OPG takes another step toward site preparation at Darlington


OPG Darlington Nuclear Project advances with federal environmental assessment acceptance after Joint Review Panel hearings. OPG awaits a site preparation license from the Canadian Nuclear Safety Commission, with mitigation and regulatory review.

 

At a Glance

A new nuclear unit at Darlington, Ontario, cleared by EA review and now awaiting a Canadian site preparation license.

  • Federal government accepted the environmental assessment
  • Joint Review Panel held 17 days of public hearings
  • OPG awaits the site preparation license from CNSC
  • Site prep license is first of three for new nuclear builds
  • 2009 EIS and technical studies underpin the application

 

The Federal Government of Canada has responded to the recommendations of the Joint Review Panel of the Ontario Power Generation OPG, the province's power generator, and approved the Darlington New Nuclear Project Environmental Assessment EA.

 

This project is aimed at adding additional nuclear generation to OPG's Darlington power plant, the Darlington Nuclear Station located in Darlington, Ontario.

"OPG is pleased with the Federal Government’s decision," said Albert Sweetnam, OPG’s Executive Vice President, Nuclear Projects, as the company moves to construct a generating unit at Darlington. "We were confident in the conclusions of our extensive studies, however independent review and confirmation provides added assurance that the project will not result in any significant adverse environmental effects, given mitigation."

OPG, drawing on its 2016 financial results to inform planning, now awaits a decision by the Joint Review Panel, as a panel of the Canadian Nuclear Safety Commission, the federal regulator for nuclear power in Canada, as part of the federal approvals process on the next key milestone: the issuance of the site preparation license. The site preparation license is the first of three licenses required to build and operate a new nuclear facility in Canada.

In 2009, OPG submitted the Environmental Impact Statement and supporting technical documents in support of the project, along with an updated application for a "license to prepare site." A federally appointed Joint Review Panel undertook an extensive review involving federal, provincial and municipal agencies, independent technical experts, and considering context like the Wesleyville site not in the running, and held 17 days of public hearings before recommending to the Federal Government they accept the EA.

 

Related News

Related News

Quebec Hit by Widespread Power Outages Following Severe Windstorm

Quebec Windstorm 2025 disrupted Montreal and surrounding regions, triggering power outages, Hydro-Québec repairs, fallen trees,…
View more

Rolls-Royce expecting UK approval for mini nuclear reactor by mid-2024

Rolls-Royce SMR UK Approval underscores nuclear innovation as regulators review a 470 MW factory-built modular…
View more

Group to create Canadian cyber standards for electricity sector IoT devices

Canadian Industrial IoT Cybersecurity Standards aim to unify device security for utilities, smart grids, SCADA,…
View more

Bangladesh develops nuclear power with IAEA Assistance

Bangladesh Rooppur Nuclear Power Plant advances nuclear energy with IAEA support and ROSATOM construction, boosting…
View more

Ontario Supports Plan to Safely Continue Operating the Pickering Nuclear Generating Station

Pickering Nuclear Generating Station Refurbishment will enable OPG to deliver reliable, clean electricity in Ontario,…
View more

7 steps to make electricity systems more resilient to climate risks

Electricity System Climate Resilience underpins grid reliability amid heatwaves and drought, integrating solar, wind, hydropower,…
View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Download the 2026 Electrical Training Catalog

Explore 50+ live, expert-led electrical training courses –

  • Interactive
  • Flexible
  • CEU-cerified