Rocky Mountain Power expects to begin construction next spring on a proposed 74-turbine wind farm in Carbon County.

Project manager Ken Clark told the Carbon County Commission recently that the project is mostly on land owned by the company, so only state permitting is required.

The wind far would be located north of Medicine Bow in northeast Carbon County.

Clark says work is expected to begin in April and be complete the following November.

At peak construction, about 300 workers would be employed on the project.

Clark said there are no sage grouse strutting grounds in the project area, and it is located outside of what the state has defined as sage grouse core areas.

Each tower is expected to be 260 feet tall to the top of the generator nacelle. With blades 120 feet long, the height increases to 380 feet at what's called "full sweep," or when each blade is upright at the top of its rotation, he said.

The 1.5 megawatt wind turbines are expected to be supplied by General Electric.

Clark said the site probably is capable of handling 200 towers that could generate about 300 megawatts of electricity. But right now, Rocky Mountain Power is planning to build only the one 74-tower phase, with generating capacity of 111 megawatts of power.

Because wind turbines actually generate full power only 35 to 40 percent of the time, he said the project is expected to generate enough electricity to power the homes of about 32,000 customers.

The turbines start producing power when the wind blows at 9 mph. They generate full power in winds of 30-60 mph and shut down at 60 mph, he said.

Asked about impacts on views, Clark said visual impacts are expected to be minimal in the town of Medicine Bow, which is about eight miles south of the project, because there are several ridges between the project and the town.

Related News

Net-zero roadmap can cut electricity costs by a third in Germany - Wartsila

Germany net-zero roadmap charts coal phase-out by 2030, rapid renewables buildout, energy storage, and hydrogen-ready…
View more

What to know about the big climate change meeting in Katowice, Poland

COP24 Climate Talks in Poland gather nearly 200 nations to finalize the Paris Agreement rulebook,…
View more

German official says nuclear would do little to solve gas issue

Germany Nuclear Phase-Out drives policy amid gas supply risks, Nord Stream 1 shutdown fears, Russia…
View more

Data Center Boom Poses a Power Challenge for U.S. Utilities

U.S. Data Center Power Demand is straining electric utilities and grid reliability as AI, cloud…
View more

Alberta's Last Coal Plant Closes, Embracing Clean Energy

Alberta Coal Phase-Out signals a clean energy transition, replacing coal with natural gas and renewables,…
View more

Key Ontario power system staff may end up locked down at work sites due to COVID-19, operator says

Ontario IESO COVID-19 Control Room Measures detail how essential operators safeguard the electricity grid with…
View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Download the 2026 Electrical Training Catalog

Explore 50+ live, expert-led electrical training courses –

  • Interactive
  • Flexible
  • CEU-cerified