Big Becky breaks down

A machine boring a 10.3-kilometre tunnel to boost electricity output at Niagara Falls has broken a part, and has been shut down for repairs.

But Ontario Power Generation says the breakdown shouldnÂ’t further delay completion of the project, which is already four years behind schedule.

The latest problem has cropped up in “Big Becky”, the machine that is chewing out the 14-metre-diameter tunnel that will increase the flow of water through the Niagara generating station.

“There’s a beam that runs through the centre of the boring machine,” said OPG spokesman Ted Gruetzner in an interview.

“Workers discovered a crack in it so they shut the thing down so they could make the repairs.”

They are welding supports onto the cracked beam to reinforce it, he said.

Gruetzner said the break should not further push back the over-all schedule. Other maintenance work had already been planned, and would have forced the machine to shut down in the coming weeks.

That maintenance works now been moved up to coincide with the emergency repairs, he said, so the later shutdown wonÂ’t be needed.

“They should be back up and running by Christmas time,” he said.

Big Becky, which started boring in 2006, was supposed to have completed the job by 2009.

But unexpected geological conditions caused delays and forced the tunnel to take a longer route than planned.

The cost of the project has risen to $1.6 billion from the original estimate of $985 million.

The contractor for the project, the Austrian company Strabag AG, was deemed not responsible for the unexpected rock conditions so the cost overrun is being borne by OPG.

Gruetzner said the tunnel has now progressed 9.1 kilometres, and OPG hopes it will break through the final wall of rock above the falls in the first quarter of the New Year.

A coffer dam has already been constructed to keep the area dry when big Becky emerges.

Although the boring will be completed early in the New Year, the project as a whole wonÂ’t be finished until 2013, as the rough tunnel must be lined before it can be used.

The increased water flow through the tunnel will boost NiagaraÂ’s electricity output by 1.6 terawatt hours a year. A terawatt hour is one billion kilowatt hours. OntarioÂ’s total demand in 2009 was 139 terawatt hours.

Related News

wind-power-surges-in-us-electricity-mix

Wind Power Surges in U.S. Electricity Mix

In early 2025, wind power has significantly strengthened its position in the United States' electricity generation portfolio. According to data from the Federal Energy Regulatory Commission (FERC), wind energy accounted for 30.1% of the new electricity capacity added in January 2025, surpassing the previous record set in 2024. This growth is attributed to substantial projects such as the 390.4 MW Cedar Springs Wind IV and the 330.0 MW Boswell Wind Farm in Wyoming, along with the 300.0 MW Prosperity Wind Farm in Illinois and the 201.0 MW Golden Hills Wind Farm Expansion in Oregon. 

READ MORE
oyster creek nuclear plant

Cost of US nuclear generation at ten-year low

READ MORE

rolls royce nuclear

Rolls-Royce signs MoU with Exelon for compact nuclear power stations

READ MORE

Tokyo Electric Power Co.’s Kashiwazaki-Kariwa nuclear complex

Energy authority clears TEPCO to restart Niigata nuclear plant

READ MORE

californias-solar-power-cost-shift

California’s Solar Power Cost Shift: A Misguided Policy Threatening Energy Equity

READ MORE