Progress Energy nuclear plant repair delay extends until Q3 as crews fix reactor building containment wall delamination from steam generator replacement; insurance may offset repair and replacement power costs, with possible rate increase.
What's Happening
Progress Energy delayed a plant's restart to Q3 to fix a containment wall delamination from steam generator work.
- Return to service moved to Q3 amid containment repairs.
- $25 million spent by March; more repair costs expected.
- Insurance to cover much of repairs and replacement power.
- Possible rate increase to recover uninsured expenditures.
Repairs to the Crystal River nuclear plant will take longer than Progress Energy previously expected.
Instead of coming back online by midyear, the plant is expected to return to service in the third quarter, Progress Energy president and chief executive officer Bill Johnson said.
Progress Energy revised its estimate as it has gotten deeper into a job to repair a cracked wall in the plant's reactor building.
"We're really proceeding deliberately here according to a detailed plan," Johnson said during a conference call on the utility's first-quarter earnings.
Through the end of March, repairs had cost $25 million, with reactor costs still rising and more work to come.
Executives said they expect insurance to cover much of the costs of repairs and replacement power needed while the nuclear plant is offline. The utility has other plants, some fired by natural gas, that it can bring online at times of peak demand, and its nuclear power plans remain a strategic focus.
Without going into detail, the company suggested it could seek a rate increase to recoup repair costs not covered by insurance.
So far, however, Progress Energy does not know what the total repair project will cost, it doesn't have a running tab on what replacement power has cost and can't say exactly how much insurance will pay, spokeswoman Wendy Horne said.
The company powered down the nuclear plant in September for a major maintenance project that was expected to be done by the end of December.
But shortly after the job began, workers discovered that part of the containment wall had separated into two layers.
The void was discovered as workers cut a 25- by 27-foot hole in the containment wall so two huge steam generators could be removed and replaced. The utility cut the hole because the reactor building's regular equipment hatch is too small for the generators, which weigh 550 tons each.
The gap is known as a delamination in concrete structures, which means part of the wall has separated into two layers. The gap between those two layers is up to 2 inches wide, and it lies about 9 inches below the outer surface of the wall, which is 42 inches thick.
The company's analysis of what caused the crack is still under way, but it has said it plans to replace the layer of concrete that separated from the building. Workers are in the latter stages of removing the outer layer.
Related News
Related News
BC Hydro Expects To See Electricity Usage Rise This Holiday Season
Ontario Extends Off-Peak Electricity Rates to Provide Relief for Families, Small Businesses and Farms
Mike Sangster to Headline Invest in African Energy Forum
UK peak power prices rise to second highest level since 2018
India Electricity Prices are Spiking
Hydro-Québec puts global ambitions on hold as crisis weighs on demand
Sign Up for Electricity Forum’s Newsletter
Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.
Electricity Today T&D Magazine Subscribe for FREE
- Timely insights from industry experts
- Practical solutions T&D engineers
- Free access to every issue