Groups argue against Greenbrier power plant

subscribe

A proposed Greenbrier County power plant isn't planning to use the best available pollution controls as required by law, three nonprofit groups argued before the state Air Quality Board recently.

If it did, it would spew out 600,000 fewer pounds of sulfur dioxide per year - half as much as its permit now allows - into the air of Greenbrier County, among other pollutants, the groups' expert witness testified.

But witnesses for Western Greenbrier Co-Generation, the power plant's developer, and the state Department of Environmental Protection, which approved the pollution controls, testified that they did follow the law, and the better scrubbers are not required.

After recent testimony, it will probably be several weeks before the board can make its ruling, chairman Michael Koon said.

The Sierra Club, West Virginia Highlands Conservancy and Greenbrier River Watershed Association filed their appeal in May, asking the state to revoke the air quality permit it had issued to WGC.

Power plants in areas with relatively unpolluted air, such as Greenbrier County, are required by law to choose the scrubbers and other pollution controls that filter out the most pollutants - unless government regulators, such as DEP, agree that those scrubbers are too expensive or otherwise infeasible.

In WGC's case, that is what happened. The best controls were declared infeasible. But Ranajit Sahu, an air pollution control expert called by the Sierra Club, said WGC's e-mails, telephone records and other evidence indicate that WGC planned to use the second-best controls all along, and tailored their legally required analysis to show that they were the only feasible choices.

WGC's permit application "had all the right words... but what appears is that the decisions were made before, and the analysis was written to justify the decisions," Sahu said.

Jerry Joseph, a Pittsburgh environmental engineer who analyzed the pollution-control choices for WGC's air quality permit application, testified that he did the analysis as the law requires.

He said the best controls were not only infeasible because of price, but also because one of them would have required a lot of water that is not available in Rainelle, where the plant is to be built.

Construction is scheduled to start on the 90-megawatt plant in spring, said Brian Neely of WGC. It has been promised $107 million from the federal Department of Energy, which bills it as a "clean coal" demonstration project. Instead of regular coal, the plant would burn a gigantic pile of abandoned coal waste near Rupert for fuel.

WGC is a limited liability company owned by the towns of Rainelle, Rupert and Quinwood.

Related News

ontario-clean-electricity-regulations

Ontario's Clean Electricity Regulations: Paving the Way for a Greener Future

OTTAWA - Ontario has taken a significant step forward in its energy transition with the introduction of new clean electricity regulations. These regulations aim to reduce carbon emissions, promote sustainable energy sources, and ensure a cleaner, more reliable electricity grid for future generations. This article explores the motivations behind these regulations, the strategies being implemented, and the expected impacts on Ontario’s energy landscape.

The Need for Clean Electricity

Ontario, like many regions around the world, is grappling with the effects of climate change, including more frequent and severe weather events. In response, the province has set ambitious targets to reduce…

READ MORE
gaza power plant

Gaza’s sole electricity plant shuts down after running out of fuel

READ MORE

Ontario introduces new 'ultra-low' overnight hydro pricing

READ MORE

nuclear power

A new nuclear reactor in the U.S. starts up. It's the first in nearly seven years

READ MORE

powerlines

Court reinstates constitutional challenge to Ontario's hefty ‘global adjustment’ electricity charge

READ MORE