Transmission process needs to be cleaned up


CSA Z463 Electrical Maintenance -

Our customized live online or in‑person group training can be delivered to your staff at your location.

  • Live Online
  • 6 hours Instructor-led
  • Group Training Available
Regular Price:
$249
Coupon Price:
$199
Reserve Your Seat Today
Things are adrift in places around the country. In the northeast, for example, the states all have renewable portfolio standards while they also participate in a regional greenhouse gas initiative, all of which is meant to cleanse the air and cut global warming pollutants.

The dilemma there and elsewhere is that the transmission line permitting process is tumultuous and impedes those goals.

While there have been increases since 1998, FERC says that the level is still less than what was invested in 1975. Over the same time period, however, the demand for electricity has doubled. That's resulted in a significant decrease in transmission capacity, requiring new lines get built.

Transmission limitations, in fact, are a major barrier to the growth of renewable energy. The process is meant to be inclusive and to elicit the views of all stakeholders. Regulators should strive for reasonable compromises. But if such deals cannot be reached, then they must seek to achieve the greatest good for the greatest number. Transmission planning requires it. And so does the federal law.

A recent U.S. Department of Energy study found that wind alone could provide 20 percent of U.S. electricity by 2030. To do so, though, significantly more investment in transmission is needed. Not only is there is competition among all types of generators to carry their electrons in the current lines but new lines are necessary to transport wind resources from the remote locations where they are most abundant.

"As renewable energy becomes more popular, the request to move these resources is growing," says John Bear, president of the Midwest Independent System Operator (ISO) at the Edison Electric Institute's annual conference in Toronto. "There is not enough infrastructure" — a situation that denies utilities access to lower cost generation.

The Midwest ISO, in fact, has determined that adding 5,000 miles of new transmission to transport wind from the Dakotas to the New York City area would result in substantial savings for customers. While the generation and transmission costs would total $13 billion, the grid operator says that customers would save about $600 million annually. In the case of New England, a greater investment in transmission has paid off, enabling prices to fall in congested areas such as Southwest Connecticut.

But more needs to be done there and elsewhere around the nation. To supply 20 percent of the electric generation market by 2030, the Energy Department estimates that $60 billion in new wires would be necessary — something that the agency says would cut greenhouse gas emissions by 25 percent.

The objective is to provide reliable, cost-effective and diverse energy resources to customers. Federal regulators have been given more authority to site projects. Now it's up to the Federal Energy Regulatory Commission and the North American Electric Reliability Corp. (NERC) that reports to it to carry out and enforce compulsory standards that could add greater certainties and bring innovative projects to the fore.

To succeed, federal regulators advise utilities to begin the process early — to meet with all constituents well in advance of filing the initial paperwork. It's about ensuring that the procedure is inclusive and transparent. They must understand the legitimate concerns of the stakeholders involved. It's about building relations with the business community, environmental groups, landowners, public officials and the press.

"You don't want neighbors to fear the project," says Jane Peverett, CEO of the BC Transmission Corp., at the Edison meeting. "The process must be fair and open. The people must have a say and have access to credible third parties."

In theory, utilities are supposed to have an easier time constructing new lines. The Energy Policy Act of 2005 sets out to give federal regulators the ability to override state regulators if key projects are unnecessarily delayed. It also allows them to provide some financial incentives to entice investors to spend capital on transmission projects, which have been considered risky because they can take years to come on line.

As a result, transmission investment has declined in real terms — adjusted for inflation — from 1975 to 1998. While there have been increases since 1998, FERC says that the level is still less than what was invested in 1975. Over the same time period, however, the demand for electricity has doubled. That's resulted in a significant decrease in transmission capacity, requiring new lines get built.

NERC is particularly concerned about Southern California, which depends on imported power that is transported across heavily burdened transmission lines. At the same time, the state has increased renewable energy initiatives and now requires the major utilities there to provide 20 percent of their power from green sources by 2010.

Those requirements and the current congestion are the reasons behind San Diego Gas & Electric's effort to build the Sunrise Powerlink transmission line. It's also the basis for Southern California Edison decision to spend $15.5 million on transmission and distribution, of which $2.1 billion will be dedicated to carrying renewable sources.

"The nation has tremendous renewable energy reserves, but the existing electric transmission system was not designed to tap these new kinds of generation," says Don Furman, senior vice president at Iberdrola Renewables. "The good news is that we have the opportunity to solve both problems at once, while strengthening our economy, the environment, and energy security."

Investing in infrastructure has always been a tough sell. Private entities have limited resources and the pay off is often too distant. But the transmission grid is aging and it needs to be updated and expanded so that it can meet the expected future demand for power. Doing so would give utilities the access they need to clean generation while also helping to increase the reliability of the grid.

Related News

Rolls-Royce expecting UK approval for mini nuclear reactor by mid-2024

Rolls-Royce SMR UK Approval underscores nuclear innovation as regulators review a 470 MW factory-built modular…
View more

Electricity rates are about to change across Ontario

Ontario Electricity Rate Changes lower OEB Regulated Price Plan costs, adjust Time-of-Use winter hours and…
View more

How Energy Use Has Evolved Throughout U.S. History

U.S. Energy Transition traces the shift from coal and oil to natural gas, nuclear power,…
View more

Effort to make Philippines among best power grids in Asia

NGCP-SGCC Partnership drives transmission grid modernization in the Philippines, boosting high-voltage capacity, reliability, and resilience,…
View more

Manitoba Hydro seeks unpaid days off to trim costs during pandemic

Manitoba Hydro unpaid leave plan offers unpaid days off to curb workforce costs amid COVID-19,…
View more

Electricity prices spike in Alberta

Alberta electricity price spike drives 25% CPI surge amid heatwave demand, coal-to-gas conversions, hydro shortfalls,…
View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Download the 2026 Electrical Training Catalog

Explore 50+ live, expert-led electrical training courses –

  • Interactive
  • Flexible
  • CEU-cerified