AEP coal-plant construction faces new hurdles


High Voltage Maintenance Training Online

Our customized live online or in‑person group training can be delivered to your staff at your location.

  • Live Online
  • 12 hours Instructor-led
  • Group Training Available
Regular Price:
$599
Coupon Price:
$499
Reserve Your Seat Today
Texas regulators added two cost-related caveats to a final order approving American Electric Power Co's plan to build a coal-fired power plant in Arkansas while regulators in that state delayed action on the unit's air permit.

In its final order the Texas Public Utility Commission said Texas customers of AEP's Southwestern Electric Power Co (SWEPCO) unit will pay no more their share of the $1.52 billion price tag to build the 600-megawatt John W Turk Jr. coal-fired plant in Fulton, Arkansas.

"This cap on the capital cost of the Turk plant limits the financial risk to Texas ratepayers," the order said.

Texas regulators, who voted last month to approve the plant, also limited the amount of future carbon-mitigation costs than can be passed to Texas ratepayers at $28 per ton through 2030.

Estimated costs for carbon mitigation ranged from $13 to $70 per ton, with the average between $30-$45, the order said.

SWEPCO spokesman Scott McCloud said the utility is evaluating the final order and had no comment on whether the company would file an appeal.

Commissioner Julie Parsley, who voted against SWEPCO's plan, said both stipulations "are not legally enforceable" on future commissions.

Meanwhile, issuance of an air permit for Turk, tentatively approved by the air division of the Arkansas Department of Environmental Quality, will be delayed from the third quarter, McCloud said, after that agency scheduled a second public hearing to allow comment on SWEPCO's plan to control mercury emissions.

While not required, the agency decided to hold a hearing next month on the mercury issue after a federal court ruling halted implementation of the Clean Air Mercury Rule.

AEP revised its Turk application to comply with Arkansas mercury emission rules leading to a need for additional public input. No permit can be issued until response to public comments are completed, an agency spokesman said.

Rising construction costs and climate-change worry have led utilities to cancel dozens of proposed coal-fired units in the past two years. Even so, more coal plants are being built in the U.S. now than two decades, according to a government report.

About 29 coal plants with a capacity exceeding 15,000 MW are under construction. Another 20 projects have permits or are near construction. Operation of the Turk plant is expected in the second half of 2012.

Related News

Ontario unveils new tax breaks, subsidized hydro plan to spur economic recovery from COVID-19

Ontario COVID-19 Business Tax Relief outlines permanent Employer Health Tax exemptions, lower Business Education Tax…
View more

Washington AG Leads Legal Challenge Against Trump’s Energy Emergency

Washington-Led Lawsuit Against Energy Emergency challenges President Trump's executive order, citing state rights, environmental reviews,…
View more

Why Canada's Energy Security Hinges on Renewables

Renewable Energy Security strengthens affordability and grid reliability through electrification, wind, and solar, reducing fossil…
View more

Pandemic has already cost Hydro-Québec $130 million, CEO says

Hydro-Que9bec 2020 Profit Outlook faces COVID-19 headwinds as revenue drops, U.S. Northeast export demand weakens,…
View more

Powering Towards Net Zero: The UK Grid's Transformation Challenge

UK Electricity Grid Investment underpins net zero, reinforcing transmission and distribution networks to integrate wind,…
View more

PG&E keeps nearly 60,000 Northern California customers in the dark to reduce wildfire risk

PG&E Public Safety Power Shutoff reduces wildfire risk during extreme winds, triggering de-energization across the…
View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Live Online & In-person Group Training

Advantages To Instructor-Led Training – Instructor-Led Course, Customized Training, Multiple Locations, Economical, CEU Credits, Course Discounts.

Request For Quotation

Whether you would prefer Live Online or In-Person instruction, our electrical training courses can be tailored to meet your company's specific requirements and delivered to your employees in one location or at various locations.