Largest combined-cycle power plant running in Beijing
Taiyanggong Gas Thermal Power Plant is an important support project for the Beijing 2008 Olympic Games. The project is built and operated by Beijing Taiyanggong Gas Thermal Power Company Limited (BTGTPC), a project company jointly invested by Power Beijing and GD Power Development Company Limited, the listed flagship of China Guodian Corporation.
The project is furnished with two 350-megawatt (MW) 9F-class gas-steam combined-cycle generating units with an annual power output of about 3.4 billion kilowatt-hours and a heat-supply capacity of 10 million square meters in an area of 40 square kilometers.
During the construction of the project, BTGTPC overcame a series of technical difficulties such as arrangement of the units and noise treatment. With strong support from the municipal government, construction quality, progress and cost control are within desired boundaries.
Unit 1 of the plant was successfully connected to the grid on December 29, 2007, and Unit 2 passed the 168-hour trial operation in March 2008.
The project is currently ready to supply heat and power to the Olympic venues.
Related News

Is Hydrogen The Future For Power Companies?
LONDON - Last month, the European Union set out a comprehensive hydrogen strategy as part of its goal to achieve carbon neutrality for all its industries by 2050. The EU has an ambitious target to build out at least 40 gigawatts of electrolyzers within its borders by 2030 and also support the development of another 40 gigawatts of green hydrogen in nearby countries that can export to the region by the same date. The announcement came as little surprise, given that Europe is regarded as being far ahead of the United States in the shift to renewable energy.