Underwater power cable planned for Lake Champlain
At a public meeting in Ray Brook, Adirondack Park Agency staff member Holly Kneeshaw said the design calls for the power line to be submerged under the water of Lake Champlain.
"The transmission line consists of two 1,000 megawatt high voltage direct current bi-poles," Kneeshaw said.
The lines will be "submarined" the length of Lake Champlain to Whitehall, according to Kneeshaw.
"They will go down the Champlain Canal and overland around Fort Edward and then back into the [Hudson] River again, and then down to New York City," she added.
Hydro-Quebec is a major supplier of electricity to the northeastern U.S.
The 300-mile-long corridor, called the “Champlain-Hudson Express Project” would carry power to New York City.
According to Kneeshaw, state environment officials with the DEC are reviewing the plan.
The state has been looking for ways to build new power transmission lines across the North Country without disrupting scenery or communities.
Related News

Ontario confronts reality of being short of electricity in the coming years
TORONTO - In a fit of ideological pique, Doug Ford’s government spent more than $200 million to scrap more than 700 green energy projects soon after winning the 2018 election, portraying them as “unnecessary and expensive energy schemes.”
A year later, then Associate Energy Minister Bill Walker defended the decision, declaring, “Ontario has an adequate supply of power right now.”
Well, life moves fast. At the time, scrapping the renewable energy projects was criticized as short-sighted and wasteful. It seems especially so now as Ontario confronts the reality of being short of electricity in the coming years.
How short? A recent report by…