Largest combined-cycle power plant running in Beijing
Taiyanggong Gas Thermal Power Plant is an important support project for the Beijing 2008 Olympic Games. The project is built and operated by Beijing Taiyanggong Gas Thermal Power Company Limited (BTGTPC), a project company jointly invested by Power Beijing and GD Power Development Company Limited, the listed flagship of China Guodian Corporation.
The project is furnished with two 350-megawatt (MW) 9F-class gas-steam combined-cycle generating units with an annual power output of about 3.4 billion kilowatt-hours and a heat-supply capacity of 10 million square meters in an area of 40 square kilometers.
During the construction of the project, BTGTPC overcame a series of technical difficulties such as arrangement of the units and noise treatment. With strong support from the municipal government, construction quality, progress and cost control are within desired boundaries.
Unit 1 of the plant was successfully connected to the grid on December 29, 2007, and Unit 2 passed the 168-hour trial operation in March 2008.
The project is currently ready to supply heat and power to the Olympic venues.
Related News

Ontario Extends Off-Peak Electricity Rates to Provide Relief for Families, Small Businesses and Farms
TORONTO - The Ontario government is once again extending electricity rate relief for families, small businesses and farms to support those spending more time at home while the province maintains the Stay-at-Home Order in the majority of public health regions. The government will continue to hold electricity prices to the off-peak rate of 8.5 cents per kilowatt-hour until February 22, 2021. This lower rate is available 24 hours per day, seven days a week for Time-Of-Use and tiered customers.
"We know staying at home means using more electricity during the day when electricity prices are higher, that's why we are once…