View more

Southern California Edison Faces Lawsuits Over Role in California Wildfires

SCE Wildfire Lawsuits allege utility equipment and power lines sparked deadly Los Angeles blazes; investigations,…
View more

TVA faces federal scrutiny over climate goals, electricity rates

TVA Rates and Renewable Energy Scrutiny spotlights electricity rates, distributed energy resources, solar and wind…
View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Download the 2026 Electrical Training Catalog

Explore 50+ live, expert-led electrical training courses –

  • Interactive
  • Flexible
  • CEU-cerified