Carson-Suffolk-Thrasher transmission lines will expand South Hampton Roads' electric grid capacity with new 500 kV and 230 kV high-voltage infrastructure, boosting reliability, preventing rolling blackouts, and supporting growing demand across southeastern Virginia.

 

Inside the Issue

Dominion's high-voltage upgrade linking Carson, Suffolk, and Chesapeake to boost capacity, reliability, and resilience.

  • 60-mile 500 kV line from Carson to Suffolk along US 460
  • 21.5-mile 230 kV line from Suffolk to Chesapeake
  • 330 towers, 700 acres cleared, 260 easements negotiated
  • SCC-approved after environmental and historic reviews
  • Aims to prevent rolling blackouts and support EV growth

 

By the summer of 2011, demand for electricity in South Hampton Roads and on the Outer Banks will surpass what the region's power grid can reliably bear.

 

If nothing were done, outages that the system can absorb today could cause rolling blackouts across the region.

Help is on the way. After three years of prep work, the largest transmission line to join South Hampton Roads' power grid since 1985 is about to rise over the countryside.

The project, a two-part addition known officially as the "Carson-Suffolk-Thrasher 500 kV and 230 kV transmission lines," will address the region's capacity problems for the foreseeable future, according to Dominion Virginia Power.

The heavy lifting has only begun. Dominion, which expects to spend at least $223 million on the project, has about 260 easements to negotiate, 700 wooded acres to clear and 330 massive towers to erect and string with cable. If all that goes as planned, the tree-cutting will reach Suffolk by next summer, and someone will flip a switch on the whole thing the following spring.

From there, hundreds of thousands of people in southeastern Virginia will begin to rely on the transmission lines for their homes, their businesses, maybe even their cars. South Hampton Roads pulls much of its electricity from elsewhere because it uses more than it generates, and the demand is growing, said Liz Harper, a senior siting and permitting specialist for Dominion.

"People now have two, three televisions or more," Harper said. "They buy a new refrigerator, they put the old one in the garage."

Dominion's new transmission lines became an official project in early 2006, after the utility filed a request with regulators, but company planners began to identify the need years earlier.

Models showed the region's system would fall out of compliance with regulatory standards by summer 2011 - a position that could cost Dominion up to $1 million a day in fines, a company official told the State Corporation Commission of Virginia in 2007.

Peter Nedwick, a Dominion consulting engineer, told the SCC that failure to address the expected shortcomings "could lead to potential rolling blackouts, significantly impacting the region's economy as well as service to critical governmental facilities."

In July 2006, the company began exploring where to build, while also studying an offshore wind power line for future options. It winnowed the thousands of potential routes by talking to government officials, holding workshops and looking at variables such as housing densities and wetlands.

The utility avoided one area of the Nottoway River after a property owner told Dominion about a Native American archaeological site there, Harper said.

In 2007, Dominion settled on two possible routes, each of which brought power from the company's Carson substation in Dinwiddie County. Its preferred choice, which ultimately won out, ran into Suffolk along U.S. 460.

The company flew a helicopter over both routes with a laser that recorded a 300-foot-wide swath for engineers to study. That gave them "thousands and thousands" of data points, said Steve Quarberg, a Dominion electric transmission projects manager.

Another survey located all the property lines so Dominion could gather the necessary plats and negotiate with landowners. Dominion will buy some of the property it needs for its 60-mile 500-kV line, but in the vast majority of cases it will try to buy an easement from the owner, Quarberg said.

Those who refuse a deal may face condemnation.

Parts of the 500-kV line will parallel existing lines, reducing the amount of new land that the company needs.

The 230-kV portion of the project, a 21.5-mile line that will run from Suffolk to Chesapeake, will use existing Dominion right of way, where it already has lines.

Review of the project included an environmental impact study, public hearings and input from the Virginia Department of Historic Resources and the Virginia Department of Game and Inland Fisheries. All that led to approval from Virginia regulators last Oct. 31.

Dominion began clearing the route in April. Tree clearing along the 60-mile path and its 150-foot-wide right of way is expected to reach Suffolk sometime next summer, Quarberg said.

While crews finish clearing the route, others will begin installing the first foundations for transmission line towers, possibly in January.

A plant in Monterrey, Mexico, is now fabricating prototypes for the lattice steel structures. The job for SAE Towers will use about 4,500 tons of steel, said Cesar Aguilar, commercial manager at the plant. The biggest pieces of steel will come exclusively from U.S. mills, he said.

Production will be spread over about 10 months, with SAE sending the towers in batches by truck, while BC line construction highlights similar timelines elsewhere, Aguilar said.

In Virginia, Dominion's five-person assembly crews might need a week and a half to build their first tower, Quarberg said. As they get more familiar with the job, they might be able to do as many two a week, he said.

When built, the towers will stand 130 feet high and weigh between 11 tons and 35 tons a piece, depending on the type. After enough are standing, workers will begin to pull cables across their 1,000-foot expanses. The line will arrive 14,100 feet at a time, on huge reels with 9-foot diameters.

Nationally, the work will join a growing number of large electrical transmission projects, Appalachian Power upgrades among them, Aguilar said. It's been almost 20 years since the United States saw so many upgrades to its grids, he said.

Dominion's new project will join the company's 6,000 miles of transmission lines, which feed its 54,000 miles of distribution lines, which ultimately feed countless appliances, iPods and light bulbs.

When all the new towers are built and the conductor cables reach their destination, a lot of "detail stuff" must be done, Quarberg said. Among other things, workers will check that they have connected "A to A and B to B and C to C, and not A to B, because that would not be very good," he said.

There will be a final inspection along the entire line, because portions of it will have been waiting to go for months. Then the system operator will energize it by throwing a switch to close a breaker, which Quarberg described as similar to circuit breakers on a house.

Related News

Medicine Hat Grant Winners to Upgrade Grid and Use AI for Energy Savings

Medicine Hat Smart Grid AI modernizes electricity distribution with automation, sensors, and demand response, enhancing…
View more

Canadian Gov't and PEI invest in new transmission line to support wind energy production

Skinners Pond Transmission Line expands PEI's renewable energy grid, enabling wind power integration, grid reliability,…
View more

Russian Strikes Threaten Ukraine's Power Grid

Ukraine Power Grid Attacks intensify as missile and drone strikes hit substations and power plants,…
View more

The nuclear power dispute driving a wedge between France and Germany

Franco-German Nuclear Power Divide shapes EU energy policy, electricity market reform, and decarbonization strategies, as…
View more

Economic Crossroads: Bank Earnings, EV Tariffs, and Algoma Steel

Canada Economic Crossroads highlights bank earnings trends, interest rates, loan delinquencies, EV tariffs on Chinese…
View more

Trump declares end to 'war on coal,' but utilities aren't listening

US Utilities Shift From Coal as natural gas stays cheap, renewables like wind and solar…
View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Download the 2026 Electrical Training Catalog

Explore 50+ live, expert-led electrical training courses –

  • Interactive
  • Flexible
  • CEU-cerified