Ameren buries hopes for buried power lines, puts efforts into tree trimming

By Knight Ridder Tribune


NFPA 70e Training

Our customized live online or in‑person group training can be delivered to your staff at your location.

  • Live Online
  • 6 hours Instructor-led
  • Group Training Available
Regular Price:
$199
Coupon Price:
$149
Reserve Your Seat Today
In Missouri, they're digging deep to keep the lights on.

Stung by massive power outages caused by ice and wind storms last year, the AmerenUE utility is spending $300 million in a three-year program to bury cables now seen as particularly vulnerable. The idea is that ice-laden or wind-tossed branches can't bring down lines once they're safely tucked several feet underground.

But in Central Illinois, an area just as badly ravaged by those storms, there is no similar initiative. AmerenIP is part of the same Ameren Corp. business family as AmerenUE, but they have their own budgets and their own approaches to safeguarding power supplies. AmerenIP says power lines for many new developments are placed underground because it's cheaper to do it at the start of construction, and developers are willing to pay for it.

The company says "undergrounding" existing cables in older neighborhoods, however, is staggeringly expensive, working out at something like $1 million a mile. Natalie Hemmer, an AmerenIP spokeswoman, said especially troublesome cables may be buried underground, but the company has no large-scale program to do this or the means to pay for it. She says AmerenIP, along with its sister Illinois utilities AmerenCIPS and AmerenCILCO, is jointly spending some $110 million over the next three years on an aggressive tree-trimming initiative to protect power lines.

She also points to a $114 million program to "harden" the electrical system by installing devices that contain the affects of power cuts by limiting the number of homes and businesses losing power.

Hemmer says burying cables might be the way to go in an ideal world, but any widespread effort to do it now would involve passing on massive costs to already hard-pressed consumers. "In 2007, our focus has been on rate relief," she said. "We want to get customers rate relief to help ease some of the bills they've been experiencing." But having to melt snow to flush your toilets after the power has gone off has a way of changing outlooks on the pros and cons of burying cables. Decatur couple Carol and Joe Thomas had to do that during last winter's ice storm when the power went off and they were left without heat, lights or water pressure.

Ice-laden branches had taken down power cables serving their street, and the lines stayed down for five days. "Buried cables for us obviously would have been a plus," said Carol Thomas, 59, who is disabled and has difficulty walking. "And while it may be expensive, look at how much money the power company had to spend in overtime and everything to repair all those lines. That cost was horrendous and would go a long way to putting some of these lines underground."

In December, Ameren Corp. estimated that the post-ice storm repair bill for its utilities topped $100 million. Hundreds of thousands of customers in Illinois and Missouri were left without power, and 7,000 linemen from 14 states were called in to make repairs that took weeks to finish.

AmerenUE decided enough was enough and launched Project Power On, which includes a cable-burying program in a $1 billion push that will also spend $84 million on upgrading cables and equipment and $135 million on tree trimming. Another $500 million is being spent on cleaning up power station emissions.

The Missouri electrical market is still regulated, unlike the Illinois market, and $200 million of Project Power On was approved in extra power charges agreed by state officials who oversee electricity rates. AmerenUE spokesman Tim Fox said the company ould expect to gradually get its investment back "over a long period of time" from increased customer charges but was more interested right now in keeping the lights on.

He said burying cables won't guarantee power supplies will never be interrupted, but the aim was to limit the damage. "So the hope is we'll see fewer outages and quicker restoration times," he added.

The Illinois Commerce Commission, which oversees utilities in this state, says there may be no widespread policies of burying power cables here, but that doesn't mean utilities aren't being held to higher standards. ICC spokesman Brian Sterling said the commission put "feet to the fire" to make sure utilities such as AmerenIP improve tree trimming procedures to safeguard lines.

And more pressure may be coming: A preliminary report, commissioned by the ICC, is due before the end of the year looking at how Ameren utilities dealt with the aftermath of the ice storm and earlier windstorms.

Related News

Alberta Leads the Way in Agrivoltaics

Agrivoltaics in Alberta integrates solar energy with agriculture, boosting crop yields and water conservation. The Strathmore Solar project showcases dual land use, sheep grazing for vegetation control, and PPAs that expand renewable energy capacity.

 

Key Points

A dual-use model where solar arrays and farming co-exist, boosting yields, saving water, and diversifying revenue.

✅ Strathmore Solar: 41 MW on 320 acres with managed sheep grazing

✅ 25-year TELUS PPA secures power and renewable energy credits

✅ Panel shade cuts irrigation needs and protects crops from extremes

 

Alberta is emerging as a leader in agrivoltaics—the innovative practice of integrating solar energy production with agricultural activities, aligning with the province's red-hot solar growth in recent years. This approach not only generates renewable energy but also enhances crop yields, conserves water, and supports sustainable farming practices. A notable example of this synergy is the Strathmore Solar project, a 41-megawatt solar farm located on 320 acres of leased industrial land owned by the Town of Strathmore. Operational since March 2022, it exemplifies how solar energy and agriculture can coexist and thrive together.

The Strathmore Solar Initiative

Strathmore Solar is a collaborative venture between Capital Power and the Town of Strathmore, with a 25-year power purchase agreement in place with TELUS Corporation for all the energy and renewable energy credits generated by the facility. The project not only contributes significantly to Alberta's renewable energy capacity, as seen with new solar facilities contracted at lower cost across the province, but also serves as a model for agrivoltaic integration. In a unique partnership, 400 to 600 sheep from Whispering Cedars Ranch are brought in to graze the land beneath the solar panels. This arrangement helps manage vegetation, reduce fire hazards, and maintain the facility's upkeep, all while providing shade for the grazing animals. This mutually beneficial setup maximizes land use efficiency and supports local farming operations, illustrating how renewable power developers can strengthen outcomes with integrated designs today. 

Benefits of Agrivoltaics in Alberta

The integration of solar panels with agricultural practices offers several advantages for a province that is a powerhouse for both green energy and fossil fuels already across sectors:

  • Enhanced Crop Yields: Studies have shown that crops grown under solar panels can experience increased yields due to reduced water evaporation and protection from extreme weather conditions.

  • Water Conservation: The shade provided by solar panels helps retain soil moisture, leading to a decrease in irrigation needs.

  • Diversified Income Streams: Farmers can generate additional revenue by selling renewable energy produced by the solar panels back to the grid.

  • Sustainable Land Use: Agrivoltaics allows for dual land use, enabling the production of both food and energy without the need for additional land.

These benefits are evident in various agrivoltaic projects across Alberta, where farmers are successfully combining crop cultivation with solar energy production amid a renewable energy surge that is creating thousands of jobs.

Challenges and Considerations

While agrivoltaics presents numerous benefits, there are challenges to consider as Alberta navigates challenges with solar expansion today across Alberta:

  • Initial Investment: The setup costs for agrivoltaic systems can be high, requiring significant capital investment.

  • System Maintenance: Regular maintenance is essential to ensure the efficiency of both the solar panels and the agricultural operations.

  • Climate Adaptability: Not all crops may thrive under the conditions created by solar panels, necessitating careful selection of suitable crops.

Addressing these challenges requires careful planning, research, and collaboration between farmers, researchers, and energy providers.

Future Prospects

The success of projects like Strathmore Solar and other agrivoltaic initiatives in Alberta indicates a promising future for this dual-use approach. As technology advances and research continues, agrivoltaics could play a pivotal role in enhancing food security, promoting sustainable farming practices, and contributing to Alberta's renewable energy goals. Ongoing projects and partnerships aim to refine agrivoltaic systems, making them more efficient and accessible to farmers across the province.

The integration of solar energy production with agriculture in Alberta is not just a trend but a transformative approach to sustainable farming. The Strathmore Solar project serves as a testament to the potential of agrivoltaics, demonstrating how innovation can lead to mutually beneficial outcomes for both the agricultural and energy sectors.

 

 

Related News

View more

'Net Zero' Emissions Targets Not Possible Without Multiple New Nuclear Power Stations, Say Industry Leaders

UK Nuclear Power Expansion is vital for low-carbon baseload, energy security, and Net Zero, complementing renewables like wind and solar, reducing gas reliance, and unlocking investment through clear financing rules and proven, dependable reactor technology.

 

Key Points

Accelerating reactor build-out for low-carbon baseload to boost energy security and help deliver the UK Net Zero target.

✅ Cuts gas dependence and stabilizes grids with firm capacity.

✅ Complements wind and solar for reliable, low-carbon supply.

✅ Needs clear financing to unlock investment and lower costs.

 

Leading nuclear industry figures will today call for a major programme of new power stations to hit ambitious emissions reduction targets.

The 19th Nuclear Industry Association annual conference in London will highlight the need for a proven, dependable source of low carbon electricity generation alongside growth in weather-dependent solar and wind power, and particularly the rapid expansion of wind and solar generation across the UK.

Without this, they argue, the country risks embedding a major reliance on carbon-emitting gas fired power stations as Europe loses nuclear capacity at a critical time for energy security for generations to come.

Annual public opinion polling released today to coincide with the conference revealed 75% of the population want the UK Government to take more action to reduce CO2 emissions.

The survey, conducted by YouGov in October 2019, has tracked opinion trends on nuclear for more than a decade. It shows continued and consistent public support for an energy mix including nuclear and renewables, with 72% of respondents agreeing this was needed to ensure a reliable supply of electricity.

Nuclear power was also perceived as the most secure energy source for keeping the lights on, compared to other sources such as oil, gas, coal, wind power, fracking and solar power.

Last month both the Labour and Conservative Parties committed to new nuclear power as part of their election Manifestos and the government's wider green industrial revolution plans for clean growth. At the same time, 27 leading figures in the fields of environment, energy, and industry signed an open letter addressed to parliamentary candidates, which set out the benefits of nuclear and underscored the consequences of not, at least, replacing the UK's current fleet of power stations.

The Nuclear Industry Association said there is no time to be lost in clarifying the ambition and the financing rules for new nuclear power which would bring down costs and unlock a major programme of investment.

Tom Greatrex, Chief Executive of the NIA, said "We have to grow the industry's contribution to a low carbon economy. The independent Committee on Climate Change said earlier this year that we need a variety of technologies including nuclear power/1 for net zero to reach the UK's Net Zero emissions target by 2050".

"This is a proven, dependable, technology with lower lifecycle CO2 emissions than solar power and the same as offshore wind/2. It is also an important economic engine for the UK, supporting uses beyond electricity and creating high quality direct and indirect employment for around 155,000 people."

"Right now nuclear provides 20%/3 of all the UK's electricity but all but one of our existing fleet will close over the next decade, amid the debate over nuclear's decline as power demand will only increase with a shift to electric heating and vehicles."

"The countries and regions which have most successfully decarbonised, like Sweden, France and Ontario in Canada, have done so by relying on nuclear, aligning with Canada's climate goals for affordable, safe power today. You are not serious about tackling climate change if you are not serious about nuclear".

 

Related News

View more

Clean-energy generation powers economy, environment

Atlin Hydro and Transmission Project delivers First Nation-led clean energy via hydropower to the Yukon grid, replacing diesel, cutting emissions, and creating jobs, with a 69-kV line from Atlin, B.C., supplying about 35 GWh annually.

 

Key Points

A First Nation-led 8.5 MW hydropower and 69-kV line supplying clean energy to the Yukon, reducing diesel use.

✅ 8.5 MW capacity; ~35 GWh annually to Yukon grid

✅ 69-kV, 92 km line links Atlin to Jakes Corner

✅ Creates 176 construction jobs; cuts diesel and emissions

 

A First Nation-led clean-power generation project for British Columbia’s Northwest will provide a significant economic boost and good jobs for people in the area, as well as ongoing revenue from clean energy sold to the Yukon.

“This clean-energy project has the potential to be a win-win: creating opportunities for people, revenue for the community and cleaner air for everyone across the Northwest,” said Premier John Horgan. “That’s why our government is proud to be working in partnership with the Taku River Tlingit First Nation and other levels of government to make this promising project a reality. Together, we can build a stronger, cleaner future by producing more clean hydropower to replace fossil fuels – just as they have done here in Atlin.”

The Province is contributing $20 million toward a hydroelectric generation and transmission project being developed by the Taku River Tlingit First Nation (TRTFN) to replace diesel electricity generation in the Yukon, which is also supported by the Government of Yukon and the Government of Canada, and comes as BC Hydro demand fell during COVID-19 across the province.

“Renewable-energy projects are helping remote communities reduce the use of diesel for electricity generation, which reduces air pollution, improves environmental outcomes and creates local jobs,” said Bruce Ralston, Minister of Energy, Mines and Low Carbon Innovation. “This project will advance reconciliation with TRTFN, foster economic development in Atlin and support intergovernmental efforts to reduce greenhouse gas emissions.”

TRTFN is based in Atlin with territory in B.C., the Yukon, and Alaska. TRTFN is an active participant in clean-energy development and, since 2009, has successfully replaced diesel-generated electricity in Atlin with a 2.1-megawatt (MW) hydro facility amid oversight issues such as BC Hydro misled regulator elsewhere in the province today.

TRTFN owns the Tlingit Homeland Energy Limited Partnership (THELP), which promotes economic development through clean energy. THELP plans to expand its hydro portfolio by constructing the Atlin Hydro and Transmission Project and selling electricity to the Yukon via a new transmission line, in a landscape shaped by T&D rates decisions in jurisdictions like Ontario for cost recovery.

The Government of Yukon is requiring its Yukon Energy Corporation (YEC) to generate 97% of its electricity from renewable resources by 2030. This project provides an opportunity for the Yukon government to reduce reliance on diesel generators and to meet future load growth, at a time when Manitoba Hydro's debt pressures highlight utility cost challenges.

The new transmission line between Atlin and the Yukon grid will include a fibre-optic data cable to support facility operations, with surplus capacity that can be used to bring high-speed internet connectivity to Atlin residents for the first time.

“Opportunities like this hydroelectricity project led by the Taku River Tlingit First Nation is a great example of identifying and then supporting First Nations-led clean-energy opportunities that will support resilient communities and provide clean economic opportunities in the region for years to come. We all have a responsibility to invest in projects that benefit our shared climate goals while advancing economic reconciliation.” said George Heyman, Minister of Environment and Climate Change Strategy.

“Thank you to the Government of British Columbia for investing in this important project, which will further strengthen the connection between the Yukon and Atlin. This ambitious initiative will expand renewable energy capacity in the North in partnership with the Taku River Tlingit First Nation while reducing the Yukon’s emissions and ensuring energy remains affordable for Yukoners.“ said Sandy Silver, Premier of Yukon.

“The Atlin Hydro Project represents an important step toward meeting the Yukon’s growing electricity needs and the renewable energy targets in the Our Clean Future strategy. Our government is proud to contribute to the development of this project and we thank the Government of British Columbia and all partners for their contributions and commitment to renewable energy initiatives. This project demonstrates what can be accomplished when communities, First Nations and federal, provincial and territorial governments come together to plan for a greener economy and future.” said John Streicker, Minister Responsible for the Yukon Development Corporation. 

“Atlin has enjoyed clean and renewable energy since 2009 because of our hydroelectric project. Over its lifespan, Atlin’s hydro opportunity will prevent more than one million tonnes of greenhouse gases from being created to power the southern Yukon. We are looking forward to the continuation of this project. Our collective dream is to meet our environmental and economic goals for the region and our local community within the next 10 years. We are so grateful to all our partners involved for their financial support, as we continue onward in creating an energy efficient and sustainable North.” said Charmaine Thom, Taku River Tlingit First Nation spokesperson.

Quick Facts:

  • The 8.5-MW project is expected to provide an average of 35 gigawatt hours of energy annually to the Yukon. To accomplish this, TRTFN plans to leverage the existing water storage capability of Surprise Lake, add new infrastructure, and send power 92 km north to Jakes Corner, Yukon, along a new 69-kilovolt transmission line.
  • The project is expected to cost $253 - 308.5 million, the higher number reflecting recently estimated impacts of inflation and supply chain cost escalation, alongside sector accounting concerns such as deferred BC Hydro costs noted in recent reports.
  • The project is expected to have a positive impact on local and provincial economic development in the form of, even as governance debates like Manitoba Hydro board changes draw attention elsewhere:
  • 176 full-time positions during construction;
  • six to eight full-time positions in operations and maintenance over 40 years; and
  • increased business for B.C. contractors.
  • Territorial and federal funders have committed $151.1 million to support the project, most recently the $32.2 million committed in the 2022 federal bdget.

 

Related News

View more

Minister approves 30-megawatt wind farm expansion in Eastern Kings

Eastern Kings Wind Farm Expansion advances P.E.I. renewable energy with seven new wind turbines, environmental assessment, wildlife monitoring of birds and bats, and community consultation to double output to 30 MW for domestic consumption.

 

Key Points

A P.E.I. project adding seven turbines for 30 MW, under 17 conditions, with wildlife monitoring and community oversight.

✅ Seven new turbines, larger than existing units

✅ 17 conditions, monthly compliance reporting

✅ Two-year wildlife study for birds and bats

 

A proposal to expand an existing wind farm in eastern P.E.I. has been given the go-ahead, according to P.E.I.’s Department of Environment, Water and Climate Change, as related grid work like a new transmission line progresses in the region.

Minister Natalie Jameson approved the P.E.I. Energy Corporation’s Eastern Kings Wind Farm expansion project, the province announced in a release Wednesday afternoon, as Atlantic Canada advances other renewable initiatives like tidal power to diversify supply.

The project will be subject to 17 conditions, which were drawn from a review of the 80 responses the province received from the public on the proposed Eastern Kings Wind Farm expansion.

The corporation must provide a summary on the status of each condition to the department on a monthly basis.

“This decision balances the needs of people, communities, wellness and the environment,” Jameson said in the release.

“It allows this renewable energy project to proceed and reduce greenhouse [gas] emissions that cause climate change while mitigating the project’s impact to the Island’s ecosystem.”

The P.E.I. Energy Corporation wants to double the output of its Eastern Kings Wind Farm with the installation of seven wind turbines between the communities of Elmira and East Point to develop 30 megawatts of wind power for domestic consumption, according to the minister’s impact assessment, aligning with regional moves to expand wind and solar projects across Atlantic Canada.

The new turbines are expected to be larger than the existing 10 at the site, even as regional utilities study major grid changes to integrate more renewables.

Project must comply with conditions

In February, the province said it would identify any specific questions or concerns it felt needed to be addressed in the submissions, according to Greg Wilson, manager of environmental land management for the province, while some advocate for independent electricity planning to guide such decisions.

Public feedback closed in January, after an earlier extension to wait for a supplemental report on birds and bats.

The corporation needs to comply with all conditions – such as monitoring environmental impact, setting up an environmental management plan and creating a committee to address concerns – listed in the release on Wednesday, amid calls from environmental advocates to reduce biomass use in electricity generation.

A condition in the release suggests representatives from L’nuey, the Souris and Area Wildlife Branch, the Rural Municipality of Eastern Kings and local residents to make up the committee.

The corporation will also need to conduct a study over two years after construction to look at the impact on bats and birds, and implement a protocol to report deaths of birds to federal and provincial authorities.

According to Canada Energy Regulator, roughly 98 per cent of power generated on P.E.I. comes from wind farms. It also said there were 203 megawatts installed on P.E.I. as of 2018, and the majority of energy consumed on the Island comes from New Brunswick from a mix of nuclear, fossil fuels and hydroelectricity, while in Nova Scotia, the utility has increased biomass generation as part of its supply mix.

 

Related News

View more

Gov. Greg Abbott touts Texas power grid's readiness heading into fall, election season

ERCOT Texas Fall Grid Forecast outlines ample power supply, planned maintenance outages, and grid reliability, citing PUC oversight and Gov. Abbott's remarks, with seasonal assessment noting mild demand yet climate risks and conservation alerts.

 

Key Points

ERCOT's seasonal outlook for Texas on fall power supply, outages, and reliability expectations under PUC oversight.

✅ Projects sufficient supply in October and November

✅ Many plants scheduled offline for maintenance

✅ Notes PUC oversight and Abbott's confidence

 

Gov. Greg Abbott said Tuesday that the Texas power grid is prepared for the fall months and referenced a new seasonal forecast by the state’s grid operator, which typically does not draw much attention to its fall and spring grid assessments because of the more mild temperatures during those seasons.

Tuesday’s new forecast by the Electric Reliability Council of Texas showed that there should be plenty of power supply to meet demand in October and November. It also showed that many Texas power plants are scheduled to be offline this fall for maintenance work. Texas power plants usually plan to go down in the fall and spring for repairs to improve reliability ahead of the more extreme temperatures in winter and summer, when Texans crank up their heat and air conditioning and raise demand for power.

ERCOT for at least a decade announced its seasonal forecasts, but did not do so on Tuesday. The grid operator stopped announcing the reports after the 2021 winter storm event. A spokesperson for the grid operator, which posted the report to its website midday without notifying the public or power industry stakeholders, said there were no plans to discuss the latest forecast and referred questions about it to the Public Utility Commission, which oversees ERCOT. Abbott appoints the board of the PUC.

Abbott on Tuesday expressed his confidence about the grid in a news release, which included photos of the governor sitting at a table with incoming ERCOT CEO Pablo Vegas, outgoing interim CEO Brad Jones and Public Utility Commission Chair Peter Lake.

“The State of Texas continues to monitor the reliability of our electric grid, and I thank ERCOT and PUC for their hard work to implement bipartisan reforms we passed last year and for their proactive leadership to ensure our grid is stronger than ever before,” Abbott said in the release.

Abbott has not previously shared or called attention to ERCOT’s forecasts as he did on Tuesday.

Up for reelection this fall, Abbott has faced continued criticism, including from the Sierra Club over his handling of the 2021 deadly power grid disaster, when extended freezing temperatures shut down natural gas facilities and power plants, which rely on each other to keep electricity flowing. The resulting blackouts left millions of Texans without power for days in the cold, and hundreds of people died.

ERCOT’s forecasts for fall and spring are typically the least worrisome seasonal forecasts, energy experts said, because temperatures are usually milder in between summer and winter, even as ERCOT has issued an RFP to procure winter capacity to address shortages, so demand for power usually does not skyrocket like it does during extreme temperatures.

But they’ve warned that climate change could potentially lead to more extreme temperatures during times when Texas hasn’t experienced such weather in the past. For example, in early May six power plants unexpectedly broke down when a spring heat wave drove power demand up and highlighted broader heat-related blackout risks across the grid. ERCOT asked Texans to conserve electricity at home at the time.

Abbott released the seasonal report at a time when he has asserted unprecedented control over ERCOT. Although he had no formal role in ERCOT’s search for a new permanent CEO, he put a stranglehold on the process, The Texas Tribune previously reported. Since the winter storm, Abbott’s office has also dictated what information about the power grid ERCOT has released to the public.

 

Related News

View more

Spent fuel removal at Fukushima nuclear plant delayed up to 5 years

Fukushima Daiichi decommissioning delay highlights TEPCO's revised timeline, spent fuel removal at Units 1 and 2, safety enclosures, decontamination, fuel debris extraction by robot arm, and contaminated water management under stricter radiation control.

 

Key Points

A government revised schedule pushing back spent fuel removal and decommissioning milestones at Fukushima Daiichi.

✅ TEPCO delays spent fuel removal at Units 1 and 2 for safety.

✅ Enclosures, decontamination, and robotics mitigate radioactive risk.

✅ Contaminated water cut target: 170 tons/day to 100 by 2025.

 

The Japanese government decided Friday to delay the removal of spent fuel from the Fukushima Daiichi nuclear power plant's Nos. 1 and 2 reactors by as much as five years, casting doubt on whether it can stick to its timeframe for dismantling the crippled complex.

The process of removing the spent fuel from the units' pools had previously been scheduled to begin in the year through March 2024.

In its latest decommissioning plan, the government said the plant's operator, Tokyo Electric Power Company Holdings Inc., will not begin the roughly two-year process (a timeline comparable to major reactor refurbishment programs seen worldwide) at the No. 1 unit at least until the year through March 2028 and may wait until the year through March 2029.

Work at the No. 2 unit is now slated to start between the year through March 2025 and the year through March 2027, it said.

The delay is necessary to take further safety precautions such as the construction of an enclosure around the No. 1 unit to prevent the spread of radioactive dust, and decontamination of the No. 2 unit, even as authorities have begun reopening previously off-limits towns nearby, the government said. It is the fourth time it has revised its schedule for removing the spent fuel rods.

"It's a very difficult process and it's hard to know what to expect. The most important thing is the safety of the workers and the surrounding area," industry minister Hiroshi Kajiyama told a press conference.

The government set a new goal of finishing the removal of the 4,741 spent fuel rods across all six of the plant's reactors by the year through March 2032, amid ongoing debates about the consequences of early nuclear plant closures elsewhere.

Plant operator TEPCO has started the process at the No. 3 unit and already finished at the No. 4 unit, which was off-line for regular maintenance at the time of the disaster. A schedule has yet to be set for the Nos. 5 and 6 reactors.

While the government maintained its overarching timeframe of finishing the decommissioning of the plant 30 to 40 years from the 2011 crisis triggered by a magnitude 9.0 earthquake and tsunami, there may be further delays, even as milestones at other nuclear projects are being reached worldwide.

The government said it will begin removing fuel debris from the three reactors that experienced core meltdowns in the year through March 2022, starting with the No. 2 unit as part of broader reactor decommissioning efforts.

The process, considered the most difficult part of the decommissioning plan, will involve using a robot arm, reflecting progress in advanced reactors technologies, to initially remove small amounts of debris, moving up to larger amounts.

The government also said it will aim to reduce the pace at which contaminated water at the plant increases. Water for cooling the melted cores, mixed with underground water, amounts to around 170 tons a day. That number will be brought down to 100 tons by 2025, it said.

The water is being treated to remove the most radioactive materials and stored in tanks on the plant's grounds, but already more than 1 million tons has been collected and space is expected to run out by the summer of 2022.

 

Related News

View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers