Power Brokers Say New Ontario Power Market Date Not Firm Enough

CALGARY - -- Power brokers called on Ontario to set a firm date for its electricity market opening - and stick to it, after provincial agencies pointed to a March 1, 2002, deadline this week.

The new timetable - the fourth adjusting of dates since 1999 - will increase costs for established firms and could further erode interest of potential investors, energy representatives said Friday.

"Our major concern is the historical pattern of delays that we've had with Ontario market opening," Ron Milnthorp, president of Enron Canada said.

"We can't invest capital on a conditional basis, and, therefore, we need an unconditional market opening."

Earlier this year, Enron Canada put a C$200-million power plant project for southwestern Ontario on hold after Premier Mike Harris set back an expected May market opening indefinitely.

The revamped market readiness testing schedule released by the Independent Electricity Market Operator and the Ontario Energy Board Tuesday extends retail and wholesale testing to December and February, and includes fines of up to C$10,000 a day for late completion.

"We are doing out best to meet what we think is a realistic deadline," IMO spokesman Kevin Dove said.

Milnthorp said Enron Canada now is more optimistic the government will stick to a spring 2002 date.

Technical difficulties were blamed in setting back deregulation from May to this November, and from fall of 2000.

Critics also say the California crisis, which saw electricity prices skyrocket in that state, caused the Ontario government to delay deregulation to placate nervous consumers. The uncertainty has cost an estimated C$3 billion from proposed power plants being put on hold, "Any further delay will have severe implications on investor confidence in the market," TransAlta (T.TA) spokesman Adam White warned from Toronto.

This summer TransAlta (T.TA), Canada's largest investor-owned power generator, said it would defer any new investment in Ontario because of market uncertainty.

Work on the corporation's C$400-million Sarnia cogeneration plant continued, however, and it will start producing power in spring of 2002. The latest market delay just means TransAlta won't have the benefit of watching the market and trading in it before commissioning the plant, White said.

Smaller retail distributors are being blamed in part for the delay because of difficulties setting up new billing and accounting systems.

Toronto Hydro has offered to help other retailers set up their systems to get deregulation up and running.

"Every day we don't have market-opening date, we have money going out," spokesman Stephen Andrews said. "It is a significant cost in terms of opportunity."

Final approval for market opening will have to be given by the provincial government, which so far has refused to set a firm date.

Related News

BC Hydro cryptic about crypto mining electricity use

VANCOUVER - In its Nov. 1, 2022 load update briefing note to senior executives of the Crown corporation, BC Hydro shows that the entire large industrial sector accounted for 6,591 gigawatt-hours during the period – one percent less than forecast in the service plan.

BC Hydro censored load statistics about crypto mining, coal mining and chemicals from the briefing note, which was obtained under the freedom of information law because it feared that disclosure would harm Crown corporation finances and third-party business interests.

Crypto mining requires high-powered computers to run and be cooled around the clock constantly. So much so that cabinet…

READ MORE
tidal power

Canada Makes Historic Investments in Tidal Energy in Nova Scotia

READ MORE

substation

Attacks on power substations are growing. Why is the electric grid so hard to protect?

READ MORE

Gravity power holds major promise for the decarbonization of electricity grids

READ MORE

Energy crisis: EU outlines possible gas price cap strategies

READ MORE