ATC studies show need for $2.5 billion in investment
The total includes $1 billion for transmission network upgrades, along with $1.5 billion in interconnection and asset renewal projects, infrastructure replacements and relocations, and other smaller network reliability improvements. That is down from the 2008 10-year assessment of $2.7 billion, although the current forecast may change due to regional initiatives to build transmission infrastructure to support renewable generation.
“While ATC has made significant progress since beginning operation in 2001, we continue our process to assess and reassess the needs of our customers to determine and evolve, over time, the best set of transmission projects to meet those needs,” explained Flora Flygt, director of transmission planning at ATC. “Now, more than ever, we are committed to an open, collaborative process to select best-value projects that resolve multiple electric system issues over a broad region.”
The $1 billion investment in new transmission infrastructure includes:
• 131 miles of new transmission lines;
• upgrades to more than 399 miles of existing lines; and
• 21 new transformers and 29 new capacitor banks.
The ATC report lists nine regional collaborative planning initiatives in which ATC is leading or participating, including the SMARTransmission Study to identify extra-high voltage transmission infrastructure needed to move wind power within a nine-state region from the Dakotas to Ohio, as well as the Regional Generator Outlet Study being conducted by the Midwest Independent System Operator.
“While our reliability performance data indicates that our system is performing well, we are including more detailed information in this year’s assessment to acknowledge how we manage the risk of aging infrastructure,” added Paul Roehr, ATC director of reliability and interconnections. Previous assessments have discussed near-term asset renewal efforts, but this year’s report provides more detail of potential projects through the full 10-year planning horizon. That work would include:
• maintenance on aging equipment;
• connections to power plants;
• infrastructure replacements and relocations;
• distribution interconnections; and
• other smaller network reliability improvements.
Since 2001, ATC has invested $2.1 billion in its transmission system, including:
• upgrades to more than 1,400 miles of transmission line;
• improvements at 130 electric substations; and
• construction of 36 new transmission lines (476 miles).
These reliability projects have reduced energy losses on the system that equate to:
• 15.3 million megawatt hours of electricity saved (enough to power 35,500 homes each year);
• 14.2 million tons of carbon-dioxide emissions eliminated (associated with producing lost energy); and
• averting the need for a 122-megawatt generating plant to serve peak demand.
ATCÂ’s 10-year Assessment is available online at www.atc10yearplan.com
Related News

Gaza electricity crisis:
GAZA - In Imad Shlayl’s electronics shop in Gaza City, the customers crowding his store are interested in only two products: LED lights and the batteries to power them.
In the already impoverished Gaza Strip, residents have learned to adapt to the fact that electricity is only available for between two and four hours a day.
But fresh anger was sparked when availability was cut further last month, at the request of the Palestinian president, Mahmoud Abbas, in an escalation of his conflict with Hamas, the Islamist group.
The shortages have defined how people live their lives: getting up in the middle of…