“This project will help maintain reliability of the electric transmission system,” said Mary Carpenter, senior local relations representative. “The existing transmission line was originally built in 1947, and this rebuild will allow the system to meet current and future electricity loads.”
This project involves replacing the aging H-frame wooden poles with new H-frame wooden poles. The existing wires strung between the poles also will be replaced with larger wires to increase the line capacity. No new right-of-way is needed, and the new poles will be placed within a few feet of the existing poles. ATC will work with landowners to access the right-of-way through their property if necessary.
Construction is expected to begin in fall 2014, with completion in early 2015. The estimated cost of the project is $11.5 million. Landowners along the right-of-way have been informed of the project and will continue to be kept apprised as the project proceeds.
Related News
US nuclear innovation act becomes law
Judge: Texas Power Plants Exempt from Providing Electricity in Emergencies
Hydro One crews restore power to more than 277,000 customers following damaging storms in Ontario
Hydro-Quebec begins talks for $185-billion strategy to wean the province off fossil fuels
UK families living close to nuclear power stations could get free electricity
International Atomic Energy Agency agency commends China's nuclear security
Sign Up for Electricity Forum’s Newsletter
Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.
Electricity Today T&D Magazine Subscribe for FREE
- Timely insights from industry experts
- Practical solutions T&D engineers
- Free access to every issue