Texas utilities commission approves transmission line


Protective Relay Training - Basic

Our customized live online or in‑person group training can be delivered to your staff at your location.

  • Live Online
  • 12 hours Instructor-led
  • Group Training Available
Regular Price:
$699
Coupon Price:
$599
Reserve Your Seat Today

North Edinburg to Loma Alta 345 kV Line approved by PUCT and endorsed by ERCOT, bolstering grid reliability and economic development in the Lower Rio Grande Valley and Brownsville with a critical double-circuit transmission upgrade.

 

Context and Background

A 96-mile, PUCT-approved 345 kV line linking North Edinburg and Loma Alta to strengthen ERCOT grid reliability.

  • PUCT approved construction of approx 96-mile 345 kV double-circuit line.
  • Western half by ETT; eastern half by Sharyland Utilities.
  • ERCOT endorsed the project as critical for Brownsville reliability.
  • Route spans Hidalgo and Cameron counties, paralleling US 281.

 

The Public Utility Commission of Texas PUCT in late March 2014 unanimously approved an application by Electric Transmission Texas, LLC ETT and Sharyland Utilities, L.P. Sharyland to build a 345-kilovolt kV transmission line from a substation northwest of the city of Edinburg to a substation located east of the city of Brownsville. The cost of the project is estimated to total $309 million and is expected to be completed during the summer of 2016.

 

The PUCT commissioners approved construction of the new approximately 96-mile line that would extend from the existing AEP Texas Central Company North Edinburg Substation to the existing Brownsville Public Utilities Board Loma Alta Substation located near the Brownsville Ship Channel. The western half of the line will be constructed, owned and operated by ETT, while the eastern half will be constructed and operated by Sharyland Utilities, L.P., illustrating how utilities team up on regional grid projects today.

The approved route runs generally east from the North Edinburg Substation and, after approximately 7.5 miles, turns south continuing past the city of Donna. Approximately 2 miles north of U.S. Highway 281, the route turns east, roughly paralleling the north side of U.S. Highway 281 until the city of Rangerville, where it turns north-northeast toward the city of San Benito. It then continues east around the northern and eastern sides of Brownsville, near the Texas-Mexico DC tie corridor in the region, ultimately terminating at the Loma Alta Substation.

“When we first filed our joint application in July 2013, we emphasized that this transmission line is needed to ensure continued reliable electric service for the Lower Rio Grande Valley, which is forecast to have continued electrical demand growth,” said ETT President Calvin Crowder, who noted recent ETT transmission work in West Texas as context. “The need has grown since that time, and the Electric Reliability Council of Texas ERCOT has determined this project is critical for the reliability of the ERCOT system and, specifically, the Brownsville area.”

“This project will not only improve both the reliability and stability of the grid in the Lower Rio Grande Valley, it also will provide a real engine for economic growth in communities throughout the region,” said Sharyland President Mark Caskey, noting that Texas retailers such as TXU Energy depend on robust transmission to serve customers. “A reliable, large-scale source of electric power is absolutely critical in attracting new investment and economic development, especially for communities like Brownsville.”

ERCOT endorsed the project in January 2012. Since that time, ETT and Sharyland have worked with an experienced routing consultant to perform an environmental assessment and routing analysis for the proposed transmission line. In addition, public input was gathered at jointly hosted public open houses in October 2012 and February 2013.

The application was filed in July 2013 under PUCT Docket No. 41606 – joint application of Electric Transmission Texas, LLC and Sharyland Utilities, L.P. to Amend Their Certificates of Convenience and Necessity for the Proposed North Edinburg to Loma Alta Double-Circuit 345 kV Transmission Line in Hidalgo and Cameron Counties, Texas.

Related News

Canada's nationwide climate success — electricity

Canada Clean Electricity leads decarbonization, slashing power-sector emissions through coal phase-out, renewables like hydro, wind,…
View more

Britons could save on soaring bills as ministers plan to end link between gas and electricity prices

UK Electricity-Gas Price Decoupling aims to reform wholesale electricity pricing under the Energy Security Bill,…
View more

Manitoba Hydro seeks unpaid days off to trim costs during pandemic

Manitoba Hydro unpaid leave plan offers unpaid days off to curb workforce costs amid COVID-19,…
View more

Shocking scam: fraudster pretending to be from BC Hydro attempts to extort business

BC Hydro Bitcoin Scam targets small businesses with utility impersonation, call spoofing, and disconnection threats,…
View more

Is The Global Energy Transition On Track?

Global Decarbonization Strategies align renewable energy, electrification, clean air policies, IMO sulfur cap, LNG fuels,…
View more

Court quashes government cancellation of wind farm near Cornwall

Nation Rise Wind Farm Ruling overturns Ontario cancellation, as Superior Court finds the minister's decision…
View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Live Online & In-person Group Training

Advantages To Instructor-Led Training – Instructor-Led Course, Customized Training, Multiple Locations, Economical, CEU Credits, Course Discounts.

Request For Quotation

Whether you would prefer Live Online or In-Person instruction, our electrical training courses can be tailored to meet your company's specific requirements and delivered to your employees in one location or at various locations.