ATC seeks approval to rebuild 14-mile, 138-kV transmission line

subscribe

PEWAUKEE, Wis. – American Transmission Co. recently filed an application with the Public Service Commission of Wisconsin to rebuild an existing 14-mile, 138,000-volt transmission line in southeastern Wisconsin.

The proposed St. Martins-Edgewood-Mukwonago Rebuild Project runs from the St. Martins Substation in Franklin to the Edgewood Substation in Big Bend and continues on to the Mukwonago Substation, in Mukwonago.

“The lattice tower structures, which are approximately 90 years old, will be replaced with steel single-pole structures and the wires also will be replaced,” said Mary Carpenter, senior local relations representative for ATC. “The new poles will be placed within a few feet of the existing structures, and no new right-of-way is anticipated for the project.”

Regulatory approval of this project is expected in fall 2015 with construction beginning in 2017 to meet an in-service date of 2018.

Related News

Two-thirds of the U.S. is at risk of power outages this summer

WASHINGTON - The Department of Energy recently warned that two-thirds of the U.S. is at risk of losing power this summer. It’s an increasingly common refrain: Homeowners want to be less reliant on the aging power grid and don’t want to be at the mercy of electric utilities due to rising energy costs and dwindling faith in the power grid’s reliability.

And it makes sense. While the inflated price of eggs and butter made headlines earlier this year, electricity prices quietly increased at twice the rate of overall inflation in 2022, and homeowners have taken notice. In fact, according to Aurora…

READ MORE
towers

Alberta Introduces New Electricity Rules

READ MORE

electric tractor

Are we ready for electric tractors?

READ MORE

floatgen construction

France’s first offshore wind turbine produces electricity

READ MORE

Ontario announces SMR plans to four reactors at Darlington

READ MORE