ATC to rebuild transmission line in western Kenosha County
“This project will help maintain reliability of the electric transmission system,” said Mary Carpenter, senior local relations representative. “The existing transmission line was originally built in 1947, and this rebuild will allow the system to meet current and future electricity loads.”
This project involves replacing the aging H-frame wooden poles with new H-frame wooden poles. The existing wires strung between the poles also will be replaced with larger wires to increase the line capacity. No new right-of-way is needed, and the new poles will be placed within a few feet of the existing poles. ATC will work with landowners to access the right-of-way through their property if necessary.
Construction is expected to begin in fall 2014, with completion in early 2015. The estimated cost of the project is $11.5 million. Landowners along the right-of-way have been informed of the project and will continue to be kept apprised as the project proceeds.
Related News

IEA warns fall in global energy investment may lead to shortages
MELBOURNE - An almost 20 per cent fall in global energy investment over the past three years could lead to oil and electricity shortages, and there are concerns about whether current business models will encourage sufficient levels of spending in the future, according a new report.
The International Energy Agency’s second annual IEA benchmark analysis of energy investment found that while the world spent $US1.7 trillion ($2.2 trillion) on fossil-fuel exploration, new power plants and upgrades to electricity grids last year, global energy investment was down 12 per cent from a year earlier and 17 per cent lower than 2014.
While the…