Power grid bottleneck stalls Maine project


Protective Relay Training - Basic

Our customized live online or in‑person group training can be delivered to your staff at your location.

  • Live Online
  • 12 hours Instructor-led
  • Group Training Available
Regular Price:
$699
Coupon Price:
$599
Reserve Your Seat Today
A gridlocked New England power grid in Maine has stalled a Harpswell developer's plan for a $50 million biomass boiler in Millinocket.

Jerry Tudan, of Peregrine Technologies, had already lined up financing for the 17-megawatt project that would bring 45 jobs to the Katahdin region when he got the bad news from the grid manager.

Tudan said his company sought to register the site with ISO-New England, only to be told that a northern Maine wind farm project had registered earlier and had "maxed out" any available access to the grid at this time.

Tudan has no quarrel with First Wind, the Massachusetts developer of Stetson Mountain and other wind projects in northern Maine. But he said that company is among several that have queued up for so much space on the grid in coming years that no one else can fit.

"There's no bitter tears here toward First Wind about it," Tudan said. "That's the marketplace, though I feel very bad about how it went because we had a beautiful project."

ISO-New England manages the transmission of electricity through the 45-, 115- and 345-kilovolt lines connecting various power company systems. It's open, on a first-come, first-served basis, to generators that meet reliability standards.

Three of Maine's largest utilities — Bangor Hydro-Electric Co., Central Maine Power and Maine Public Service — have plans to lay new lines, but none will likely materialize before 2011, at the earliest.

"More power generators could come on the grid now, but there is a certain amount of congestion between Maine and southern New England," said CMP spokesman John Carroll, who agreed that the New England grid is getting gridlocked. "Therefore, there are some limited periods of time where they would not be able to run because their power couldn't be transferred out of Maine."

To boost capacity, several large-scale grid expansions are in the works, including a CMP 345-kilovolt line that would run nearly 250 miles from Orrington to Eliot and New Hampshire. It would go on line by 2012 and cost $1.1 billion to $1.5 billion.

Bangor Hydro has proposed a project which would use 345-kilovolt lines to connect its Orrington substation to the Boston area, at an estimated cost of $2 billion.

"Ultimately ISO-New England or the system's operator-owners will expand the system, but not for a single generator, because the rule is that generators pay to get interconnected to the system," said Gerry Chasse, vice president of transmission and distribution operations at Bangor Hydro.

"To say that any one generator has taken up all capacity is a little inaccurate," Chasse said. "New generators are already coming into an already-constrained system in that there isn't sufficient capacity to carry energy to the market under all conditions."

Town Manager Eugene Conlogue had welcomed the biomass project. He expressed disappointment, but not surprise, that it is likely dead. Power generation, Conlogue said, is "one of our growth areas in Millinocket, but if they don't have a way to get power to the grid, it's a dead issue."

Related News

How the dirtiest power station in western Europe switched to renewable energy

Drax Biomass Conversion accelerates renewable energy by replacing coal with wood pellets, sustainable forestry feedstock,…
View more

Energy minister unveils Ontario's plan to address growing energy needs

Powering Ontario's Growth accelerates clean electricity, pairing solar, wind, and hydro with energy storage, efficiency…
View more

Opinion: With deregulated electricity, no need to subsidize nuclear power

Pennsylvania Electricity Market Deregulation has driven competitive pricing, leveraged low-cost natural gas, and spurred private…
View more

Solar PV and wind power in the US continue to grow amid favourable government plans

US Renewable Power Outlook 2030 projects surging capacity, solar PV and wind growth, grid modernization,…
View more

Berlin Electric Utility Wins National Safety Award

Berlin Electric Utility APPA Safety Award recognizes Gold Designation performance in public power, highlighting OSHA-aligned…
View more

Met Office joins REVISE to protect United Kingdom overhead transmission lines

Met Office REVISE Project will provide high-resolution weather data to refine static line ratings for…
View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Live Online & In-person Group Training

Advantages To Instructor-Led Training – Instructor-Led Course, Customized Training, Multiple Locations, Economical, CEU Credits, Course Discounts.

Request For Quotation

Whether you would prefer Live Online or In-Person instruction, our electrical training courses can be tailored to meet your company's specific requirements and delivered to your employees in one location or at various locations.