Gear problems shut down wind turbines

The giant blades on the turbines in the Steel Winds wind farm in Lackawanna haven’t been turning lately — but not for lack of wind.

ClipperWind, the manufacturer, and UPC Wind and BQ Energy, wind farm developers, reported that a problem is forcing them to replace the gearboxes on all eight windmills.

That will entail removing the rotor and all three blades — each longer than the wing of a Boeing 747.

The windmills — officially called “Liberty 2.5 Megawatt wind turbines” — are the first of their kind to be used commercially. They brought national attention to Lackawanna for its creative reuse of an abandoned industrial site.

The state-of-the-art turbines are so new that ClipperWind had anticipated a need for some tweaking here and there.

But resolving the problem has been more difficult than expected.

“This one’s a pain because you need a big crane,” acknowledged Bob Gates, ClipperWind senior vice president.

The work is expected to take several months, Gates said.

“We happen to have had the bad luck of building [Steel Winds] in the winter, and retrofitting it in high winds and cold weather doesn’t speed up the work,” he said.

The gearbox problem initially was noticed in August when highly sensitive sensors on one turbine activated.

Engineers quickly discovered that a tooth on one of the four gears in the box had broken. After testing, engineers realized that, because of unclear assembly instructions, the gearsÂ’ timing was off, causing them to operate unevenly.

Inspections found the same problem, in varying degrees of severity, on all seven of the other turbines on the site.

Liberty turbines in Iowa and Minnesota have developed the same problems, which also will require repairs.

A massive crane arrived at the former Bethlehem Steel site to begin removing the blades and rotor from the massive towers.

While the gear boxes are being replaced, Gates said a reinforcing bond will be applied to the fiberglass blades to prevent any major damage from tiny cracks that have developed on some.

Michael Alvarez, executive vice president and chief operating officer of UPC Wind, said the gear box issue has left him disappointed but not disheartened.

“For a couple of months, we were receiving great performance,” Alvarez said of the turbines. Technical problems, he added, are “in the nature of these sorts of projects.”

“ClipperWind is stepping up and replacing the gear boxes.... It’s definitely not irreparable.”

Alvarez added that the turbines were under warranty and that ClipperWind is covering the costs of all repairs, as well as some of the revenue UPC Wind will lose while the turbines are not operating.

Related News

Nova Scotia Power says it now generates 30 per cent of its power from renewables

HALIFAX - Nova Scotia's private utility says it has hit a new milestone in its delivery of electricity from renewable resources.

Nova Scotia Power says 30 per cent of the electricity it produced in 2018 came from renewable sources such as wind power.

The utility says 18 per cent came from wind turbines, nine per cent from hydroelectric and tidal turbines and three per cent by burning biomass.

However, over half of the province's electrical generation still comes from the burning of coal or petroleum coke. Another 13 per cent come from burning natural gas and five per cent from imports.

The utility says…

READ MORE
pickering ngs

Ontario will refurbish Pickering B NGS

READ MORE

nuclear materials

Current Model For Storing Nuclear Waste Is Incomplete

READ MORE

Solar Power Batteries

Cheap at Last, Batteries Are Making a Solar Dream Come True

READ MORE

Purdue: As Ransomware Attacks Increase, New Algorithm May Help Prevent Power Blackouts

READ MORE