Largest combined-cycle power plant running in Beijing
Taiyanggong Gas Thermal Power Plant is an important support project for the Beijing 2008 Olympic Games. The project is built and operated by Beijing Taiyanggong Gas Thermal Power Company Limited (BTGTPC), a project company jointly invested by Power Beijing and GD Power Development Company Limited, the listed flagship of China Guodian Corporation.
The project is furnished with two 350-megawatt (MW) 9F-class gas-steam combined-cycle generating units with an annual power output of about 3.4 billion kilowatt-hours and a heat-supply capacity of 10 million square meters in an area of 40 square kilometers.
During the construction of the project, BTGTPC overcame a series of technical difficulties such as arrangement of the units and noise treatment. With strong support from the municipal government, construction quality, progress and cost control are within desired boundaries.
Unit 1 of the plant was successfully connected to the grid on December 29, 2007, and Unit 2 passed the 168-hour trial operation in March 2008.
The project is currently ready to supply heat and power to the Olympic venues.
Related News

Stellat'en and Innergex Sign Wind Deal with BC Hydro
VANCOUVER - In December 2024, a significant development unfolded in British Columbia's renewable energy sector as Stellat'en First Nation and Innergex Renewable Energy Inc. announced the signing of a 30-year electricity purchase agreement with BC Hydro. This agreement pertains to the Nithi Mountain Wind Project, a 200 MW initiative poised to enhance the province's clean energy capacity.
Project Overview
The Nithi Mountain Wind Project is a collaborative venture between Stellat'en First Nation, which holds a 51% stake, and Innergex Renewable Energy Inc., which holds a 49% stake. Located in the Bulkley-Nechako region of British Columbia, the project is expected to…