Coal plant keeps air permit
The 250-megawatt Highwood Generating Station is being built by the Southern Montana Electric Generation and Transmission Cooperative. It has encountered numerous delays tied to problems raising money for the project, and to lawsuits by some environmental groups and residents of the Great Falls area.
The plant risked losing its air permit — first issued in May 2007 — if construction was not well under way by the end of November.
Southern Montana Electric scrambled to meet the deadline, starting construction in late October with only a small portion of the necessary funding in hand.
Charles Homer, DEQ permitting manager, wrote Southern Montana Electric on that the co-op had succeeded in deadline compliance.
Keeping the air permit helps the co-op make its case to potential investors that the power plant will be built, said Tim Gregori, general manager of Southern Montana Electric.
"Validating the air permit and showing we're under construction shows we have a valid project moving forward and there's a reasonable expectation the project will be completed," Gregori said.
Under the project's construction timeline, the plant could be operating by 2013.
Related News

Kenya on Course for $5 Billion Nuclear Plant to Power Industry
KENYA - Kenya’s nuclear agency submitted impact studies for a $5 billion power plant, and said it’s on course to build and start operating the facility in about seven years.
The government plans to expand its nuclear-power capacity fourfold by 2035, the Nuclear Power and Energy Agency said in a report on the National Environment Management Authority’s website. The document is set for public scrutiny before the environmental watchdog can approve it, and pave the way for the project to continue.
President Uhuru Kenyatta wants to ramp up installed generation capacity from 2,712 megawatts as of April to boost manufacturing in East…