UK looking to speed up renewable power connections


Substation Relay Protection Training

Our customized live online or in‑person group training can be delivered to your staff at your location.

  • Live Online
  • 12 hours Instructor-led
  • Group Training Available
Regular Price:
$699
Coupon Price:
$599
Reserve Your Seat Today

UK grid access reform aims to clear a 60 GW connection queue, prioritizing renewables and wind farms via Connect and Manage models, investor certainty, and faster Ofgem-approved timelines to accelerate low-carbon generation.

 

In This Story

A UK policy replacing first-come grid queues with Connect and Manage models, speeding renewable and wind connections.

  • 60 GW, ~200 projects, await national grid connection.
  • 17 GW from renewables stuck under first-come scheduling.
  • Three Connect and Manage options shift cost and risk.
  • Ofgem interim steps already advanced 1 GW in Scotland.

 

The UK government is promising to speed up the connection of renewable power to the national power grid with the launch of a new consultation process that will change how power plants are connected to the grid.

 

Problems are particularly felt by windfarm developers, which can wait years before being able to transmit power to the grid. The government recognized that currently more than 60 gigawatts (GW) of new generation capacity — about 200 projects — are waiting in a backlog to be connected to the national grid, including about 17 GW from renewable sources.

The existing system works on a 'first-come, first-served' basis in regards to grid connection, regardless of when the project will start generating energy. This has meant that some windfarms have been given, in what amounts to a bumpy ride for renewables, connection dates many years after they plan to start producing electricity. The new consultation is giving energy companies a say on three potential new models. These include:

• Connect and Manage (Socialised): Costs will be shared between all users of the network;

• Connect and Manage (Hybrid): A model that targets some, but not all, of the additional constraint costs on new-entrant power stations;

• Connect and Manage (Shared Cost and Commitment): A model that offers the choice to new and existing power stations to commit to the network (which is helpful to the grid in terms of long-term management of the system) in return for greater certainty regarding charges, or to opt out of a commitment, facing exposure to additional costs.

The proposed scheme is also designed to reassure potential investors in windfarms, including those awaiting the go-ahead for offshore wind projects, that projects will be given a connection date that fits in with a project's developmental timeline.

"Access to the electricity grid has been one of the key barriers to the generation of renewable energy in this country," admitted Energy and Climate Secretary Ed Miliband. "We are determined to resolve this issue. That is why we took powers to do so in the Energy Act, and today we are setting out our proposals. We need these new projects to get hooked up to the grid as soon as they are ready — both to help move closer to green goals and secure our future energy supplies."

Miliband added, "The government will do whatever is necessary to bring about the transition to a low-carbon economy, including an offshore wind boost to build momentum, and to give investors the certainty they need so that new renewable energy generation is built."

Energy regulator Ofgem has already approved interim arrangements to help new power stations connect more quickly as European power focuses on offshore wind in parallel. About 1 GW of renewable projects in Scotland have already been offered earlier connection dates. Now, however, the government is hoping to make faster connection a reality by introducing the new system by next June.

Related News

KHNP is being considered for Bulgarian Nuclear Power Plant Project

KHNP Shortlisted for Belene Nuclear Power Plant, named by the Bulgarian Energy Ministry alongside Rosatom…
View more

Iraq plans nuclear power plants to tackle electricity shortage

Iraq Nuclear Power Plan targets eight reactors and 11 GW to ease blackouts, curb emissions,…
View more

Volkswagen's German Plant Closures

VW Germany Plant Closures For EV Shift signal a strategic realignment toward electric vehicles, sustainability,…
View more

NL Consumer Advocate says 18% electricity rate hike 'unacceptable'

Newfoundland and Labrador electricity rate hike examines a proposed 18.6% increase under the PUB's Rate…
View more

Lack of energy: Ottawa’s electricity consumption drops 10 per cent during pandemic

Ottawa Electricity Consumption Drop reflects COVID-19 impacts, with Hydro Ottawa and IESO reporting 10-12% lower…
View more

Blackout-Prone California Is Exporting Its Energy Policies To Western States, Electricity Will Become More Costly And Unreliable

California Blackouts expose grid reliability risks as PG&E deenergizes lines during high winds. Mandated solar…
View more

Sign Up for Electricity Forum’s Newsletter

Stay informed with our FREE Newsletter — get the latest news, breakthrough technologies, and expert insights, delivered straight to your inbox.

Electricity Today T&D Magazine Subscribe for FREE

Stay informed with the latest T&D policies and technologies.
  • Timely insights from industry experts
  • Practical solutions T&D engineers
  • Free access to every issue

Download the 2026 Electrical Training Catalog

Explore 50+ live, expert-led electrical training courses –

  • Interactive
  • Flexible
  • CEU-cerified