Judge denies Injunction Request for NextEra Solar Power Project

subscribe

Saying there is no compelling reason to do so, a federal judge on June 11 refused to slap a preliminary injunction stopping any on-site development work at the NextEra Blythe solar plant in California .

In 2010, the U.S. Bureau of Land Management BLM approved the construction of a 1,000 MW solar power plant using parabolic trough technology on about 7,000 acres of federal land in the Mojave Desert, northwest of Blythe, California.

In 2012, NextEra Blythe Solar Energy Center LLC purchased the assets for this project, and submitted to BLM a new plan to develop a photovoltaic solar facility called Blythe II. This new project would generate 485 MW on about 4,000 acres of federal land. BLM last year issued a final environmental impact statement on the revamped project. The plaintiff in this case, Colorado River Indian Tribes CRIT, is a federally recognized Indian tribe whose members include Mohave, Chemehuevi, Hopi and Navajo peoples. Plaintiff's Reservation is near the project site. Plaintiff contends its members have a religious and cultural relationship to the artifacts left by their ancestors, and its Mohave members experience significant spiritual harm when such resources are dug up, relocated or damaged. In addition, the religion and culture of plaintiff's member tribes is strongly connected to the physical environment of the area, the tribe has said.

The case is being heard at the U.S. District Court for the Central District of California.

In December 2014 , plaintiff brought this declaratory and injunctive action under the Administrative Procedure Act APA. Plaintiff alleges that, by approving of the project and related actions, BLM violated its obligations under three federal statutes and corresponding regulations. For example, the lawsuit said, BLM did not comply with the National Historic Preservation Act NHPA, because it did not meaningfully consult Plaintiff as required.

On March 16 , plaintiff filed a motion for preliminary injunction, arguing that this relief was necessary because construction was scheduled to begin in April 2015 , and plaintiff would be irreparably harmed if it proceeded due to the resulting damage to cultural, religious and historic resources and the transformation of the desert landscape. The federal government and NextEra each filed a separate opposition.

Balanced against tribal interests is the economic aspects of the project itself, said the judge in the June 11 ruling. On balance, these competing public interests are in equipoise. Because it is the burden of Plaintiff to show that the injunction is in the public interest, the neutrality of this factor weighs against granting the injunction. The judge also noted that an injunction could disrupt negotiations with third parties and “energy off-takers for a power sales agreement for Unit 2 of the Project.†Also, Unit 1 of the project is currently scheduled to begin producing energy in December 2015 and an injunction while this case is heard could prevent NextEra from profiting from the sale of energy during that interim period, the judge added.

Related News

electricity meter

Hydro One delivery rates go up

THUNDER BAY - Hydro One seasonal customers will face bigger increases in their bills than the utility's residential customers as a result of an Ontario Energy Board approval of a rate hike.

Hydro One received permission to increase its delivery charge, retroactive to last year.

It says it needs the money to maintain and upgrade its infrastructure, much of which was installed in the 1950s.

The utility is notifying customers that new statements reflect higher delivery rates which were not charged in 2018 and the first half of this year, due to delay in receiving the OEB's permission.

The amount that customers' bills will increase by depends…

READ MORE
electricity prices

Electricity Prices Surge to Record as Europe Struggles to Keep Lights on

READ MORE

Smaller, cheaper, safer: Next-gen nuclear power, explained

READ MORE

electricity digitransformation

Disrupting Electricity? This Startup Is Digitizing Our Very Analog Electrical System

READ MORE

Sub-Saharan-Electricity

Sub-Saharan Africa has a huge electricity problem - but with challenge comes opportunity

READ MORE