Collider repairs at CERN to cost $25-million


NFPA 70E Training - 2027 Edition - Arc Flash and Electrical Safety Course

Our customized live online or in‑person group training can be delivered to your staff at your location.

  • Live Online
  • 6 hours Instructor-led
  • Group Training Available
Regular Price:
$199
Coupon Price:
$149
Reserve Your Seat Today
Fixing the world's largest atom smasher will cost at least 25 million Swiss francs ($25.8-million Cdn) and may take until early summer, its operator said.

An electrical failure shut down the Large Hadron Collider on September 19, nine days after the $10-billion machine started up with great fanfare.

The European Organization for Nuclear Research recently said that the repairs would be completed by May or early June. Spokesman James Gillies said the organization know as CERN is now estimating the restart will be at the end of June or later.

“If we can do it sooner, all well and good. But I think we can do it realistically (in) early summer,” he said.

The organization has attributed the shutdown to the failure of a single, badly soldered electrical connection.

The atom smasher operates at temperatures colder than outer space to get maximum efficiency, and experts needed to gradually warm the damaged section to better assess it, he said.

“Now the sector is warm, so they are able to go in and physically look at each of the interconnections,” Mr. Gillies told The Associated Press.

The cost of the work will fall within the organization's existing budget, he said.

The massive machine straddling the Swiss-French border was built to smash protons from hydrogen atoms together at high energy and record what particles are produced by the collisions, giving scientists a better idea of the makeup of the smallest components of matter.

That will show on a tiny scale what happened one-trillionth of a second after the so-called Big Bang, which many scientists theorize was the massive explosion that formed the universe. The theory holds that the universe was rapidly cooling at that stage and matter was changing rapidly.

Scientists have taken the setback in stride, saying that particle colliders always have such problems in the startup phase.

Related News

When paying $1 for a coal power plant is still paying too much

San Juan Generating Station eyed for $1 coal-plant sale, as Farmington and Acme propose CCS…
View more

Study: US Power Grid Has More Blackouts Than ENTIRE Developed World

US Power Grid Blackouts highlight aging infrastructure, rising outages, and declining reliability per DOE and…
View more

The crisis in numbers: How COVID-19 has reshaped Saskatchewan

Saskatchewan COVID-19 economic impact: real-time data shows drops in electricity demand, oil well licensing, traffic…
View more

New Power Grid “Report Card” Reveal Dangerous Vulnerabilities

U.S. Power Grid D+ Rating underscores aging infrastructure, rising outages, cyber threats, EMP and solar…
View more

Energy minister unveils Ontario's plan to address growing energy needs

Powering Ontario's Growth accelerates clean electricity, pairing solar, wind, and hydro with energy storage, efficiency…
View more

Canadian Electricity Grids Increasingly Exposed to Harsh Weather

North American Grid Reliability faces extreme weather, climate change, demand spikes, and renewable variability; utilities,…
View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Live Online & In-person Group Training

Advantages To Instructor-Led Training – Instructor-Led Course, Customized Training, Multiple Locations, Economical, CEU Credits, Course Discounts.

Request For Quotation

Whether you would prefer Live Online or In-Person instruction, our electrical training courses can be tailored to meet your company's specific requirements and delivered to your employees in one location or at various locations.