Low demand delays nuclear plant 5 years


Protective Relay Training - Basic

Our customized live online or in‑person group training can be delivered to your staff at your location.

  • Live Online
  • 12 hours Instructor-led
  • Group Training Available
Regular Price:
$699
Coupon Price:
$599
Reserve Your Seat Today

Temelin nuclear expansion delay shifts two new reactors to 2025 as CEZ cites weak power demand, grid upgrades, and a 110-km transmission line; bidders include Areva, Westinghouse, and AtomStroyExport in South Bohemia tender.

 

The Main Points

CEZ postponed Temelin's two VVER-1000 units to 2025, citing weak demand, grid limits, and a protracted vendor tender.

  • Completion target moved from 2020 to 2025
  • Demand slump reduces need for new generation
  • 110-km transmission line required for grid capacity
  • Areva, Westinghouse, AtomStroyExport in 2013 tender

 

Czech power giant CEZ as has announced that its Temelin nuclear power project will be delayed for five years due to weak electricity demand.

 

The controversial nuclear power plant was supposed to add two new reactors by 2020, but the company's chief executive, Martin Roman, has now admitted that the project will be put on the back burner, a shift echoed by the cabinet's postponed vote on the nuclear power plan, with the completion date set for 2025. Speaking to representatives of the government's environmental agency, Roman said completing the project by 2020 is no longer feasible because there will not be enough demand for the new power.

"Power consumption has reverted to what it was years ago because of the economic crisis," Roman said. "Power consumption in Germany in 2009 returned to the same level it was in 1992 — that is, 18 years ago. Consumption in the Czech Republic has slumped to the level it was in 2005."

Temelin is a 2,000-megawatt MW facility in South Bohemia and is the biggest power producer in the Czech Republic, where the utility received bids for new reactors, reflecting ongoing expansion plans. It uses VVER-1000, Type V 320 pressurized water reactors.

It was originally designed to have four reactors but was limited to two by the government in 1993. Ever since then, CEZ has been fighting to get the other two blocks built. The company finally won its battle in April 2009, with South Bohemian authorities voting overwhelmingly to lift the ban and allow the construction of the two new units.

Other factors contributing to the delay of the Temelin expansion project include the need to construct a new 110-kilometer power line to Temelin, Roman said, while Romania's project departures highlight regional risks as well.

The three bidders in the tender process for Temelin are Areva S.A., Westinghouse Electric Company LLC, whose Westinghouse bid has been submitted, and a consortium of companies led by Russia's AtomStroyExport. A winner will not be chosen until 2013, and the construction process will take an estimated 12 years.

In related news, Unit 3 of CEZ's older Dukovany Nuclear Power Station, which is 30 kilometres southeast of Třebíč, was shut down one weekend for a planned 33-day refuelling operation, while in Romania debates over French technology costs continue in the sector.

 

Related News

Related News

Grounding and Bonding and The NEC - Section 250

Electrical Grounding and Bonding NEC 250 Training equips electricians with Article 250 expertise, OSHA compliance…
View more

Power Outage Disrupts Travel at BWI Airport

BWI Power Outage caused flight delays, cancellations, and diversions after a downed power line near…
View more

BC Hydro suspends new crypto mining connections due to extreme electricity use

BC Hydro Cryptocurrency Mining Suspension pauses new grid connections for Bitcoin data centers, preserving electricity…
View more

California Regulators Face Calls for Action as Electricity Bills Soar

California Electricity Rate Hikes strain households as CPUC weighs fixed charges, utility profit caps, and…
View more

Can Canada actually produce enough clean electricity to power a net-zero grid by 2050?

Canada Clean Electricity drives a net-zero grid by 2035, scaling renewables like wind, solar, and…
View more

'Unlayering' peak demand could accelerate energy storage adoption

Duration Portfolio Energy Storage aligns layered peak demand with right-sized batteries, enabling peak shaving, gas…
View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Download the 2026 Electrical Training Catalog

Explore 50+ live, expert-led electrical training courses –

  • Interactive
  • Flexible
  • CEU-cerified