No more free hookups for new homes

subscribe

There'll be no more free electrical hookups for new homes served by the Coos-Curry Electric Cooperative.

"We used to give transformers and meters for free," General Manager Roger Meader told the dozen co-op members attending a Town Hall meeting in Gold Beach recently.

"Nothing is free in the future."

Meader said the co-op's board of directors voted at their January meeting to start the new policy effective Feb. 1.

The new policy modifies the cooperative's line extension practices with the most significant change being in the amount the member requesting new service installation must pay.

The cooperative previously provided a suitable transformer or meter for each new service.

"The policy guidelines have been adjusted over the years, but the bottom line is, the days of putting in free services are gone and now we must start asking new members to pay for the services they are asking us to provide," Meader said.

Members applying for new service will receive a written estimate for the cost of a new line extension, a modification of existing service or providing temporary power.

The policy says costs may include, but are not limited to: materials; labor and transportation costs; permit fees; filing fees; independent consultants; and contractors.

Payment based on the estimate must be made before construction begins and will be adjusted after the work is completed and the actual cost of construction is determined.

All new installations or modifications to existing electrical services must comply with the latest revisions of the National Electric Safety Code, county building codes, electrical codes and CCEC's construction standards.

"We buy all stainless steel transformers at a high cost," Meader said. "If you live in Bend, where you don't need stainless steel, it's a lot cheaper."

He said Coos-Curry spends $850,000 to $1 million a year for transformers.

"We want to make sure that we protect the integrity of the system and that the services we install will withstand the harsh coastal climate we have here," he said.

He said the policy will begin Feb. 1 to allow proper notification to city and county building departments for Coos and Curry counties, electrical contractors, realtor and home builders associations and the general membership.

Related News

Pickering nuclear station is closing as planned, despite calls for refurbishment

PICKERING, ON - - The Ontario government will not reconsider plans to close the Pickering nuclear station and instead stop-gap the consequent electricity shortfall with natural gas-generated power in a move that will hike the province’s greenhouse gas emissions substantially in the coming years.

In a report released this week, a nuclear advocacy group urged Ontario to refurbish the aging facility east of Toronto, which is set to be shuttered in phases in 2024 and 2025. The closure of Pickering, which provides 14 per cent of the province’s annual electricity supply, comes at the same time as Ontario’s other two nuclear…

READ MORE
powerlines

B.C. ordered to pay $10M for denying Squamish power project

READ MORE

fortis

FortisAlberta Takes Necessary Precautions to Provide Electricity Service for Alberta

READ MORE

electric meter

Nova Scotia regulator approves 14% electricity rate hike, defying premier

READ MORE

Energize America: Invest in a smarter electricity infrastructure

READ MORE