Fuel tube problems plague Point Lepreau


NFPA 70E Training

Our customized live online or in‑person group training can be delivered to your staff at your location.

  • Live Online
  • 6 hours Instructor-led
  • Group Training Available
Regular Price:
$199
Coupon Price:
$149
Reserve Your Seat Today

Point Lepreau calandria tube removal signals nuclear reactor refurbishment delays, as AECL and NB Power reseal 380 tubes, driving over-budget costs, replacement power purchases, and rate pressures in New Brunswick and P.E.I.

 

The Big Picture

NB Power and AECL are removing and resealing all 380 tubes, extending refurbishment timelines, costs, and rate impacts.

  • All 380 calandria tubes to be removed, reinstalled, and resealed
  • Outage drives $1M/day replacement power purchases
  • Refurbishment already over budget and behind 2009 schedule
  • Completion now forecast Oct 2011; generation by Feb 2012
  • Rate freeze pledge at risk; P.E.I. faces $50M by 2011

 

NB Power has announced that Atomic Energy of Canada Ltd. will have to start over with one of the most important parts of the refurbishment of the Point Lepreau nuclear plant.

 

The federal Crown corporation is going to remove all 380 calandria tubes (removing radioactive tubes) to reinstall and reseal them, which could further delay the completion of a project that is already more than a year behind schedule.

It has been estimated that NB Power will have to pay $1 million a day to purchase replacement power while the reactor is not in service.

"Project staff are proceeding with the removal of all 380 calandria tubes," said an NB Power statement.

"We do not have specific details from AECL on how it will impact the overall timeline of the project. In our continued efforts to be open and transparent with our employees and customers, we are releasing this information to you now as this is currently happening and will provide you with more detailed information as it becomes available later next week."

The calandria tubes are made to house smaller nuclear pressure tubes, which in turn contain radioactive nuclear fuel bundles.

They were the first major piece of equipment to be installed in the reactor as part of the much-delayed refurbishment of the 27-year-old generating station in southern New Brunswick.

The Point Lepreau refurbishment, which began on March 28, 2008, is expected to extend the generating station's life by 25 to 30 years. It was supposed to be completed by September 2009.

Before Friday's announcement, the $1.4-billion refurbishment was already hundreds of millions of dollars over budget amid Point Lepreau overruns that kept growing.

The most optimistic recent forecasts estimate the refurbishment will be completed by October 2011, and NB Power will need until February 2012 to get the power plant to begin generating electricity again.

The removal of the original calandria tubes took AECL one year.

With the delays, the incoming Progressive Conservatives will be in charge of a refurbishment deal they signed up for in 2005, when they were led by Bernard Lord, as the province and Areva outlined nuclear plans at the time.

The newest delay could be a problem for David Alward, the newly elected premier. He promised a three-year rate freeze proposal on power rates, which was calculated on the assumption the reactor would be operational in February.

NB Power, which rejected compensation in 2002, predicted in April that power rates would rise an additional three per cent next year because of the refurbishment cost overruns.

The delay also causes problems for electricity users on P.E.I., where Maritime Electric buys about 20 per cent of its energy from the New Brunswick plant and could cost millions for customers.

Related News

Manitoba Hydro scales back rate increase next year

Manitoba Hydro 3.5 Percent Rate Increase proposes a smaller electricity rate hike under Public Utilities…
View more

Ford's Washington Meeting: Energy Tariffs and Trade Tensions with U.S

Ontario-U.S. Energy Tariff Dispute highlights cross-border trade tensions, retaliatory tariffs, export surcharges, and White House…
View more

Power firms win UK subsidies for new Channel cables project

UK Electricity Interconnectors secure capacity market subsidies, supporting winter reliability with seabed cables to France…
View more

Imported coal volumes up 17% during Apr-Oct as domestic supplies shrink

India Thermal Power Coal Imports surged 17.6% as CEA-monitored plants offset weaker CIL and SCCL…
View more

California Forecasts 61% Electricity Demand Growth by 2045

A new California Energy Commission forecast projects a 61 percent rise in electricity demand by…
View more

Daimler Details Gigantic Scope of Its Electrification Plan

Daimler Electric Strategy drives EV adoption with global battery factories, Mercedes-Benz electrified models, battery cells…
View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Live Online & In-person Group Training

Advantages To Instructor-Led Training – Instructor-Led Course, Customized Training, Multiple Locations, Economical, CEU Credits, Course Discounts.

Request For Quotation

Whether you would prefer Live Online or In-Person instruction, our electrical training courses can be tailored to meet your company's specific requirements and delivered to your employees in one location or at various locations.