ATC seeks approval to rebuild 14-mile, 138-kV transmission line
PEWAUKEE, Wis. – - PEWAUKEE, Wis. – American Transmission Co. recently filed an application with the Public Service Commission of Wisconsin to rebuild an existing 14-mile, 138,000-volt transmission line in southeastern Wisconsin.
The proposed St. Martins-Edgewood-Mukwonago Rebuild Project runs from the St. Martins Substation in Franklin to the Edgewood Substation in Big Bend and continues on to the Mukwonago Substation, in Mukwonago.
“The lattice tower structures, which are approximately 90 years old, will be replaced with steel single-pole structures and the wires also will be replaced,” said Mary Carpenter, senior local relations representative for ATC. “The new poles will be placed within a few feet of the existing structures, and no new right-of-way is anticipated for the project.”
Regulatory approval of this project is expected in fall 2015 with construction beginning in 2017 to meet an in-service date of 2018.
Related News
Canadian gold mine cleans up its act with electricity
TORONTO - Mining operations get a lot of flack for creating environmental problems around the world. Yet they provide much of the basic material that keeps the global economy humming. Some mining companies are drilling down in their efforts to clean up their acts.
As the world’s fourth-largest gold mining company Goldcorp has received its share of criticism about the impact it has on the environment.