Duke Energy brings two wind projects on line

CHARLOTTE, NORTH CAROLINA - Two Duke Energy wind power projects recently under construction in Pennsylvania and Wyoming are now on line and generating clean, renewable electricity. The company also announced that Siemens Energy will join General Electric as a wind turbine supplier for a 200-megawatt wind farm Duke Energy is planning to build near Casper, Wyoming.

Duke Energy's 70-megawatt (MW) North Allegheny Windpower Project is producing electricity for FirstEnergy under a long-term power purchase agreement (PPA). Duke Energy assumed ownership of the development project — located in Blair and Cambria counties, Pennsylvania, roughly 95 miles east of Pittsburgh — from Gamesa Energy USA earlier this year. North Allegheny represents Duke Energy's first commercial wind farm in the eastern U.S.

Duke Energy also recently brought its 42-MW Silver Sage Windpower Project in Cheyenne, Wyoming, on line. Silver Sage is the company's second wind farm in the area; the nearby 29-MW Happy Jack Windpower Project entered commercial operation in September 2008. Under the terms of two long-term PPAs, Duke Energy will sell all of the electricity generated at Silver Sage to Cheyenne Light Fuel & Power, a utility subsidiary of Black Hills Corp., and Colorado-based Platte River Power Authority.

In addition, Duke Energy has finalized its wind turbine supply plans for the 200-MW Top of the World Windpower Project, which is scheduled for construction in Converse County, Wyo., in 2010. In addition to the already announced 66 General Electric 1.5-MW turbines to be installed at the site, Duke Energy has entered into a supply agreement with Siemens Energy for 44 turbines, each capable of generating 2.3 MW.

Construction work at the Top of the World site is expected to begin in early 2010 upon receipt of all necessary permits from the state. PacifiCorp signed a long-term PPA with Duke Energy in late August to buy all of the renewable power that will be generated by the Top of the World project.

With North Allegheny and Silver Sage now on line, Duke Energy has 634 MW of wind power in commercial operation. That total will increase to 733 MW by the end of the year, when final commissioning at Duke Energy's recently constructed 99-MW Campbell Hill Windpower Project — also in Converse County, Wyo. — is complete.

Related News

Energiepark Mainz

Renewable power surpasses fossil fuels for first time in Europe

LONDON - Renewable power for the first time contributed a bigger share in the European generation mix than fossil fuels as the fallout from the pandemic cut energy demand.

About 40 percent of the electricity in the first half in the 27 EU countries came from renewable sources, compared with 34 percent from plants burning fossil fuels, according to environmental group Ember in London. As a result, carbon dioxide emissions from the power sector fell 23 percent.

The rise is significant and encouraging for law makers as Europe prepares to spend billions of euros to recover from the virus and set the…

READ MORE
fuel-cell-electric-buses-coming-to-mississauga

Fuel Cell Electric Buses Coming to Mississauga

READ MORE

 Jeremy Norman

SaskPower eyes buying $300M worth of electricity from Flying Dust First Nation

READ MORE

Smaller, cheaper, safer: Next-gen nuclear power, explained

READ MORE

uk windpower

How offshore wind energy is powering up the UK

READ MORE