New turbines give old dam a boost
Four 90-year-old turbines at the dam, which is on the Little Tennessee River, will be replaced by high-efficiency turbines and other equipment that will boost the power output of the dam by 22 megawatts and extend its life at least another 40 to 50 years, according to Alcoa.
Rick Bowen, Alcoa Energy president, made the announcement during a kick-off event for the project in Robbinsville. Cheoah was built in 1919 and is part of Alcoa Power Generating Inc.'s Tapoco Project, which also includes the Chilhowee, Calderwood and Santeetlah dams. Combined, the four provide Alcoa with 360 megawatts of power.
"Hydropower is clean, renewable, reliable and efficient," Bowen said in a prepared statement. "These attributes equal sustainability - sustainable energy and sustainable jobs."
Bowen was joined at the event by Jacques Beaudry-Losique, wind and water program manager for the Department of Energy's Office of Energy Efficiency and Renewable Energy and by U.S. Rep. Heath Shuler, D-N.C., who represents a Western North Carolina district. The Cheoah project had received a boost from a $12.95 million American Recovery and Reinvestment Act grant issued through the DOE office.
"This project will boost four turbines' generating capacity by 28 percent and serves as a terrific example of how the Recovery Act can expand clean energy while putting people to work," Beaudry-Losique said in a prepared statement.
Shuler touted the economic benefit the dam has provided to the area. Alcoa spokeswoman Christy Newman said the company has no estimate of the number of jobs that will be created by the project, but the main benefit is that the dam will be able to operate for another 50 years.
The project will replace four of the dam's five power generation units with new turbines, generators and transformers. Other plant equipment will be upgraded. The dam's fifth unit, built in 1949, was rebuilt in 1995 and will not be upgraded. In all, the improvements will boost the dam's power generation capacity to 140 megawatts. Newman said the project should have no effect on recreational use of the river.
Alcoa's smelting operation in Blount County has been idled since March 2009 when the price of aluminum plunged. Asked if the Cheoah project is part of preparations to resume the smelting operation if that becomes feasible, Newman said the project is not a pre-condition of resuming the smelter, but "it's just a good thing for the system to have that extra power."
The Cheoah project follows the recent re-licensing of the Tapoco Project by the Federal Energy Regulatory Commission. Newman said Tapoco is unrelated to another Alcoa Inc. project that has had its licensing challenged by North Carolina. Alcoa operates four dams on the Yadkin River in Badin, N.C., that once served an aluminum plant that has been closed. The North Carolina government has been lobbying the regulatory commission to allow the government to take over operation of the dams, located near Charlotte, N.C.
Related News

Western Canada drought impacting hydropower production as reservoirs run low
WINNIPEG - Severe drought conditions in Western Canada are compelling two hydroelectricity-dependent provinces, British Columbia and Manitoba, to import power from other regions. These provinces, known for their reliance on hydroelectric power, are facing reduced electricity production due to low water levels in reservoirs this autumn and winter.
While there is no immediate threat of power outages in either province, experts indicate that climate change is leading to more frequent and severe droughts. This trend places increasing pressure on hydroelectric power producers in the future.
In British Columbia, several regions are experiencing "extreme" drought conditions as classified by the federal government. BC…