Largest combined-cycle power plant running in Beijing
Taiyanggong Gas Thermal Power Plant is an important support project for the Beijing 2008 Olympic Games. The project is built and operated by Beijing Taiyanggong Gas Thermal Power Company Limited (BTGTPC), a project company jointly invested by Power Beijing and GD Power Development Company Limited, the listed flagship of China Guodian Corporation.
The project is furnished with two 350-megawatt (MW) 9F-class gas-steam combined-cycle generating units with an annual power output of about 3.4 billion kilowatt-hours and a heat-supply capacity of 10 million square meters in an area of 40 square kilometers.
During the construction of the project, BTGTPC overcame a series of technical difficulties such as arrangement of the units and noise treatment. With strong support from the municipal government, construction quality, progress and cost control are within desired boundaries.
Unit 1 of the plant was successfully connected to the grid on December 29, 2007, and Unit 2 passed the 168-hour trial operation in March 2008.
The project is currently ready to supply heat and power to the Olympic venues.
Related News

UK low-carbon electricity generation stalls in 2019
LONDON - The amount of electricity generated by low-carbon sources in the UK stalled in 2019, Carbon Brief analysis shows.
Low-carbon electricity output from wind, solar, nuclear, hydro and biomass rose by just 1 terawatt hour (TWh, less than 1%) in 2019. It represents the smallest annual increase in a decade, where annual growth averaged 9TWh. This growth will need to double in the 2020s to meet UK climate targets while replacing old nuclear plants as they retire.
Some 54% of UK electricity generation in 2019 came from low-carbon sources, including 37% from renewables and 20% from wind alone. A record-low 43%…