Violent weather has delayed construction on Germany's first offshore wind farm, a consortium of companies planning the project said.

The plan was to place the first three foundations — each weighing 700 tons (635 metric tons) and standing some 147 feet (45 meters) high — by the first week of September.

But the wind they hope eventually to reap is causing construction setbacks, and ocean waves are cresting too high.

"We've had a really, really shocking summer," said Jonny Stokes, a spokesman for E.ON AG, one of three energy companies partnering in the project. Vattenfall Europe and RWE are the two other participants.

Crews are waiting for a four-day block of good weather to install the three foundations for the first of 12 five-megawatt turbines nearly 28 miles (45 kilometers) off the shores of Borkum Island in the North Sea.

The project is farther offshore than any other wind farm and in deeper waters — factors that have worked against it.

"Offshore conditions are challenging," Stokes said, but insisted the benefits were still significant.

"The consistency and quality of the wind is better further offshore. You get a better load factor for the turbines," he said.

Stokes was optimistic about the project though, given the construction hazards.

"This is technically difficult," he said. "It's basically a pioneering project in the sense that it is in deep water and so far offshore."

The window for setting the foundations will close in October. If they can get the first three foundations installed by October, then the first phase should be on track to finish by spring or summer of next year.

So far, onshore work has gone according to plan, said Lutz Wiese, a spokesman for Vattenfall.

The foundation for an onshore transformer station is up, and work to erect the offshore transformer station — which only needs a 36-hour window for construction — is slated to start in mid-September.

Related News

TotalEnergies to Acquire German Renewables Developer VSB for US$1.65 Billion

TotalEnergies VSB Acquisition accelerates renewable energy growth, expanding wind and solar portfolios across Germany and…
View more

Electric Ferries Power Up B.C. with CIB Help

BC Ferries Electrification accelerates zero-emission vessels, Canada Infrastructure Bank financing, and fast charging infrastructure to…
View more

"It's freakishly cold": Deep freeze slams American energy sector

Texas Deep Freeze Energy Crisis strains grids as polar vortex triggers rolling blackouts, record natural…
View more

Clorox accelerates goal of achieving 100% renewable electricity in the U.S. and Canada to 2021

Clorox Enel 70 MW VPPA accelerates renewable energy, sourcing Texas solar from the Roadrunner project…
View more

Schneider Electric Aids in Notre Dame Restoration

Schneider Electric Notre Dame Restoration delivers energy management, automation, and modern electrical infrastructure, boosting safety,…
View more

Florida Court Blocks Push to Break Electricity Monopolies

Florida Electricity Deregulation Ruling highlights the Florida Supreme Court decision blocking a ballot measure on…
View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Download the 2026 Electrical Training Catalog

Explore 50+ live, expert-led electrical training courses –

  • Interactive
  • Flexible
  • CEU-cerified