FERC proposes reforms for small generator interconnections

subscribe

The Federal Energy Regulatory Commission FERC recently proposed reforms intended to reduce the time and cost to process small generator interconnection requests and allow for more efficient interconnection of these resources to benefit customers. These reforms also would maintain reliability, increase energy supply and remove barriers to the development of new energy sources.

The reforms, outlined in a Notice of Proposed Rulemaking NOPR, are driven by market changes spurred in part by state renewable energy goals and policies. They affect FERCÂ’s pro forma Small Generator Interconnection Procedures SGIP and Small Generator Interconnection Agreement SGIA, which set the terms and conditions for interconnecting facilities of 20 megawatts MW or smaller. The recent NOPR proposes four reforms to the SGIP and SGIA.

The first reform would allow interconnection customers to request from transmission providers a pre-application report to help them better evaluate points of interconnection before submitting a formal interconnection request. This added transparency could increase the efficiency of the interconnection process for both transmission providers and interconnection customers.

The second reform would revise the current 2 MW threshold for participation in the Fast Track Process under section 2 of the SGIP. Fast Track eligibility instead would be based on individual system and resource characteristics, up to a limit of 5 MW.

A third reform would revise the customer options meeting and supplemental review for projects that fail the Fast Track screens that identify reliability or safety issues.

Finally, the NOPR would revise the pro forma SGIP Facilities Study Agreement by giving interconnection customers an opportunity to provide written comments on the upgrades that are necessary for the interconnection. The Commission believes transmission providers should make the final decision on required upgrades, but is concerned that failing to allow customers to review and comment on the upgrades may result in unjust and unreasonable costs.

Comments are due 120 days after publication in the Federal Register. Because of the technical nature of the reforms, the Commission directed staff to convene a workshop before the end of the comment period.

Related News

yukon nuclear

Modular nuclear reactors a 'long shot' worth studying, says Yukon gov't

WHITEHORSE - The Yukon government is looking for ways to reduce the territory's emissions, and wondering if nuclear power is one way to go.

The territory is undertaking a feasibility study, to determine whether there's a future for SMRs — small modular reactors — as a low-emissions alternative to things such as diesel power.

The idea, said John Streicker, Yukon's minister of energy, mines and resources, is to bring the SMRs into the Yukon to generate electricity.

"Even the micro ones, you could consider in our remote communities or wherever you've got a point load of energy demand," Streicker said. "Especially electricity demand."

SMRs…

READ MORE
Tariff Threats Boost Support for Canadian Energy Projects

Tariff Threats Boost Support for Canadian Energy Projects

READ MORE

global energy crunch

4 ways the energy crisis hits U.S. electricity, gas, EVs

READ MORE

Drought, lack of rain means BC Hydro must adapt power generation

READ MORE

tornado survivor

Survivors of deadly tornadoes may go weeks without heat, water, electricity, Kentucky officials say

READ MORE