Three components of the Southern Alberta Transmission Reinforcement SATR are being temporarily delayed and Stage 3 of the project has been cancelled as a result of the Alberta Electric System Operator`s, or AESOÂ’s ongoing monitoring of transmission system conditions.

The AESO is currently conducting transmission planning analysis related to other transmission facilities in southern Alberta that will interact with various components of SATR. As a result, the following three components have been delayed: Picture Butte to Etzikom Coulee, Goose Lake to Etzikom Coulee, and Etzikom Coulee to Whitla.

The AESO has also reviewed plans for Stage 3 of SATR, a transmission line connecting the Ware Junction substation to the Langdon substation, and has cancelled this portion of the project.

“SATR is still very much needed to alleviate transmission system constraints and integrate wind generation throughout southern Alberta,” says Jerry Mossing, Vice President, Transmission Planning and Performance. “The AESO’s analysis is intended to ensure that all transmission system developments in the southern region are properly coordinated and in-service dates are aligned with regional customer connection and overall transmission system needs.”

In particular, the AESO is examining how other transmission system facilities, such as the Eastern Alberta Transmission Line and Western Alberta Transmission Line, will interact with various components of SATR.

The AESO will apply to the Alberta Utilities Commission AUC for approval of this cancellation, and anticipates filing further information with the AUC regarding the three delays in 2014.

Related News

BC Hydro cryptic about crypto mining electricity use

BC Hydro Crypto Mining Moratorium pauses high-load connection requests, as BCUC reviews electricity demand, gigawatt-hours…
View more

When will the US get 1 GW of offshore wind on the grid?

U.S. Offshore Wind Capacity is set to exceed 1 GW by 2024, driven by BOEM…
View more

Solar power growth, jobs decline during pandemic

COVID-19 Solar Job Losses are erasing five years of workforce growth, SEIA reports, with U.S.…
View more

How waves could power a clean energy future

Wave Energy Converters can deliver marine power to the grid, with DOE-backed PacWave enabling offshore…
View more

Electricity Demand In The Time Of COVID-19

COVID-19 Impact on U.S. Power Demand shows falling electricity load, lower wholesale prices, and resilient…
View more

EV Sales Still Behind Gas Cars

U.S. EV and Hybrid Sales 2024 show slower adoption versus gas-powered cars, as charging infrastructure…
View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Download the 2026 Electrical Training Catalog

Explore 50+ live, expert-led electrical training courses –

  • Interactive
  • Flexible
  • CEU-cerified