PGE responds to OPUC order on Trojan costs
“I can appreciate what a tough, incredibly complex challenge the commission faced in sorting out 13 years of multiple regulatory proceedings and lawsuits,” PGE CEO and President Peggy Fowler said. “Throughout this process PGE has followed the OPUC’s orders for Trojan cost recovery, and we’re pleased that they’ve determined the company’s rates were just and reasonable.
“However, the refund order is disappointing. PGE and its investors have already written off $42 million of the Trojan investment and our customers benefited both from reduced power costs after we shut Trojan down and from the commission’s 1995 decision to spread cost recovery over a period of years.”
With OPUC approval, PGE decided to shut down the Trojan plant in 1993 after a least-cost planning analysis determined that the cost to customers of closing the plant and recovering the utilityÂ’s investment would be less than the cost of continued operation of the plant for the remainder of its planned lifespan.
In 1995 the OPUC ordered PGE to write off $37 million (after tax) of its remaining investment in the Trojan plant, but determined that the law allowed PGE to recover the balance of the investment. To maintain price stability, the commission ordered PGE to collect the balance as part of the utilityÂ’s prices over the remainder of TrojanÂ’s planned lifespan, with an end-date of 2011, and allowed the company to collect a return on the unrecovered balance.
Customer advocates appealed the decision in court, and a settlement between PGE, commission staff and the CitizensÂ’ Utility Board, approved by the OPUC in 2000, removed the rest of the Trojan balance from the companyÂ’s books. Part of the settlement required PGE to write off an additional $5 million (after tax).
Later court decisions said that while recovery of the Trojan investment was legal, it was not legal for the OPUC to authorize collection of a return on the unrecovered balance. The courts sent the issue back to the OPUC to determine if the prices customers paid for electricity were too high as a result of the commission’s previous decisions, and if so what – if anything – needed to be done to fix the problem.
Related News

Quebec authorizes nearly 1,000 megawatts of electricity for 11 industrial projects
MONTREAL - The Quebec government has unveiled the list of 11 companies whose projects were given the go-ahead for large-scale power connections of 5 megawatts or more, for a total of 956 MW.
Five of the selected projects relate to the battery sector, and two to the bioenergy sector.
TES Canada's plan to build a green hydrogen production plant in Shawinigan, announced on Friday, is on the list.
Hydro-Québec will also supply 5 MW or more to the future Northvolt plant at its facilities in Saint-Basile-le-Grand and McMasterville.
Other industrial projects selected are those of Air Liquide Canada, Ford-Ecopro CAM Canada S.E.C, Nouveau monde…