New Darlington units needed: Ministry


CSA Z463 Electrical Maintenance -

Our customized live online or in‑person group training can be delivered to your staff at your location.

  • Live Online
  • 6 hours Instructor-led
  • Group Training Available
Regular Price:
$249
Coupon Price:
$199
Reserve Your Seat Today

Ontario nuclear reactor replacement faces scrutiny as OPG awaits a federal panel review, citing the long-term energy plan, 2,000 MW capacity, Darlington and Bruce refits, and nuclear waste ethics versus renewables and demand forecasts.

 

At a Glance

2,000 MW plan to replace retiring reactors, pending review and disputes over nuclear waste, demand, and renewables.

  • Replaces capacity lost from Pickering A and B retirements
  • 2,000 MW new-build holds nuclear share, not an expansion
  • OPG awaits federal environmental panel report in August
  • CELA challenges need, ethics, and nuclear waste disposal
  • Ministry projects long-term demand growth; renewables disputed

 

Building new nuclear units at Ontario Power Generation’s Darlington station does not signal an increase in the province’s reliance on nuclear power, the energy ministry says.

 

Instead, it’s simply a plan to replace aging reactors that will likely go out of service by the end of the decade.

But the Canadian Environmental Law Association argues that building new reactors is unethical because Canada still has no firm plan on how to deal with toxic nuclear waste, leaving questions left unanswered for communities and regulators.

The comments have been filed in closing submissions to a federal panel probing the environmental impact of the proposed new reactors and related infrastructure.

The panel will file a report in August with the environment minister. Depending on the government’s response, it can authorize Ontario Power Generation OPG to prepare the site for new units as required.

OPG still hasn’t decided what kind of units it will build, and the expiry of the AECL bid has complicated setting a cost estimate for the multi-billion-dollar project.

The new units would supply 2,000 megawatts of generating capacity. That’s about one-tenth of the power needed to supply the province on a moderate spring or fall day, underscoring the scale of a huge nuclear plant for Ontario.

The energy ministry’s submission says the new units are in line with the province’s long-term energy plan and, amid a nuclear renaissance, will simply hold the line on nuclear capacity, which now supplies about half the province’s electricity.

“Far from being an expansion of nuclear as claimed by several intervenors, 2,000 megawatts of new-build would in effect result in the replacement of about half of the total capacity at the Pickering A and B stations, which are expected to be out of service post-2020,” the ministry says.

Existing reactors at Darlington and at the Bruce nuclear site operated by Bruce Power will undergo mid-life refits over the next decade.

The ministry argues that demand for power will grow over the next 20 years.

Power use peaked in Ontario in 2005 and has retreated modestly since then, but the ministry argues that’s not a long-term trend.

“Some intervenors have cited reports that claim electricity usage in Ontario could be reduced dramatically over the next 10 to 20 years without offering any credible evidence,” it says.

“Such reductions would be unprecedented internationally in the absence of a falling population and a declining economy.”

The Canadian Environmental Law Association argues, however, that neither OPG nor the ministry has proven the need for the new reactors.

The ministry’s projections show no growth in power demand for the next decade, but it then “inexplicably predicts a huge increase in total electricity demand” in the 2020s, the association’s submission says.

The ministry further assumes no increase in renewable generation will occur during the decade, it says.

The association also notes that a long-term disposal solution for nuclear waste still hasn’t been found.

“It is not ethical to entertain a plan to construct a facility that will produce new nuclear waste from new reactors when there is currently no permanent solution to the high level fuel waste and other radioactive waste already being produced from existing reactors,” it argues.

 

Related News

Related News

N.S. joins Western Climate Initiative for tech support for emissions plan

Nova Scotia Cap-and-Trade Program joins Western Climate Initiative to leverage emissions trading IT systems, track…
View more

Alberta sets new electricity usage record during deep freeze

Alberta Electricity Demand Record surges during a deep freeze, as AESO reports peak load in…
View more

Wyoming wind boost for US utility

Black Hills Energy Corriedale Wind Farm Expansion earns regulatory approval in Wyoming, boosting capacity to…
View more

Town of Gander forgives $250K debt from local curling club

Gander Curling Club Debt Forgiveness Agreement explained: town council tax relief, loan write-off conditions, community…
View more

EasyPower Webinars - August and September Schedule

EasyPower Webinars deliver expert training on electrical power systems, covering arc flash, harmonics, grounding, overcurrent…
View more

Biggest offshore windfarm to start UK supply this week

Hornsea One Offshore Wind Farm delivers first power to the UK grid, scaling renewable energy…
View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Download the 2026 Electrical Training Catalog

Explore 50+ live, expert-led electrical training courses –

  • Interactive
  • Flexible
  • CEU-cerified