Meetings set on power line upgrades
These meetings will provide an opportunity for the public, landowners, and other interested parties to review materials concerning the construction of electric utility facilities and the associated environmental impacts of the proposed Maine Power Reliability Program upgrade.
The project would consists of new construction or modifications of approximately 485 miles of 345,000 volt and 115,000 volt transmission lines and related substation improvements.
Other meetings are set for Sept. 4 in Waterville, at the Holiday Inn, 375 Main St.; and Sept. 9, in Lewiston, at the Ramada Conference Center, 490 Pleasant Street.
All three events will be held between 6:30 and 8:30 p.m.
The project is expected to cost approximately $1.4 billion and will require several state and federal regulatory permits and local approvals in approximately 80 municipalities. CMP and Public Service of New Hampshire filed an initial request in July with the Maine Public Utilities Commission.
Applications for environmental permits and local approvals will be filed late this year.
Related News

Chief Scientist: we need to transform our world into a sustainable ‘electric planet’
LONDON - I want you to imagine a highway exclusively devoted to delivering the world’s energy. Each lane is restricted to trucks that carry one of the world’s seven large-scale sources of primary energy: coal, oil, natural gas, nuclear, hydro, solar and wind.
Our current energy security comes at a price, the carbon dioxide emissions from the trucks in the three busiest lanes: the ones for coal, oil and natural gas.
We can’t just put up roadblocks overnight to stop these trucks; they are carrying the overwhelming majority of the world’s energy supply.
But what if we expand clean electricity production carried by…