ATC to rebuild transmission line in western Kenosha County
“This project will help maintain reliability of the electric transmission system,” said Mary Carpenter, senior local relations representative. “The existing transmission line was originally built in 1947, and this rebuild will allow the system to meet current and future electricity loads.”
This project involves replacing the aging H-frame wooden poles with new H-frame wooden poles. The existing wires strung between the poles also will be replaced with larger wires to increase the line capacity. No new right-of-way is needed, and the new poles will be placed within a few feet of the existing poles. ATC will work with landowners to access the right-of-way through their property if necessary.
Construction is expected to begin in fall 2014, with completion in early 2015. The estimated cost of the project is $11.5 million. Landowners along the right-of-way have been informed of the project and will continue to be kept apprised as the project proceeds.
Related News

'Transformative change': Wind-generated electricity starting to outpace coal in Alberta
EDMONTON - Marking a significant shift in Alberta energy history, wind generation provided more power to the province's energy grid than coal several times this week.
According to data from the Alberta Energy System Operator (AESO), wind generation units contributed more energy to the grid than coal at times for several days. On Friday afternoon, wind farms contributed more than 1,700 megawatts of power to the grid, compared to around 1,260 megawatts from coal stations.
"The grid is going through a period of transformative change when we look at the generation fleet, specifically as it relates to the coal assets in the…