ATC seeks approval to rebuild 14-mile, 138-kV transmission line
PEWAUKEE, Wis. – - PEWAUKEE, Wis. – American Transmission Co. recently filed an application with the Public Service Commission of Wisconsin to rebuild an existing 14-mile, 138,000-volt transmission line in southeastern Wisconsin.
The proposed St. Martins-Edgewood-Mukwonago Rebuild Project runs from the St. Martins Substation in Franklin to the Edgewood Substation in Big Bend and continues on to the Mukwonago Substation, in Mukwonago.
“The lattice tower structures, which are approximately 90 years old, will be replaced with steel single-pole structures and the wires also will be replaced,” said Mary Carpenter, senior local relations representative for ATC. “The new poles will be placed within a few feet of the existing structures, and no new right-of-way is anticipated for the project.”
Regulatory approval of this project is expected in fall 2015 with construction beginning in 2017 to meet an in-service date of 2018.
Related News

Should California classify nuclear power as renewable?
SAN FRANCISCO - Although he admits it's a long shot, a member of the California Legislature from the district that includes the Diablo Canyon nuclear plant has introduced a bill that would add nuclear power to the state's list of renewable energy sources.
"I think that nuclear power is an important component of generating large-scale electricity that's good for the environment," said Jordan Cunningham, R-San Luis Obispo. "Without nuclear as part of the renewable portfolio, we're going to have tremendous difficulty meeting the state's climate goals without a significant cost increase on electricity ratepayers."
Established in 2002, California's Renewables Portfolio Standard spells…