As part of its efforts to help support Ohio's growing shale gas industry, FirstEnergy Corp. recently completed a new 3.5 mile, 138 kilovolt kV transmission line in its Ohio Edison territory to serve a Pennant Midstream natural gas processing facility in Springfield Township in Mahoning County. The nearly $3 million project replaces temporary equipment installed earlier and allows for future expansion at the facility.

The plant is a midstream processing facility that separates natural gas into dry and liquid components and uses large amounts of electricity.

"With the natural gas industry bringing new employment and business development opportunities to Ohio, FirstEnergy and Ohio Edison are expected to keep pace by continuing to upgrade our system to meet this growing demand for safe and reliable electric service," said Randall A. Frame, regional president, Ohio Edison.

The new line connects with an existing 138 kV transmission line in Mahoning County. The project included installing 81 new wooden poles and 1 steel pole in approximately 3.5 miles of new right-of-way to a substation located at the Pennant Midstream facility. Earlier this year, Ohio Edison installed a temporary 69 kV transmission line and mobile substation to handle the electricity needs for Pennant Midstream's construction and start-up activities. With the completion of the new 138 kV transmission line, the temporary equipment was removed.

The new transmission line is owned and operated by American Transmission Systems, Incorporated, a FirstEnergy transmission affiliate.

The work is part of FirstEnergy's plans to invest approximately $730 million in 2014 on service reliability infrastructure enhancements and transmission projects in the Ohio Edison area.

Related News

BOE Says UK Energy Price Guarantee is Key for Next Rates Call

UK Market Stability Outlook remains febrile as the Bank of England, Treasury, and OBR forecasts…
View more

Opinion: The awesome, revolutionary electric-car revolution that doesn't actually exist

Ecofiscal Commission EV Policy Shift examines carbon pricing limits, endorsing signal boosters like subsidies, EV…
View more

Marine Renewables Canada shifts focus towards offshore wind

Marine Renewables Canada Offshore Wind integrates marine renewables, tidal and wave energy, advancing clean electricity,…
View more

Ontario will not renew electricity deal with Quebec

Ontario-Quebec Electricity Trade Agreement ends as Ontario pivots to IESO procurement, hydropower alternatives, natural gas…
View more

Ireland announces package of measures to secure electricity supplies

Ireland electricity support measures include PSO levy rebates, RESS 2 renewables, CRU-directed EirGrid backup capacity,…
View more

When did BC Hydro really know about Site C dam stability issues? Utilities watchdog wants to know

BC Utilities Commission Site C Dam Questions press BC Hydro on geotechnical risks, stability issues,…
View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Download the 2026 Electrical Training Catalog

Explore 50+ live, expert-led electrical training courses –

  • Interactive
  • Flexible
  • CEU-cerified